1 / 9

Vance County Water District Overview and Update

Vance County Water District Overview and Update. Jordan McMillen Director Vance County Planning and Development Department 156 Church St. Suite 3 Henderson, NC 27536 (252) 738-2091. Presentation Outline. History of Project Water System Details Signup Information Benefits Questions?.

caine
Download Presentation

Vance County Water District Overview and Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Vance County Water District Overview and Update Jordan McMillen Director Vance County Planning and Development Department 156 Church St. Suite 3 Henderson, NC 27536 (252) 738-2091

  2. Presentation Outline • History of Project • Water System Details • Signup Information • Benefits • Questions?

  3. History of Project • 1996 • Land Use Plan identified need for water throughout the county • 2004 • Vance County Water District formally established (Oct. 4, 2004) • Preliminary Engineering Report Completed (Engineering firm: Hobbs and Upchurch Associates) • 2006 • Jan – March; 1st set of public meetings • 2008 • March – April; Public information meetings • May; Bond Referendum for $27 million passed • October; USDA committed funds to Phase 1A (loan) • November; USDA granted $1 million grant • December; notified of $1 million grant from NC Rural Center

  4. History Cont. • 2009 • January; VC Water Board approved rules and regulations; Requirement of USDA • January; Authorization for beginning of engineering field work concurrent with sign up campaign • July – preliminary design complete; shovel ready • October – Kittrell Water Association expressed interest in Phase 1B; Application made to USDA for Phase 2A & 2B funding. Application made to NC Rural Center for $1,000,000 grant for Phase 2A & 2B. • November – Sign up campaign officially began with mass mailing and signup meetings (12/1, 12/3, 12/10). • 2010 • March – Made aware of successful funding for Phase 2A and 2B • April – Sign up campaign for Phase 2 with mass mailing and signup meetings (4/15, 4/19, 4/26). • 2011 • Finalized water purchase agreement with City of Henderson • Phase 1A Tank Site Secured; Location off of Warrenton Road .

  5. History Cont. • 2012 • Secured meter vault site (connection site to City of Henderson); • Project advertised for bidding; Selected local contractor H.G. Reynolds to complete the construction; • Water Tank advertised for bidding; Selected Caldwell Tanks from Kentucky • July 9, 2012 – Official start of Construction for Phase 1A(anticipate 9-12 months of construction); • Anticipate construction beginning on Phase 2 in Spring 2013.

  6. Water System Details (see map) • Phase 2A • Total Projected Cost - $3,898,400 • Total Project Miles – approx. 28 miles • Total Signups to date – 363 • Received 42% grant – stimulus money • Phase 2B • Total Projected Cost - $6,034,750 • Total Project Miles – approx. 44 miles • Total Signups to date – 365 • Received 33% grant – stimulus money • Phase 1A • Total Projected Cost - $7,829,000 • Total Project Miles – approx. 60 miles • PROJECT SIZE REDUCED BASED UPON SIGNUPS • Total Signups – approx. 825 of which 580 are located along roads that will be served. • Revised total cost – approx. $5.1 million • Revised mileage – approx. 35 miles. • Received $2 million grant (25%) • Phase 1B (Kittrell Water Assoc.) • Total Project Miles – approx. 35 miles

  7. Signup Information • Connection fee • Incentive connection fee of $125 vs. $750 during construction vs. $2,000 following construction. • Need 12 – 14 houses per mile or 80% signup along a given road segment for service. • Tap Options (Wet vs. Dry Tap) • Wet Tap: Pay $125 connection fee upfront plus $50 inspection fee for total of $175. Water billed at prevailing rate once operational. Owner responsible for water service line to house. • Dry Tap Option 1: Pay $125 connection fee upfront. Once operational pay minimum fee of $20 per month. Property owner will be responsible for $50 inspection fee when/if service line installed. Owner responsible for water service line to house. • Dry Tap Option 2: Pay one time fee of $800 (< 1” tap) or $1,200 (> 1” tap) with no intended use of water. This option is not counted in 80% participation requirement. • Estimated Monthly Bill • $35-$45 (5000 gallons/mo); • Following bid estimate closer to $53 for 5000 gallons/mo.

  8. Benefits of Water System • Safety – secured, regulated, constantly monitored; less likely to contamination than private wells. • Reliability – ongoing and sustainable during power outages, drought condition, etc. • Quality – wells more subject to contamination; discoloration, noticeable odor or high mineral content in well water common. • Drought Resistant • Rural fire protection • Reduced ISO insurance ratings • Reduced up front costs of wells and pumps • Economic Development - Ability to encourage and attract new development while enhancing existing development • Ability to utilize wells for outside uses (washing car, watering flowers, etc.) • Great investment for Vance County’s future

  9. Questions?

More Related