1 / 15

FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa

FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa. Electronics Installation and Commissioning Schedule. PHASE I. Installation of FECs and Backplanes Jan ’05 - Mar ’06 electrical and functional test of each FEC test of the connection between FECs and pad plane

boris
Download Presentation

FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FEE Installation & Commissioning TPC Meeting, 21 April 2006 L. Musa

  2. Electronics Installation and Commissioning Schedule PHASE I • Installation of FECs and Backplanes Jan ’05 - Mar ’06 • electrical and functional test of each FEC • test of the connection between FECs and pad plane • test of the connection between FECs and readout backplane PHASE II • Characterization of the whole system with RCUs Mar – May ’06 • Characterization of 1 readout partition at a time: noise, gain, width, baseline, time offset, temperature, voltages and currents PHASE III • Installation of RCUs May – Aug ’06 • Comprehensive test of all (216) readout partitions: FEE, DAQ, DCS, TRIGGER, HLT, ECS (power bars and cooling required)

  3. FE Cards Installation 1/2 • Organization and schedule • 2 installation crews (3 people / crew) • Installation started on the 30th January • Installation rate: ~ 1 sector / day • Status • Installation of FECs completed (on March 15), with exception of 1 sector on C side • Installation of Readout &Control backplanes completed by end of March, with exception of 1 sector on C side • The electronics of 1 sector (A09), equipped with the LV bus rods and cooling, was characterized (pedestals, noise, gain) • The electronics of sector A08 is under test

  4. FE Cards Installation 2/2 During the installation, the FECs are tested individually (stand-alone) by means of a dedicated “mounting test tool”, U2F (USB to FEC interface) • Readout of trigger related data (pulser) • Connection to the pad plane • Measurement of VCCA, VCCD, IA, ID and T • Measurement of the FEC Identifier U2F Card

  5. FE Cards Installation highlights

  6. TPC A Side (17th February ’06)

  7. Characterization of Sector A09 • Sector A09 equipped with • backplanes • cooling circuit • LV power rods • LV PS + cables (4 x 40m)

  8. Characterization of Sector A09 - IROC sum of charges, pad row 46 sum of charges baseline noise rms (ADC counts)

  9. Characterization of Sector A09 - IROC sum of samples baseline rms baseline  (PASAnoise2 + ADCnoise2) = 0.70 ADC counts

  10. Characterization of Sector A09 - OROC sum of charges sum of charges, pad row 11 baseline noise rms (ADC counts)

  11. Characterization of Sector A09 - OROC sum of samples sum of samples baseline rms baseline rms

  12. Readout Control Unit 1/2 SIU CARD RCU status and plans … DCS CARD Power Regulators

  13. Readout Control Unit 2/2 Production, test, installation and commissioning • Mass Production (240 units including 10% spares) • completed November ‘05 • Mass Test • completed December ’05 • Delivery of tested DCS cards Mar ‘06 • Delivery of tested SIU cards (DAQ project): • 1st lot (108 units) Mar ’06 • 2nd lot (108 units) May ‘06 • Assembly and final test of RCU + SIU + DCS: Apr – Jun ‘06 • Installation and commissioning of RCUs: May – Aug ‘06

  14. Preparing for Commissioning Phase III • RCU Lab - setup I  Final assembly and test of RCU + SIU + DCS • 25 FECs (readout partition) + Backplane + RCU • 1 DAQ PC (PCALD23) + single-channel RORC • 1 DCS PC (local network DHCP server, DIM Server) + Ethernet Switch • Local Trigger Crate (SBC, LTU, TTvi, TTCex) + TTCoc • RCU Lab - setup II  TPC FEE + DAQ + HLT Integration • 2 x Readout Partitions • 1 DAQ PC (EPAITBEAM02) + dual-channel RORC • 1 HLT PC + 1 HRORC • P2 SXL2 – Test of the electronics, 1 Sector at a time • 1 x Readout Partition • 1 DAQ PC (ALDAQPC021) + dual-channel RORC

  15. Conclusions • Installation of FECs almost complete (97% done) • The complete electronic chain of one TPC sector has been characterized • gain, baseline and noise distributions well within specifications • Installation of backplanes was completed by Mar ’06 • Installation and commissioning of RCUs in May - Aug ‘06

More Related