1 / 19

Tarmac Ltd

Tarmac Ltd. Stuart Goldthorpe Re-profiling of NE corner of Greenham Common. 1997. Chamberhouse Farm. Greenham Common Restoration – 2000 / 2001. Chamberhouse Farm. Greenham Common Restoration – 2000 / 2001. Greenham Common Restoration – 2000 / 2001.

bryga
Download Presentation

Tarmac Ltd

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tarmac Ltd Stuart Goldthorpe Re-profiling of NE corner of Greenham Common

  2. 1997 Chamberhouse Farm Greenham Common Restoration – 2000 / 2001

  3. Chamberhouse Farm Greenham Common Restoration – 2000 / 2001

  4. Greenham Common Restoration – 2000 / 2001

  5. Greenham Common Restoration – 2000 / 2001

  6. Planning Application LodgedPartnership between Tarmac and West Berkshire • RSPB, English Nature, Environment Agency all had major concerns • Local people objected ( ‘T’ Shirts ) • The application went through every committee stage possible at West Berks. • When approved the application went to GOSE and approved eventually by the ODPM

  7. Greenham Common Restoration – 2000 / 2001

  8. Greenham Common 1964 Re-profiling area Greenham Common Restoration – 2000 / 2001

  9. Restoration Objectives • Create wetland areas • Re-grade the surface – microhabitats • Expose true acidic soils to support heathland • Re-establish seepage lines / mires • Re-create incised valley heads Greenham Common Restoration – 2000 / 2001

  10. To unlock the Restoration Objectives • 27.5 Ha had to be re-profiled / restored • Removal to Lower Farm of 707,000m3 of ballast by separating it from material contaminated with hydrocarbons at the Common for Bio-remediation • Over 1 million m3 soil to be moved to create landform • Cost of overall contract £1.5 million

  11. Greenham Common Restoration – 2000 / 2001

  12. Greenham Common Restoration – 2000 / 2001

  13. Greenham Common Restoration – 2000 / 2001

  14. Greenham Common Restoration – 2000 / 2001

  15. Greenham Common Restoration – 2000 / 2001

  16. Greenham Common Restoration – 2000 / 2001

  17. Greenham Common Restoration – 2000 / 2001

  18. 2001 Greenham Common Restoration – 2000 / 2001

  19. Greenham Common Restoration – 2000 / 2001

More Related