1 / 10

Tracker Status Report

Tracker Status Report. 4 Station Prototype Software AFEII work at Fermilab Calibration and cosmic ray test at Fermilab Setup at KEK Plans. 4 Station Prototype. New station built to revised design: 427 m m fibre pitch Improved optical connectors Internal waveguide for patch panel

Download Presentation

Tracker Status Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tracker Status Report • 4 Station Prototype • Software • AFEII work at Fermilab • Calibration and cosmic ray test at Fermilab • Setup at KEK • Plans M. Ellis 14th September 2005

  2. 4 Station Prototype • New station built to revised design: • 427 mm fibre pitch • Improved optical connectors • Internal waveguide for patch panel • Original three stations and new station assembled into a new tracker at Imperial. • CMM measurements made of station position before tracker was made light-tight and shipped to Fermilab. M. Ellis 14th September 2005

  3. M. Ellis 14th September 2005

  4. Software • DAQ • UniDAQ used for KEK test. ADCs and TDCs read out in the same manner as for the May test. • Code to read out VLSB modules originally developed as a standalone application, now being imported into UniDAQ • Analysis • G4MICE being used for all analysis • Preparation of monitoring application underway. • More detail in talks at Tracker/DAQ and software meetings. M. Ellis 14th September 2005

  5. AFEII Work • AFEII prototype boards have been developed and tested at Fermilab. • Improved design beyond AFEI (currently used by D0) and a step along the path towards AFEII-t. • Successfully operated four AFE boards (2048 channels) in a MICE cryostat at D0 performing calibrations and recording cosmic ray events from the tracker. M. Ellis 14th September 2005

  6. Fermilab Setup M. Ellis 14th September 2005

  7. Calibration and Cosmic Rays • Calibration performed using an LED. • Can control duration of pulse and intensity to produce a sample with pedestal and one and two PE peaks or increase light to look at many PE. • After calibration, the tracker was connected to the VLPC cassettes and 3606 cosmic ray triggers were recorded. • This data is still being analysed. M. Ellis 14th September 2005

  8. VLPC/AFE Performance Reconstructed with G4MICE M. Ellis 14th September 2005

  9. Setup at KEK • Cryostat, Tracker, etc have been shipped to KEK and setup there. • Cryostat/Cryocooler is performing well. • Avnet board has failed and is being returned to Fermilab for repairs. We have two spares, so this will not cause any problem. • Spare AFEII boards and other equipment will be sent to KEK with D0 experts. M. Ellis 14th September 2005

  10. Plans • 21st September • Place BESS magnet in area • Tracker/VLPC system installed • 27th September • Accelerator tuning • D0 experts arrive and complete testing and setup of VLPC system • 30th September • Planned start of good beam. • May be delayed by 3 or 4 days. • We have 20 shifts (8 hours each) from the start of good beam. M. Ellis 14th September 2005

More Related