180 likes | 195 Views
This document outlines the status of the LCLS project management, including baseline changes, cost growth, risk management, integration, and contingency allocation. It covers procurement, installation, commissioning, and contingency analysis.
E N D
DOE Review of the LCLS Project Status of Project Management M. Reichanadter LCLS Deputy Project Director
Outline • Baseline Changes and Documentation • Managing Cost Growth • Risk Identification and Management • SLAC Management Oversight and Support • Procurement Management • Integration, Installation & Commissioning • Summary
Contingency Allocation to Date • Majority of contingency allocation is in CF. • CF baseline – Title I design, parametric cost estimate. Stable since August 2006
TEC Contingency Performance • Steady, consistent rise in project % complete. • Recent downturn due to CR. • Two dips in contingency% • 30% T2 Cost Estimate • Subcontract Bids • Apr07 Pending BCR’s • $630K - UN CT Install • $198K - Dump Shielding • $287K - Turner 2nd shift • PBCR’s are included in EAC calculation.
Continuing Resolution ETC @ System Level • Supporting details are included in backup documentation
Contingency Assessment • ~10% reserved for awarded contracts • ~25% contingency on commitments to go. • Greatest cost risk • Design, Assemble, Test • Install, Construct
Monte Carlo Contingency Analysis • Monte Carlo analysis • Uniform probability distribution for each level 2 WBS element • lower bound of 1X baseline cost estimate • upper bound of 1.40 x (bottoms-up contingency assessment) • Equivalent to 60% probability that actual cost is below the bottoms-up cost+contingency • Analysis provides that project can be completed for a TEC = $339M with a 90% confidence level.
Contingency reserve on construction • Recent DOE construction contingency experience • ORNL – Spallation Neutron Source • 5.7% - Errors, Omissions & Site Conditions • 18.0% - Owner directed changes • LBNL – Molecular Foundry • 4.7% - Errors, Omissions & Site Conditions • 4.8% - Owner directed changes (late in the game) • SLAC – Linac Coherent Light Source • 10% - Contingency reserved for remaining construction • 4% - Experience to date on construction accomplished • LCLS “Owner” Changes are anticipated to be small. • Design is ~stable. Scope is ~fixed.
Risk Identification & Management • LCLS Senior Management reviews risks monthly. • Add/retire risks, evaluate handling plans • Risks are ‘owned’ by LCLS System Managers. • Uniformity in assessing risks across the project • Better execution of resources (FTE’s & $$$) to handle the risks. • High risk items factored into LCLS contingency and EAC.
Risk registry identifies key project risks • LCLS Risk Registry is in backup documentation.
Procurement Status • Procurement Planning & Acquisition • ~85% of LCLS procurements awarded • LUSI just ramping up, using LCLS ‘cell’ • Weekly LCLS/LUSI Procurement Status Meeting • Track APPs, Procurements in Process • Report on FCOs, CORs, Negotiations • Recently added DOE Tracking Log • Procurement Issues • New LCLS Procurement Manager • Procurement Team relies heavily on consultants • LCLS ramping down, competition from other projects • SLAC recognizes need to recruit high-quality procurement professionals • Long-term strategic issue for SLAC. LCLS working with BSD.
SLAC Management & Oversight • Good interaction between LCLS and SLAC Management • Twice weekly with SLAC Management (DOE FPD/DFPD included) • Status/check-off, coordination, emerging issues • SLAC management involved in high-level Turner partnering • SLAC management’s ‘gang of five’ includes LCLS PD (Galayda) • PMOG reports to SLAC Director • Regular (monthly) interaction w/project • Conducted installation readiness review, help on vacuum chamber, etc. • Transition to Ops is being worked in close collaboration w/LCLS • SLAC resources support LCLS programmatic space renovation • Project striving to maintain flexibility on endgame • SLAC Director briefings to lab management (including LCLS) • Consultant interviewing key managers and programs/projects • See Galayda talk on transition to ops
Integration, Installation & Commissioning • Integration Mgmt Team facilitates installation tasks • Directed by RM Boyce (staff of 6) • Centrally coordinates installation readiness & planning • Review and ‘own’ ICD’s, Gaps, Conflicts • CF-Tech leads for construction • Revised cost and schedule consistent with plans for installation, commissioning and transition to ops • L4, hardware RFI milestones tracked to monitor float • Track status in weekly installation meetings (RMB talk) • Use completion milestones to transition to operations • Start-Up plan (in rev) describes commissioning steps
Summary • Contingency allocation in CF has been stable since Aug06. • Significant portion of remaining work is under contract. • Remaining cost risk will be in design, testing and assembly (labor costs) and installation contracts. • Contingency is considered adequate to address the project’s risks for the remainder of the project. • Project risks are evaluated monthly at the tactical level in the LCLS Risk Registry. • ~85% of all LCLS procurements are awarded. • Installation and uncertainties on LCLS transition to operations will be developed in the near-term.
LCLS Technical Specifications • Photon Systems beginning to finalize its design specs • QA Mgr working monitoring dates for PRD’s and ESD’s • Setting up Group to manage LCLS-LUSI Interface