Collecting Project Information

Collecting Project Information. How Should We Collect Information ? Formally (on a regular basis): what we have planned to collect what we have set up and prepared ourselves to collect Informally (not regular but often): “walking the hall” and “by the water cooler”

callia
Download Presentation

Collecting Project Information

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Collecting Project Information • How Should We Collect Information ? • Formally (on a regular basis): • what we have planned to collect • what we have set up and prepared ourselves to collect • Informally (not regular but often): • “walking the hall” and “by the water cooler” • inviting team members for informal “chat” • visit people’s “offices” - We really need both! - Informal --- is changing with internet, physically distributed resources, and social networking software

  2. Formal Data Gathering & Monitoring • Should be performed on a regular basis: • weekly • semi-monthly • monthly • etc. • How oftendepends on • the size and length of the project • the specific activity • What form depends on earlier plan and preparation: • Standard Format • Numerical/logical/etc.

  3. What Do We Collect?Remember the Goals ? • We collect data and monitor “actual” against “plannedgoals” • Product attribute goals: • quality • completeness of function • reliability • etc. • Project and People attribute goals: • productivity • schedule • morale • etc. See Chapter 8 on Measurements and Goals Most popular one

  4. Monitored Information • Project “Status” is really saying: • Where we stand today “relative” to the target • Show “actual” vs “planned” by areas of interest (“goals”) If you changed the “planned”, show the trace of changes -include the date of change - “approved-by-whom” information - ***additional info such as “impact” of change ***

  5. Several Types of Data Collection • Activity Based: • collecting information on one or more attributes related to a set of activities • completion date • time expended • effort or other resources expended • the activities are most likely those within a process or a method • Attribute Based: • collecting information on one or more sub-attributes related to a specific project attribute of interest: the specific attribute may be an entity • the specific attribute is often schedule, function, etc. In reality ---- mostly a mix of both

  6. Activity Based Example Date : _8/20/2002_ Planned Completion Actual Completion Milestone Activities Delta Req. Solicitation 07/10/2002 07/15/2002 + 5 days Req. Analysis 07/25/2002 07/25/2002 0 days Req. Documentation 08/15/2002 08/17/2002 +2 days Req. Verification 08/25/2002 Req. Approval 07/10/2002 This requirements activities based data allows us to gauge the schedule attribute of that set of activities. Note that this does not talk to resources, productivity, efficiency , etc. (only schedule)

  7. Attribute Based Example Date : 8/20/2002 Functionality Attribute Planned # of Features Completed # of Features Delta Function 1 13 (7/15) 13 (7/15) 0 Function 2 25 (8/15) 22 (8/20) -3 Function 3 9 (8/15) 8 (8/20) -1 May never be completed ? Function 4 7 (8/15) 7 (8/12) 0 Function 5 11 (8/25) 9 (8/20) -2 Note that this is collecting data on product functional completeness attribute. It is collecting data on the product “functionality” attribute and the “# of features completed” attribute on the specific date (mm, dd)for each function.

  8. A More Complex Exampleof Activitiesand a “quality”Attribute based on Severity 1 problems Date : _8/20/2002_ F1 F2 F3 . . . . Activities Delta Should be alarmed if these were from F1 or F2. Why? Req. Review (6,6) (7,7) (4,3) 1 Design Review (5,5) (6,6) (5,2) 3 Functional Test 0 (3,3) (3,3) Component Test 1 (3,2) (2,2) System Test (4,3) (3,2) 2 Note that this is collecting data on product quality attribute : Severity 1 problems (found , resolved)by each defect detection and removal activities. Delta is the number of severity 1 problem still remain unresolved. F’s are functional area(s) *** Note - - this is NOT a planned vs actualcomparison chart !! --- ? ***

  9. A More Financially Oriented Monitoring(in $k) Date: 8/20/2003 Functional Area release 1 expense release 2 expense Accumulative Rev. $ Plan Act. Plan Act. . . . . Plan Act. Plan Act Function X 4.0 3.5 5.0 5.0 9 8.5 54 1.2 Function Y 2.0 2.5 4.0 5.2 6 7.7 60 0 Function Z 16 16.2 89 2.3 7.0 6.2 9.0 10.0 . . . Expenses(people, tools, travel, education, general) by functional areas .vs. Revenue Need to spread out by Release ?

  10. Formal Status Meetings • Should be planned with and “agenda” • run this efficiently because for everyone else this is NOT their “main” responsibility • The meeting should not last more than 2-3 hours • consider the expense side of the meetings & meeting prep • (e.g.) 3hrs/40hrs per week = 7.5 % in meeting per week • Do not reschedule or postpone meeting too many times • it will lose its legitimacy and relevancy • * Do not jump too deeply into “surprise” items • schedule a separate meeting involving only the relevant people • Do not turn meeting into “rubber” stamping

  11. Informal Status Gathering • Informal Data Gathering is based on • goodwill • trust • “listening” well and patiently • If Physically Co-located • proactively “walk the halls” often • invite people into your “open” office • stop in people’s office and “chat”; do not stay too aloof • If Remote Location • make some “physical- contacts” visits • utilize phone, e-mail, video-conferencing “regularly” • Need to Develop even more “TRUST” when remote Trust