1 / 16

WRAC Acme Basin B Discharge Project February 2, 2006

WRAC Acme Basin B Discharge Project February 2, 2006. Everglades Restoration Acceler8 Projects. C-43 (Caloosahatchee River) West Reservoir EAA Reservoir Phase 1 / Boles & Cross Canals EAA Stormwater Treatment Area Expansion Picayune Strand (Southern Golden Gate Estates)

berne
Download Presentation

WRAC Acme Basin B Discharge Project February 2, 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WRAC Acme Basin B Discharge Project February 2, 2006

  2. Everglades Restoration Acceler8 Projects • C-43 (Caloosahatchee River) West Reservoir • EAA Reservoir Phase 1 / Boles & Cross Canals • EAA Stormwater Treatment Area Expansion • Picayune Strand (Southern Golden Gate Estates) • C-44 (St. Lucie Canal) Reservoir / STA • Water Preserve Areas • Acme Basin B Discharge Project • Site 1 Impoundment • C-9 Impoundment • C-11 Impoundment • WCA-3A/3B Seepage Management • Biscayne Bay Coastal Wetlands Phase 1 • C-111 Spreader Canal

  3. Acme Basin B Discharge ProjectLocation

  4. Acme Basin B Discharge Project Current Conditions S-319 PUMP #4 C-51 CANAL PUMP #3 PUMP #6 Southern Blvd. S-155A C-1 BASIN A STA-1E S-361 40 72 42 73 45 44 SECTION 24 S-362 BASIN B WCA-1 LOXAHATCHEE NATIONALWILDLIFE REFUGE PUMP #1 PUMP #2

  5. Acme Basin B Discharge Project Project Purpose The Everglades Forever Act requires that all discharges to the Everglades Protection Area must meet water quality standards by December 31, 2006. Acme Pumps #1 and #2 currently discharge stormwater runoff from Acme Basin B directly into the Arthur R. Marshall Loxahatchee Wildlife Refuge (Refuge), part of the Everglades Protection Area. The purpose of the Acme Basin B Discharge Project is to divert stormwater runoff from Acme Basin B to the C-51 West Canal and then to STA-1E for treatment prior to discharge to the Refuge. Excess available water may be used to meet water supply demands in central and southern Palm Beach County.

  6. Acme Basin B Discharge Project Project Purpose Requires: • Improvements to C-1 canal to increase conveyance capacity and connect the C-1 canal to the C-51 Canal • Construction of new pump station AcmePS7 to pump from C-1 canal into C-51 Canal • Construction of detention area in Section 24 for temporary offline storage • Construction of new pump station AcmePS24 to fill the Section 24 detention area

  7. Acme Basin B Discharge Project Project Features S-319 PUMP #4 C-51 CANAL PUMP #3 PUMP #6 Southern Blvd. S-155A NEW PUMP #7 (220 cfs) BASIN A STA-1E C-1 CANAL S-361 PUMP #8 40 SEC 24 NEW PUMP #24 (200 cfs) S-362 BASIN B WCA-1 LOXAHATCHEE NATIONALWILDLIFE REFUGE PUMP #1 PUMP #2

  8. Acme Basin B Discharge Project C-1 Canal Improvements and AcmePS7 • C-1 Canal Improvements • 3 miles of modified section for 67 to 220 cfs conveyance capacity • Two 84” culverts at FPL crossing • Meets DOT setback requirements for Flying Cow Road • Pump Station AcmePS7 • Connects C-1 to C-51 canal • 220 cfs (three 110 cfs pumps) • Diesel • Includes gravity discharge bay

  9. Acme Basin B Discharge Project Section 24 and AcmePS24 • Section 24 • Converts 365 acres of agricultural land to impoundment with upland areas and tree islands • Storage of up to 5 feet of water (1,028 ac-ft) • Two gated culverts (100 cfs each) for inflow/outflow • Pump Station AcmePS24 • Inflow pump station • 200 cfs (three 100 cfs pumps) • Diesel

  10. Section 24 with additional recreational components

  11. Acme Basin B Discharge Project Project Benefits • C-1 canal improvements and pump station AcmePS7 • Allows Basin B water to be conveyed to the C-51 canal and STA-1E • Section 24 and AcmePS24 • Provides temporary offline storage of 1,028 ac-ft of water • Maintains flood protection in Acme Basin B • Reduces phosphorous load to C-51 canal / STA-1E • Potential water supply • Provides a buffer between natural and developed areas • Converts 365 acres of agricultural land to upland and open water habitat • Provides recreational opportunities • Walking trails, overlooks, equestrian trails

  12. Required C-1 Canal modifications are less than BODR Modeling indicates that 220 cfs is not needed along entire length – flow incrementally increases from 67 cfs at Structure #40 to 220 cfs at AcmePS7 Realignment of Flying Cow Road minimized by using curb & gutter, guardrail, and steeper canal slopes Reduces cost AcmePS7 was moved 1,000 ft south from C-51 canal to near FPL crossing Moves pump station away from residences AcmePS7 equipped with gravity discharge bay Reduces cost of operation Pump stations will be diesel not electric To meet District standards Section 24 primary purpose changed from passive wetland to detention area Maintains flood attenuation and level of service locally and in the C-51 Canal Temporary storage provides regional benefits Reduces phosphorus load to C-51 Canal / STA-1E Section 24 seepage canal added Protects against groundwater mounding Acme Basin B Discharge Project Design Modifications After BODR / August 2005 Workshop

  13. Acme Basin B Discharge ProjectSchedule Planning and BODR complete Sept 2005 C-1 Canal and AcmePS7 Design complete February 2006 Procurement complete April 2006 Construction complete Nov 2006 Planning and BODR complete Sept 2005 Section 24 and AcmePS24 Design complete March 2006 Procurement complete May 2006 Construction Phase 1 operational Dec 2006 Phase 2 (landscaping, recreational) complete May 2007 2004 2005 2006 2007 2008 Timeline – Calendar Years

  14. Acme Basin B Discharge ProjectOpinion of Probable Cost C-1 Canal $1.4M AcmePS7 $4.2M Sec 24 $6.3M AcmePS24 $3.8M Design and Admin $2.6M SUBTOTAL $18.3M Sec 24 Recreation $1.0M* Sec 24 Real Estate $4.1M TOTAL $23.4M * = alternate funding sources

  15. Acme Basin B Discharge Project Questions? S-319 PUMP #4 C-51 CANAL PUMP #3 PUMP #6 Southern Blvd. S-155A NEW PUMP #7 (220 cfs) BASIN A STA-1E C-1 CANAL S-361 PUMP #8 40 SEC 24 NEW PUMP #24 (200 cfs) S-362 BASIN B WCA-1 LOXAHATCHEE NATIONALWILDLIFE REFUGE PUMP #1 PUMP #2

More Related