1 / 12

High Level Post Processing Cost Estimates

High Level Post Processing Cost Estimates. MWG SSC Meeting September 26, 2011. Post Processing Cost Estimates. Futures 4 and 8 increased EE/DR/DG Future 7 Nuclear Uprate Costs F2B, F3B, F5B, F5S7, F6B, and F6S5 integration costs Variable Energy Resource (VER) beyond 25% penetration

briar
Download Presentation

High Level Post Processing Cost Estimates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. High Level Post ProcessingCost Estimates MWG SSC Meeting September 26, 2011

  2. Post Processing Cost Estimates • Futures 4 and 8 increased EE/DR/DG • Future 7 Nuclear Uprate Costs • F2B, F3B, F5B, F5S7, F6B, and F6S5 integration costs Variable Energy Resource (VER) beyond 25% penetration • Thermal integration costs (Contingency Reserves)

  3. Energy Efficiency Demand Reduction

  4. Energy Efficiency Supply Curves

  5. Estimated Cost of Energy Efficiency

  6. Energy Efficiency Estimated Costs (Billions 2010$)

  7. Demand Response Estimated Cost (Billions 2010$) Assumptions • Costs per customer ($/customer) from recent studies divided by potential peak load reduction per customer (MW/customer) to calculate $/MW • Used $/MW for incremental peak load reductions per year in respective future

  8. Futures 4 and 8Estimated Distributed Generation Costs • 2x Distributed Generation in BAU • Assumed all behind-the-meter PV • Assumed weighted average of the 2-5 kW and 5-10 kW, $8,045/kW (2010$) • The estimated cost of the renewable distributed generation during 2015-2030 is $98B.

  9. Estimated Nuclear Uprate Costs Assumptions • $2,600/kW • All other assumptions the same as new nuclear

  10. Variable Energy ResourceEstimated Cost above 25% Penetration Limit Assumptions • EWITS Scenario 4 served as starting point - $5.13/MWh (2009$) • Gas price adjustment to capture the difference of EWITS and EIPC natural gas forecasts

  11. Variable Energy Resource Estimated Integration Costs (Billions 2010$)

  12. Contingency Reserves $2/MWh * (% coal, nuke, & CC study case/% coal, nuke, & CC BAU) Assumptions • A 2003 study, Allocating Costs of Ancillary Services: Contingency Reserves and Regulation, suggests that costs of contingency reserves to accommodate the loss of the largest unit increases the operating costs and recommends a method that allocates based on its size and forced outages to incentivize generators to maintain their units. • During Phase II the Planning Authorities should add new transmission and generation units consistent with traditional planning methods that expand the system in a manner with lowest costs. This often results in adding new transmission and generation in such a manner that the largest single contingency remains unchanged, and therefore would avoid any incremental costs.

More Related