160 likes | 284 Views
WRAC Issues Workshop Acme Basin B Discharge Project Wellington Community Center January 23, 2006. Everglades Restoration Acceler8 Projects. C-43 (Caloosahatchee River) West Reservoir EAA Reservoir Phase 1 / Boles & Cross Canals EAA Stormwater Treatment Area Expansion
E N D
WRAC Issues Workshop Acme Basin B Discharge Project Wellington Community Center January 23, 2006
Everglades Restoration Acceler8 Projects • C-43 (Caloosahatchee River) West Reservoir • EAA Reservoir Phase 1 / Boles & Cross Canals • EAA Stormwater Treatment Area Expansion • Picayune Strand (Southern Golden Gate Estates) • C-44 (St. Lucie Canal) Reservoir / STA • Water Preserve Areas • Acme Basin B Discharge Project • Site 1 Impoundment • C-9 Impoundment • C-11 Impoundment • WCA-3A/3B Seepage Management • Biscayne Bay Coastal Wetlands Phase 1 • C-111 Spreader Canal
Acme Basin B Discharge Project Current Conditions S-319 PUMP #4 C-51 CANAL PUMP #3 PUMP #6 Southern Blvd. S-155A C-1 BASIN A STA-1E S-361 40 72 42 73 45 44 SECTION 24 S-362 BASIN B WCA-1 LOXAHATCHEE NATIONALWILDLIFE REFUGE PUMP #1 PUMP #2
Acme Basin B Discharge ProjectThe Problem with Current Conditions Acme Basin B Phosphorous Discharges Flow-Weighted Mean Concentration, WY02 (May 1, 2001 through April 30, 2002) Source: 2003 Everglades Consolidated Report, Chapter 8B: Everglades Stormwater Program
Acme Basin B Discharge Project Project Purpose Acme Pumps #1 and #2 must be shut down on December 31, 2006 to comply with the Everglades Forever Act. Water in Acme Basin B must be re-routed north through Acme Basin A and discharged into the C-51 canal. Requires: • Improvements to C-1 canal to increase conveyance capacity and connect the C-1 canal to the C-51 Canal • Construction of new pump station AcmePS7 to pump from C-1 canal into C-51 Canal • Construction of detention area in Section 24 for temporary offline storage • Construction of new pump station AcmePS24 to fill the Section 24 detention area
Acme Basin B Discharge Project Project Features S-319 PUMP #4 C-51 CANAL PUMP #3 PUMP #6 Southern Blvd. S-155A NEW PUMP #7 (220 cfs) BASIN A STA-1E C-1 CANAL S-361 PUMP #8 40 SEC 24 NEW PUMP #24 (200 cfs) S-362 BASIN B WCA-1 LOXAHATCHEE NATIONALWILDLIFE REFUGE PUMP #1 PUMP #2
Acme Basin B Discharge Project C-1 Canal Improvements and AcmePS7 • C-1 Canal Improvements • 3 miles of modified section for 67 to 220 cfs conveyance capacity • Two 84” culverts at FPL crossing • Meets DOT setback requirements for Flying Cow Road • Pump Station AcmePS7 • Connects C-1 to C-51 canal • 220 cfs (three 110 cfs pumps) • Diesel • Includes gravity discharge bay
Acme Basin B Discharge Project Section 24 and AcmePS24 • Section 24 • Converts 365 acres of agricultural land to impoundment with upland areas and tree islands • Storage of up to 5 feet of water (1,028 ac-ft) • Two gated culverts (100 cfs each) for inflow/outflow • Pump Station AcmePS24 • Inflow pump station • 200 cfs (three 100 cfs pumps) • Diesel
Section 24 with additional recreational components
Acme Basin B Discharge Project Project Benefits • C-1 canal improvements and pump station AcmePS7 • Allows Basin B water to be conveyed to the C-51 canal and STA-1E • Section 24 and AcmePS24 • Provides temporary offline storage of 1,028 ac-ft of water • Maintains flood protection in Acme Basin B • Reduces phosphorous load to C-51 canal / STA-1E • Potential water supply • Provides a buffer between natural and developed areas • Converts 365 acres of agricultural land to upland and open water habitat • Provides recreational opportunities • Walking trails, overlooks, equestrian trails
Required C-1 Canal modifications are less than BODR Modeling indicates that 220 cfs is not needed along entire length – flow incrementally increases from 67 cfs at Structure #40 to 220 cfs at AcmePS7 Realignment of Flying Cow Road minimized by using curb & gutter, guardrail, and steeper canal slopes Reduces cost AcmePS7 was moved 1,000 ft south from C-51 canal to near FPL crossing Moves pump station away from residences AcmePS7 equipped with gravity discharge bay Reduces cost of operation Pump stations will be diesel not electric To meet District standards Section 24 primary purpose changed from passive wetland to detention area Maintains flood attenuation and level of service locally and in the C-51 Canal Temporary storage provides regional benefits Reduces phosphorus load to C-51 Canal / STA-1E Section 24 seepage canal added Protects against groundwater mounding Acme Basin B Discharge Project Design Modifications After BODR / August 2005 Workshop
Acme Basin B Discharge ProjectSchedule Planning and BODR complete Sept 2005 C-1 Canal and AcmePS7 Design complete February 2006 Procurement complete April 2006 Construction complete Nov 2006 Planning and BODR complete Sept 2005 Section 24 and AcmePS24 Design complete March 2006 Procurement complete May 2006 Construction Phase 1 operational Dec 2006 Phase 2 (landscaping, recreational) complete May 2007 2004 2005 2006 2007 2008 Timeline – Calendar Years
Acme Basin B Discharge ProjectOpinion of Probable Cost C-1 Canal $1.4M AcmePS7 $4.2M Sec 24 $6.3M AcmePS24 $3.8M Design and Admin $2.6M SUBTOTAL $18.3M Sec 24 Recreation $1.0M* Sec 24 Real Estate $4.1M TOTAL $23.4M * = alternate funding sources
Acme Basin B Discharge Project Questions? S-319 PUMP #4 C-51 CANAL PUMP #3 PUMP #6 Southern Blvd. S-155A NEW PUMP #7 (220 cfs) BASIN A STA-1E C-1 CANAL S-361 PUMP #8 40 SEC 24 NEW PUMP #24 (200 cfs) S-362 BASIN B WCA-1 LOXAHATCHEE NATIONALWILDLIFE REFUGE PUMP #1 PUMP #2