1 / 16

High Performance Public Buildings

High Performance Public Buildings. Proposed Final Report Joint Legislative Audit & Review Committee June 23, 2011 Mark Fleming, JLARC Staff. Overview of Audit Results. High performance requirements add 1 to 3 percent to public building design and construction costs

blythe
Download Presentation

High Performance Public Buildings

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. High Performance Public Buildings Proposed Final Report Joint Legislative Audit & Review Committee June 23, 2011 Mark Fleming, JLARC Staff

  2. Overview of Audit Results • High performance requirements add 1 to 3 percent to public building design and construction costs • High performance building energy efficiency is mixed • Lack of data and methodology issues limit evaluation of building performance • Definitive conclusion is premature High Performance Public Buildings

  3. Public Buildings Must Meet High Performance Standards • Required by ESSB 5509 (2005) to: • Promote efficient use of energy and other resources; and • Create productive learning and working environments for occupants • Legislation establishes reporting requirements • Legislature intended to monitor results Report Pages 3-6 High Performance Public Buildings

  4. 274 Projects as of June 2010 274 Total projects 90 projects 176 Incomplete 98 Complete: 74 projects 17 66 Data not reported 65 projects 32 Data available 37 15 20 7 35 45 projects 20 Number of Projects 19 58 53 39 26 School Districts State Agencies & Higher Ed Institutions Commerce-Housing Trust Fund Commerce-Community Development Source: JLARC analysis of information provided by GA, OSPI, and Department of Commerce. Report Page 7 High Performance Public Buildings

  5. Impact of high performance requirements on public building design and construction costs The Evergreen State CollegeSeminar II building

  6. Added Cost of Meeting High Performance Requirements Ranges from 1% to 3% • Estimate presented to Legislature in 2005 • High performance requirements would add about 2% to design and construction costs • Average percent of added cost: 17 State agency/higher education projects 0.9% 14 K-12 school projects 2.6% Report Pages 9-10 High Performance Public Buildings

  7. How high performance buildings actually perform Rachel Carson Elementary Library Media Center

  8. JLARC Review Analyzed Energy Performance in Four Ways 1. Actual use Compared to Design estimate • 2 of 7 buildings achieved estimated energy efficiency 2. High performance buildings Compared to Similar conventional buildings • In 5 of 8 school districts high performance buildings were more energy efficient than conventional buildings 3. Energy use Compared to National benchmark • 5 of 13 schools earn Energy Star designation 4. Energy use Compared to Change over time • 8 of 9 schools with more than 22 months data improved energy efficiency Report Pages 11-18 High Performance Public Buildings

  9. Energy Performance is Mixed • JLARC review shows that for each measure some high performance buildings demonstrate greater energy efficiency while others do not • Definitive conclusion is premature at this time Report Page 18 High Performance Public Buildings

  10. Why Actual Energy Use May Not Meet Estimates • Building managers and construction professionals identified various factors, including: • Operation and maintenance practices • How occupants use or don’t use high performance features • Some school districts have created positions to educate building managers and occupants in energy conservation practices Report Page 12 High Performance Public Buildings

  11. Lack of data and methodology issues limit evaluation Lynnwood High School

  12. Information About High Performance Buildings Is Not Complete • GA and OSPI created procedures for collecting cost and operational data • Information for many projects has not been reported • Department of Commerce • Has not reported on affordable housing projects • Interprets law as not requiring reports on community development projects Report Pages 21-22 High Performance Public Buildings

  13. JLARC Was Not Able to Assess Building Impact on Workers and Students • Most studies of worker productivity are based on subjective information, such as surveys • Two studies that measure productivity focus on industrial production • National Academy of Sciences found no evidence-based studies that analyze whether green schools differ from conventional schools on student performance Report Pages 23-24 High Performance Public Buildings

  14. Recommendation 1 • The Department of General Administration, OSPI, and Department of Commerce should develop plans to ensure that they receive complete and accurate data on high performance buildings and analyze program results. • Report to JLARC and legislative fiscal committees by December 2011 Agency Responses General Administration Concurs OSPI Concurs Commerce Concurs OFM No comment Report Page 25 High Performance Public Buildings

  15. Recommendation 2 • If the Legislature wants information on high performance projects supported by community development grants, it should clarify Chapter 39.35D RCW to specifically require the Department of Commerce to obtain that information from grant recipients. Agency Responses General Administration No comment OSPI Concurs Commerce Concurs OFM No comment Report Page 26 High Performance Public Buildings

  16. Contact Information Mark Fleming 360-786-5181 mark.fleming@leg.wa.gov www.jlarc.leg.wa.gov High Performance Public Buildings

More Related