An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Paul McCown, PE, CxA, LEED AP, CEM SSRCx, LLC HighPerformanceBuildings2007 Commissioning for LEED Certification

  2. True or False? • Commissioning requirements for LEED-NC 2.2, LEED-CS 2.0 and LEED-CI 2.0 are nearly identical. • True • It is possible to achieve the Enhanced Commissioning Credit if the CxA is hired after design is complete. • True

  3. True or False? • Different entities can provide commissioning services to fulfill the LEED scope if directed by a qualified CxA. • True • Commissioning Authorities are the smartest guys in the room.

  4. USGBC’s Mission: Promote the design and construction of buildings that are environmentally responsible, profitable, and healthy places to live, work and learn. • The organization’s activities… • Integrate building industry sectors • Lead market transformation • Educate owners and practitioners

  5. Leadership in Energy and Environmental DesignBuilding Rating Systems LEED-NC: LEED for New Construction and Major Renovations/Additions (released 2004) LEED-EB: LEED for Existing Buildings (released 2004) LEED-CI: LEED for Commercial Interiors (released 2004) LEED-CS: LEED for Core and Shell (released 2006) LEED-H: LEED for Homes (pilot) LEED-ND: LEED for Neighborhood Developments (pilot) LEED-S: LEED for Schools (not yet released)

  6. LEED-NC Overview • Credit Breakdown: • 7 Prerequisites • Certified 26 – 32 • Silver 33 – 38 • Gold 39 – 51 • Platinum 52 - 69

  7. EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems Intent: Verify that the building energy systems are installed, calibrated and perform according to the owner’s project requirements (OPR), basis of design (BOD), and construction documents. • HVAC&R systems and controls • Lighting and daylighting controls • Domestic hot water systems • Renewable energy systems (wind, solar, etc.)

  8. EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems Scope (1): • Designate a CxA to lead, review and oversee the commissioning process activities. • Experience on 2 projects • Not directly responsible for design or construction • Report directly to Owner

  9. EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems Scope (2): • Review OPR and BOD documents for clarity and completeness. Discussion – Who develops? What is your experience? Standards?

  10. EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems OPR Components: • Building use and use by space • Goals (energy, environment, etc.) • IEQ – lighting, temperature ranges, acoustics • Equipment and System Expectations • O&M and Training Expectations BOD Components: • MEP Narrative • Design assumptions • Space use • Diversity • Redundancy • Climatic data • Standards

  11. EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems Scope (3): • Develop a commissioning specification. Discussion – Spec Section? Sub-Consultant Requirements?

  12. EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems Scope (4): • Develop a commissioning plan. Discussion – Components? Remember OPR, BOD, Construction Documents

  13. EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems Scope (5): • Verify installation and performance of equipment and systems. Discussion – Who verifies what?

  14. EA Prerequisite 1: Fundamental Commissioning of the Building Energy Systems Scope (6): • Complete a summary commissioning report. Discussion – What about outstanding items?

  15. EA Credit 3: Enhanced Commissioning Intent: Begin the commissioning process early during the design process and execute additional activities after systems performance verifications is complete.

  16. EA Credit 3: Enhanced Commissioning Scope (1): • Independent CxA. • Must perform reviews, can oversee other requirements • Not an employee of the design firm • Not connected to the contractor in any way Discussion?

  17. EA Credit 3: Enhanced Commissioning Scope (2): • Design Reviews • OPR, BOD • mid CDs • Back-check review comments Discussion – What if CDs are complete?

  18. EA Credit 3: Enhanced Commissioning Scope (3): • Submittal Reviews • Review for compliance with OPR, BOD • Concurrent with A/E reviews Discussion – What are you looking for?

  19. EA Credit 3: Enhanced Commissioning Scope (4): • Systems Manual • Information for understanding system function and optimal operation • More than just O&M and blank Cx Plan Discussion – What are you including?

  20. EA Credit 3: Enhanced Commissioning Scope (5): • Owner Training • Review training plan • Verify that training takes place and is effective Discussion – What works?

  21. EA Credit 3: Enhanced Commissioning Scope (6): • Warranty Review • Meet with O&M staff and occupants • Include a plan for resolution of outstanding Cx-related activities Discussion – We told you so…

  22. LEED-CI • No design reviews • All else same

  23. LEED-EB Overview • Credit Breakdown: • 14 Prerequisites (double LEED-NC) • Certified 32 – 39 • Silver 40 – 47 • Gold 48 – 63 • Platinum 64 - 85

  24. EA Prerequisite 1: Retro-Cx Intent – Verify that fundamental building systems and assemblies are performing as intended to meet current needs and sustainability requirements. • Building Operation Plan – means for execution

  25. EA Prerequisite 1: Retro-Cx Requirements – Verify installation, calibration, and operation for functionality and efficiency of the following: • Heating, cooling, and humidity control • Lighting • Safety • Controls

  26. EA Prerequisite 1: Retro-Cx Building Operation Plan components: • Use – occupancy and schedule by space type • Static system requirements • Functional system requirements

  27. EA Prerequisite 1: Retro-Cx Performance Testing Plan (Cx Plan) components: • Part A - Inspection • Part B – Functional Verification (data logging)

  28. EA Prerequisite 1: Retro-Cx Space Temperature : • Part A – Inspection • Measure temperature and check vs space setpoint. Take a representative sample*. • Part B – Functional Verification • Trend space temperature in various locations *sample – greater of 10% minimum or 5 spaces

  29. EA Prerequisite 1: Retro-Cx Space Pressurization (pick A or B): • Option A – Instantaneous Measurements • Measure and document space pressurization requirements for each space-use type. • Option B – Trending Measurements • Trend “space” pressure to show compliance (follow regulatory standards if applicable) How? – Discussion -

  30. EA Prerequisite 1: Retro-Cx Building Envelope: • Inspection (pictures are helpful) • Basic envelope integrity (no holes, gaps) • Doors and door jams • Windows and window frames • Backdraft and mechanical dampers when fans are off • Innovation Credit opportunity – Conduct an infrared building scan once every five years.

  31. EA Prerequisite 1: Retro-Cx Heating / Cooling Systems: • Option A – Instantaneous Measurements • Design and conduct performance testing regarding HVAC systems sequence of operation. • Option B – Trending Measurements • Trend HVAC system components to show compliance How? – Discussion -

  32. EA Prerequisite 1: Retro-Cx Heating / Cooling Systems: • Boilers, Chillers, Cooling Towers • Air Handling Units • Supply Temperature Reset (air, water) • Variable Volume Modulation (air, water) • Economizer control

  33. EA Prerequisite 1: Retro-Cx Water Systems: • In conjunction with other LEED-EB Credits • WE Prereq 1: Min. Water Efficiency • WE Prereq 2: Discharge Water Compliance • Must be included in Building Operations Plan and Cx Plan for verification • Covers ALL water consuming equipment

  34. EA Prerequisite 1: Retro-Cx Lighting Systems: • Must be included in Building Operations Plan and Cx Plan for verification • Indoor – trend or otherwise verify operating hours by space type. • Outdoor – trend or otherwise verify operating hours by space type.

  35. EA Prerequisite 1: Retro-Cx Building Controls Systems: • Must be included in Building Operations Plan and Cx Plan for verification • Verify controls operation for all applicable systems and equipment – schedules, sequences, sensors, etc.

  36. EA Prerequisite 1: Retro-Cx Synergies with other LEED-EB Credits: • WE Prereq 1: Min. Water Efficiency • WE Prereq 2: Discharge Water Compliance • EA Prereq 2: Min. Energy Performance • EA Credit 1: Optimize Energy Performance • EA Credit 3.3: Building Systems Monitoring • EA Credit 5.1-3: Performance Measurement • IEQ Prereq 1: Outside Air and Exhaust • IEQ Credit 1: Outside Air Delivery Monitoring • IEQ Credit 7.1-2: Thermal Comfort

  37. Questions and Answers Thank You!