490 likes | 720 Views
PRESENTATION CONTENTS:. MAIN AND TRACKER RADIATORS STATUS:Heaters debonding issueSharp edges issueOff line\On line integration planningCAB TCS STATUS:Manufacturing status (LHP)Off line\On line integration planningCRYO TCS STATUS:Manufacturing status (LHP,spokes,brackets)Off line\On line int
E N D
1. AMS TIM FEBRUARY 2009Thermal Control System (TCS)status report Joseph Burger (MIT)
Massimiliano Olivier (CGS)
Cristian Vettore (CGS)
Marco Molina (CGS)
Dar-Jen Sun (AIDC)
Cheng Lin (SDU)
2. PRESENTATION CONTENTS: MAIN AND TRACKER RADIATORS STATUS:
Heaters debonding issue
Sharp edges issue
Off line\On line integration planning
CAB TCS STATUS:
Manufacturing status (LHP)
Off line\On line integration planning
CRYO TCS STATUS:
Manufacturing status (LHP,spokes,brackets)
Off line\On line integration planning
MLI STATUS:
BRICKS MLI installation
AMS MLI design and manufacturing status
Off line\On line integration planning
3. MAIN AND TRACKER RADIATORS INSPECTION Main and Tracker radiator panels have been inspected by CGS on October 16th at CERN before to proceed with assembly of the thermal hardware (radiators are ASI AFE items).
Inspection highlighted some NCRs that are under evaluation with AMS collaboration. Main issue under investigation:
HEATERS DEBONDING (item relevant also to ohter AMS foil heaters)
SHARP EDGES (item relevant also to zenith radiators)
4. MAIN AND TRACKER RADIATOR HEATERS DEBONDING
5. AMS FOIL HEATER GENERAL DEBONDING INVESTIGATION
6. MAIN AND TRACKER RADIATOR SHARP EDGES
7. MAIN AND TRACKER RADIATOR SHARP EDGES
8. ZENITH RADIATORS SHARP EDGES
9. RAM MAIN RADIATOR THERMAL HARDWARE ASSY AND INTEGRATION FLOW
10. WAKE MAIN RADIATOR THERMAL HARDWARE AND CAB LHP ASSEMBLY AND INTEGRATION FLOW
11. RAM AND WAKE MAIN RADIATOR THERMAL HARDWARE AND CAB LHP ASSEMBLY AND INTEGRATION SCHEDULE
13. TRACKER RADIATORS THERMAL HARDWARE ASSY AND INTEGRATION FLOW
14. TRACKER RADIATORS THERMAL HARDWARE ASSY AND INTEGRATION SCHEDULE
15. CAB TCS STATUS
CAB TCS COMPONENTS:
CAB AND USS AGHP
CAB LHP
HEATERS AND THERMOSTATS
SILVER TAPE AND MLI (ON MLI SECTION)
16. (CAB) USS Axial Groove Heat Pipes have been integrated on AMS on on October 16th according to the AMS Task Sheet (ATS) # TCS080806-22 by C.Vettore and A.Dellacqua (CGS eng and ops) with the supervision of L.Cremonesi (CGS PA\QA) and supported by J.Burger and C.Gargiulo (AMS)
17. CAB AXIAL GROOVE HEAT PIPES STATUS MANUFACTURED INSPECTED, DELIVERED TO CERN AND FIT CHECKED CON CAB FM, READY FOR INTEGRATION ON CAB FM
18. CAB LHP MANUFACTURING STATUS
19. CAB LHP MANUFACTURING STATUS*
20. CAB LHP EVAPORATOR PARTS MANUFACTURING COMPLETE, ASSEMBLY IN PROGRESS
22. SAMPLES OF SADDLES HAVE BEEN MANUFACTURED. TESTING IS IN PROGRESS TO VERIFY FINAL PLANARITY OF SADDLES WHEN LHP TUBES ARE SOLDERED.
SINGLE SADDLE SABLE BRAZED
L SHAPE 3 SADDLES SAMPLE UNDER PRODUCTION
ECD FOR COMPLETION 13/02/08. CAB LHP CONDENSER SADDLES MANUFACTURING AND PLANARITY TEST IN PROGRESS
26. CAB THERMAL HARDWARE (NO LHP) ASSY AND INTEGRATION FLOW
28. CRYO TCS STATUS
29. CRYO LHP ZENITH RADIATORS MANUFACTURING STATUS
30. CRYO LHP ZENITH RADIATORS MANUFACTURING STATUS
31. ZENITH RADIATOR PANELS 1 AND 2 ALREADY SHIPPED TO IE ON NOVEMBER 28 AND DECEMBER 12
32. ZENITH RADIATOR PANELS SILVER TAPE APPLIED
33. ZENITH RADIATOR PANELSBMJ BRACKETS
34. ZENITH RADIATOR PANEL 1 AND 2TRANSPORT CONTAINER
35. ZENITH RADIATOR SPOKES MANUFACTURING AND TESTING IN PROGRESS
36. CRYO TCS ASSY-TRANSPORT JIG AND BENDING TOOLS (1)
37. CRYO TCS ASSY-TRANSPORT JIG AND BENDING TOOLS (2)
38. CRYO TCS EVAPORATORS ASSEMBLED
39. CRYO TCS ASSY AND INTEGRATION FLOW
40. CRYO TCS ASSY AND INTEGRATION SCHEDULE
41. MLI STATUS REPORT MLI PRODUCTION
(18) blankets delivered@CERN:
(4) RICH Lateral
(4) ECAL corner ZN
(4) LTOF
(6) Bricks
MLI INSTALLATION AND FIT CHECKS:
MLI integration slot has been performed on 10-14 November 2008
2 AMS Task Sheets (ATS) have been prepared
(6) blankets delivered and installed@CERN (bricks MLI)
(8) blankets deliverded, installation to be completed by AMS collaboration (ECAL corner ZN, RICH Lat)
(4) blankets deliverd@CERN (LTOF)
(2) blankets reworked (RICH Bottom)
MLI detailed plan to completion is under development and weekly discussed at the TWG teleconference.
48. MLI MANUFACTURING STATUS