Influence on efficiency

Influence on efficiency. Questions Ideal weather The work with most influences of weather How much of the total work The influences in percent to the efficiency Rain: when it start to raining Cold: when the temperature goes under zero Warm: when the temperature is getting wormer

Download Presentation

Influence on efficiency

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Influence on efficiency Questions Ideal weather The work with most influences of weather How much of the total work The influences in percent to the efficiency Rain: when it start to raining Cold: when the temperature goes under zero Warm: when the temperature is getting wormer Snow: when start to snow Wind: start to blow Wind and rain: when both blowing and raining Wind and snow: when both blowing and snowing Wind and cold: when both blowing and cold

  2. Sheet metal workers80 persons at a conference (from whole Sweden) • Ideal weather: 15o, no wind • Worst work: sheet metal work on roofs • 20% of the total work • Rain: 30-100% (Impossible to walk on the roof) • Cold: 30-100% (Some material need at least 5o) • Warm: no big problem (?) • Snow: 50-100% (Like rain + take away snow) • Wind: 50-100% (Sheets blow away - some work e.g. window on backside no influence) • Wind and snow, wind and rain, wind and cold: 100%

  3. Electricians2 persons 60 and 30 years old • Ideal weather: 15o, no wind • Worst work: put cables together outdoors, construction • 5% of the total work • Rain: 15% • Cold: 15% (Some cables need at least 0o - gets hard) • Warm: no big problem • Snow: 25% (Like rain + take away snow) • Wind: 15% • Wind and rain: 25% • Wind and snow: 25% • Wind and cold: 15%

  4. Electrician1 persons 35 years old • Ideal weather: 15o, no wind • Worst work: put cables together outdoors, streets • >50% of the total work • Rain: 0% • Cold: >25% (Cables needs at least 0o -gets hard – can not be handled) • Warm: no big problem • Snow: 0% • Wind: 15%

  5. Bridge work4persons about 55 years old • Ideal weather: 10-15o, no wind • Worst work: formwork, moulding • 80% of the total work • Rain: 15% • Cold: 100% (Moulding below 5o not possible) • Warm: no big problem • Snow: 50% (Have to erase snow from formwork) • Wind: 0-20% (At strong wind can it be impossible to lift the formwork) • Wind and rain: 15-50% • Wind and snow: 50-100% • Wind and cold: 100% (Moulding not possible)

  6. Woodworkers and their supervisors4 woodworkers 29-45, 2 supervisors 55-60 • Ideal weather: 10-15o, no wind, no sun • Worst work: nailing the wood parts of the roof construction • 5-10% of the total work • Rain: 100% (Not possible to lay wood roof, do other work and loos 10-15%) • Cold: 0% (Down to -10o no influence) • Warm: <20o no influence, >25 10-25% influence) • Dry snow: 20% (I easy to take away) • Wet snow: 100% (Have to clean the roof from snow) • Wind: 0-20% (Takes it easy, can not lay paper) • Wind and rain: 100% (Do other jobs if possible) • Wind and snow: 100% • Wind and cold: 100% (-5o feels like -25o) To move to an other work leads to decrease of efficiency of between 10-15%

  7. Woodworkers 2 persons • Ideal weather: 10-15o, no wind, no sun • Worst work: erecting roof beams • 5-10% of the total work • Rain: 5% (Depends to the level of raining) • Cold: 0% (Down to -15o no influence, lower 5%) • Warm: <25o no influence, >25 5% influence) • Dry snow: 5% (I easy to take away) • Wet snow: 20-25% • Wind: 100% (>10 m/s not possible to lift roof beams, great risks) • Wind and rain: 100% (See wind but worse) • Wind and snow: 100% (See wind but worse) • Wind and cold: 100%(See wind but worse) To move to an other work leads to decrease of efficiency of between 10-15%