1 / 6

ERCOT System Development Update

This update covers CREZ Generation Full Interconnection Studies, RPG Project Review, and Five-Year Transmission Plan Update. It discusses projects on hold, moratorium details, and future processes. It also presents ongoing project reviews and updates.

bgaither
Download Presentation

ERCOT System Development Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT System Development Update Jeff Billo RPG Meeting

  2. Topics CREZ Generation Full Interconnection Studies RPG Project Review Update Five-Year Transmission Plan Update RPG Meeting

  3. CREZ GINR FIS Background Since August 2007 ERCOT has put on hold generation full interconnection study (FIS) requests for projects that will interconnect to “CREZ” transmission facilities Currently there are 14 studies on hold and 5 studies that would have been on hold had the moratorium started before August 2007 The Process Going Forward ERCOT will remove generation projects from being on hold once both of the following conditions are met: The project’s interconnecting TSP has been identified by the PUCT final order in docket 35665 The project’s interconnecting TSP has a code of conduct in place at the PUCT RPG Meeting

  4. RPG Project Review Update Acceptance Letter in process for: LCRA TSC Flatonia-Yoakum Project (Tier 3) ERCOT Independent Review of the Austin Energy Decker to Techridge 138 kV Circuit Relocation Project (Tier 2) is underway ERCOT Independent Review of the LCRA TSC Cushman-Highway 123 Project (Tier 2) has just begun LCRA TSC GPI-FM482-Parkway Project (Tier 2) is in Study Mode Centerpoint 2012 Northwest Houston Reliability Project (Tier 2) is in the Comment Period Comments on Sharyland ERCOT Southeast Loop Project (Tier 1) appear to be irresolvable by the RPG. ERCOT will take the comments into account as we perform the Independent Review RPG Meeting

  5. 2009 Five-Year Transmission Plan Update Currently working on case conditioning and converting case to UPLAN RPG Meeting

  6. Questions? RPG Meeting

More Related