ILC. CFS update for Europe. J.Osborne / A.Kosmicki / B.List – March 22 th 2012. TDR progress for Klycluster Scheme on the CERN Site. Several machine lattice files received from DESY EDMS (Benno List) February 2012

bette
Download Presentation

ILC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ILC CFS update for Europe J.Osborne / A.Kosmicki/ B.List – March 22th2012

  2. TDR progress for Klycluster Scheme on the CERN Site • Several machine lattice files received from DESY EDMS (Benno List) February 2012 • CERN draughtsman (Antoine Kosmicki) has spent 2 weeks putting these files together in order to generate a 3d model for the 500GeV machine • Using this 3d model and Autocad files from FNAL for Kycluster scheme, an attempt has been made to size the underground enclosures, optimised for the CERN geology. • Once ‘approved’ this new civil engineering layout will be costed by AMBERG Engineering (same company costed RDR for Europe, CLIC and also works on XFEL) • Interaction Region Studies by ARUP for CERN site are now finished. Final report today.

  3. Only e- side fully modeled (Positron Source). Impossible to model the entire machine in CATIA, which is ‘limited’ to 15km. Local co-ordinate systems needs to be created to have the entire machine into one model. ILC Project

  4. Damping ring Main cavern

  5. ∅ 14.00 x 22m 17 Damping ring Jonction cavern Interaction point (I.P.) Where X,Y,Z = 0 Service tunnel ∅4.5m ∅ 6.00 x 270m PLTR 16 ∅ 7.00 x 965m 5 ∅ 12.00 x 60m 4 ∅ 7.00 x 173m 3 ∅ 6.00 x 82m 2 Experimental caverns Positron Source / Electron BDS side (negative Z direction) ∅ 5.20 x 68m 1

  6. Damping ring Jonction cavern Service tunnel ∅4.5m PLTR Transfer tunnel between main tunnel & damping ring ERTML dump Jonction cavern

  7. e- Tune-Up Dump e+ 5GeV Boosters Service tunnel ∅4.5m e- RTML ∅ 8.00 x 130m 7 ∅ 7.00 x 965m ∅ 10.00 x 75m 6 5 e- BDS Water Tank Beam direction =

  8. Service tunnel ∅4.5m Positron Capture Chicane Traveling Wave Accelerator IP

  9. E- Fast Abort Dump Cavern Service tunnel ∅4.5m e- Fast Abort Dump Helical undulator ∅ 6.00 x 120m ∅ 6.00 x 200m 14 ∅ 5.20 x 1388m 15 13

  10. Photon Dump Cavern Service tunnel ∅4.5m ∅ 8.00 x 96m ∅ 5.20 x 467m 10 ∅ 5.20 x 242m 11 9

  11. Target bypass ‘dog-leg’ area Service tunnel ∅4.5m e- RTML ∅ 6.00 x 45m ∅ 5.20 x 242m 12 ∅ 6.00 x 200m 13 11

  12. Undulator Area Positron source targetwith remote handling area: Needs shaft and hall! Positron Capture Chicane IP

  13. 4’282’527MM from IP Shaft PM-7 ∅14m Base Cavern US-7 Service tunnel should continue to this shaft ? ∅ 5.20 x 1388m 15 ∅ 5.20 x 1388m 15 Undulator area

  14. Concerns half of the project (circled area) BUT NOT MAIN LINAC ?? 6 7 8 BDS tunnel optimized to 8m diameter for CERN GEOLGY 9 ILC Project general view 10 11 12 13 14 17 16 15 1 3 2 4 5

  15. Complexity of tunnel works ILC Experimental Caverns Damping ring Waveguides between service tunnel and BDS ? ILC Project general view

  16. Complexity of tunnel works Now five shafts at the IR ILC Project general view ILC Experimental Caverns

  17. ILC Project general view

  18. Damping ring Service tunnel goes up and over the transfer lines ILC Project general view

  19. PLTR / BDS Junction Cavern

  20. Damping Ring PLTR Bypass to damping ring

  21. e- RTML PLTR Transport zone

  22. Typical Main Linac Cross Section for Klycluster Scheme on the CERN Site 1153mm Beam to floor = 1100m

  23. Most important drawing for CFS costing : Needs checking !

  24. CERN TDR efforts for Klycluster Scheme… Next Steps • These layouts will be used for ILC Europe civil engineering costing purposes and for : • Europe Scheduling exercise (Martin Gastal & Katy Foraz) • Handling & Installation studies (Keith Kershaw) • Survey & Alignment (Helene Mainaud Durand) • Safety requirements (Fabio Corsanego) • Exact Scope of what is to included in these chapters needs to be defined. • Environmental Impact Studies are ongoing for a LC at CERN (with the help of a technical student Caroline Waaijer).

  25. BACK-UP SLIDES

  26. STEP file imported into Catia from DESY to CERN thru EDMS (Courtesy of Benno List and Don Mitchell) Even such large models can now be downloaded and put in other 3D programs

  27. Just like in the LHC UJ22 cavern, The magnets will have to be lifted Over the beam lines

  28. Environmental Impact Assessment (EIA) • Required by French and Swiss law • Feasibility issue • 3 phases • Screening: establish necessity for EIA ( ) • Scoping: conduct EIA • Review: before submission • Required knowledge • Legal framework • Policies & decision-making • Engineering • Environmental impact criteria • Biophysical, socio-cultural, socio-economical

  29. Environmental Impact Assessment • Major issues for ILC: • Civil Engineering • Excavations, spoil dumps, soil swelling, hydrology, release pollutants geothermal drillings, hydrocarbons, visual impact… • Energy consumption • Focus on renewable & sustainable energy • Water consumption • Where discharged? • Focus on renewable & sustainable energy • Social acceptance • Impacts during and after constructions, fear • Waste • Radiation Feasibility threats

  30. Environmental Impact Assessment • Next steps • Planning • Task division • cost estimates EIA • Land acquisition • Start • Work together with Swiss / French authorities • In-depth studies • Identify knowledge gaps • Address feasibility threats