150 likes | 242 Views
Strip Tracker Costing Analysis Status. Carl Haber July 25, 2011. Overview. Can mainly derive a costing framework here Only consider CORE Will depend upon eventual layout, and CHF/item Seek a framework which can be easily adapted to layout variations and new assumptions
E N D
Strip Tracker Costing AnalysisStatus Carl Haber July 25, 2011
Overview • Can mainly derive a costing framework here • Only consider CORE • Will depend upon eventual layout, and CHF/item • Seek a framework which can be easily adapted to layout variations and new assumptions • Key inputs include costs and yield estimates • Yields based upon SCT/Pixel experience • Yields based upon present R&D experience • Yields based upon cost = specifications • Other options • Industrialization • Number of sites/task: efficiency vs. activity
Costing History • See USG 6/2011 presentation from Phil • A.Clark: attempt at bottom-up for Utopia • M. Tyndel: parametric based upon SCT • S.McMahon: rationalized MT analysis • But all were influenced by SCT experience • Itemized comparison not possible in general due to differing methodology • Similar conclusions for total cost based upon very different internal assumptions
Are there important differences as compared to SCT? • ASICs will have (at least) 256 channels and are smaller • Much less internal cabling, buses for TTC and power • No TPG heat spreaders • Hybrids will be panelized for mass production, assembly, and test • Barrel support structures will be simpler since we do not need to mount modules nor dress cooling and cables • There will be no discs upon which modules are mounted, only support rings/struts for petals • Overall cost may dictate that work is broken down by item rather than site – economy of scale advantages (?)
Previous Costings (Core) • SCT: 45 MCH • M. Tyndel SCT scaled: 150 MCHF • S. McMahon: rationalized: 80 MCHF • A. Clark analysis: 70 MCHF • Most detailed, but a bit hard to follow • Expresses total module cost rather than breaking out items as they will be procured • ASICs types and counts need to be updated • Mechanical support, stave core not handled
Components • Stave Core • Facings: bulk material, cut to shape • Foam: critical patterning and gluing operation • Pipe assembly: forming and pressure certification • Edges: machining? • Bus tapes: commercial order, critical QA aspect to maintain yield of stave • Module • Sensor: pre-spec’d from vendor, loss due to handling damage • Hybrid • Substrate: commercial mfg, loss in parts mount, test • ABCn130 • HCC/DCS • PPC • Discretes • End-of-Stave: critical reliability aspect • Substrate: commercial mfg, loss in parts mount, test • ASICS • Discretes • Connectors/cables: potential high cost, critical reliability aspect
Complete staves Cores ready to load modules ready for staves EOS facings discrt sensors foam chips hybrids pipes discrt edges Bus tapes chips
Inputs • Sensor costs (N.Unno): • Strip: 70 KCHF per wafer type and 1100 CHF per piece/wafer • Strip ASIC {note: chip numbers in USG 6/11 not correct) • (ABCn130) costs (P. Farthouat):163K good die: 440 wafers = 1.55MUSD , NRE = 0.5 MUSD = 1.64 MCHF = 10 CHF/good ABCn130 (Prototype cost : 2 times NRE = 1 MUSD) • HCC, PPC, GBT • Hybrids • Stave cores and tapes
Stave/Petal Core Mechanical/Tapes • CF facing material • K13D2U, 65 grams/m2., 52 KCHF/22 Kg = 2.36 KCHF/Kg • 1 stave requires 6 x 0.120 m x 1.3 m x 1.5 (excess) = 1.4m2 x 65 = .091 Kg • 2.36 x 0.091 = 215 CHF/stave • Foam • 960 CHF ($1200) per 1’x1’x1” block = 2400 cm3 • X2 loss factor • 1 stave = 714 cm3: x 2 = 1430; (1430/2400)*960= 572 CHF • Pipe: 3 m/stave • Stainless steel negligable • Titanium: 61 CHF/m: 184 CHF/stave • Edge tube/C-channels: negligable • Bus tapes: 2@320 CHF each = 640 CHF/stave • Total: 215 + 572 + 184 + 640 = 1611 CHF/stave • 521 staves * 1611 = 840 KCH • Petal system area is about 40% of barrel: ~350 KCH
Example Estimate • Barrel stave • Core only • No setup costs, tooling, NRE • No engineering, prototyping, pre-production • No assembly, inspection, QA, or test equipment
Global Supports Comments • Not included in estimate presented here, but, • Barrels for staves, frames for petals • Barrel is conceptually similar to SCT so OK to cost by scaling and inflation, but much simpler since no dressing • BNL analysis: 1.8 MCHF • A.Clark analysis: 3 MCHF • Forward disc substrate is now gone and replaced by • Petal cores, now costed as part of cores • Support rings/frames, in principle (?) a more complicated fabrication than a thin barrel (?) not clear how to cost this • A. Clark analysis: 4.6 MCHF, seems too high… • Parametric (S.M./M.T.) analysis based on SCT concluded that these supports would total 21 MCH! Clearly too large.
Comments • Any new numbers presented here are preliminary and need to be checked further • Fairly transparent structure for costing in an itemized and yield based manner • Will extend to the disc system • Need to look critically at the off stave cable and interconnect costs, off detector electronics • Mechanical engineering aspects, outside the stave, are clearly a key area for study