Agenda The Procurement Process Post Financial-Close
Agenda The Procurement Process Post Financial-Close
The Procurement process PQQ Competitive Dialogue Outline Solutions Detailed Solutions Refined Solutions (as required) Final Tender Preferred Bidder Close
Final Tender Preparation and OBC Pre-qualification Preferred Bidder ISOS 6-8 Weeks 10-14 Weeks 26-40 Weeks 8-12 Weeks 6-24 Weeks ISDS (and refine solutions) The Procurement process: Timeline OJEU Notice Close Dialogue Financial Close ITPD Competitive Dialogue
Pre Qualification (PQQ) Procurement Preparation Issue OJEU Notice Issue PQQ to respondents Bidders conference Bidders complete and return PQQ PQQ evaluation by Project Team and advisors Agree pre-qualified bidders
Competitive Dialogue: Outline Solutions Preparation of procurement documentation and evaluation methodology (completed at or prior to finalisation of PQQ) Issue Invitation to Participate in Dialogue / ISOS to pre-qualified bidders Bidders submit Outline Solutions Evaluation and clarification Agree short-listed bidders
Competitive Dialogue: Detailed Solutions and Refined Solutions Preparation of procurement documentation and evaluation methodology (draft prior to finalisation of ISOS) Refine specification and documentation Issue Invitation to Submit Detailed Solutions (ISDS) to short-listed bidders Clarification and Dialogue Bidders submit Detailed Solutions Evaluation and clarification Negotiation Repeat and refine steps until Ready to Close dialogue Close competitive dialogue
Final Tender, Preferred Bidder and Financial Close Call For Final Tenders Bidders submit final tender Clarification and ‘fine tuning’ Evaluation Selection of Preferred Bidder Due diligence and approval Financial Close
Agenda The Procurement Process Post Financial-Close
Construction / Development phase Monitoring Testing and completion Delays – see Project Agreement Decanting
Operational phase Monitoring compliance with contract specification Application of Payment Mechanism Completion and handover Possibly: Changes to the specification Re-financing Termination