1 / 12

Introduction & Opening Remarks

Introduction & Opening Remarks. Hurricanes of 2004 & 2005 highlight the need for a fresh look at these issues We support this effort and will be active participants Help shape infrastructure strategy that works for Florida

cameo
Download Presentation

Introduction & Opening Remarks

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Introduction & Opening Remarks • Hurricanes of 2004 & 2005 highlight the need for a fresh look at these issues • We support this effort and will be active participants • Help shape infrastructure strategy that works for Florida • Be clear what we’re trying to improve; make sure any change is for the better

  2. FPSC Infrastructure Hardening Workshop January 23rd, 2006 Presented by: Michael G. Spoor, P.E. Florida Power & Light

  3. Florida Power & Light Co. • 27,000 sq. miles & 35 counties • 4.2 M customer accounts • 535 substations • Over 6K miles of transmission lines • Over 65K miles of distribution lines • Over 68K transmission structures • Over 1.1M distribution poles • Over 800K distribution transformers 2

  4. Overview • Summary of 2004 hurricane season • Lessons learned from 2004 • Summary of 2005 hurricane season • Lessons learned from 2005 • Next Steps 3

  5. Hurricane force winds Tropical storm force winds 2004 Hurricane Season Hurricane CharleyCategory 4 Hurricane FrancesCategory 2 Hurricane JeanneCategory 3 4

  6. 2004 Hurricane Season – Distribution and Transmission Equipment Repaired • Distribution • 10,379 FPL poles • 960 miles of OH conductor • 590 miles of OH service conductor • 1 million OH splices • 30 miles of UG cable • 100 miles of UG service cable • Transmission / Substation • 174 structures • 15 miles of conductor • 3 substation transformers • 10 regulators • 39 breakers 5

  7. Lessons Learned from 2004 • Hired 3rd party consultant to help evaluate system performance and restoration processes • Key findings • FPL met or exceeded standard utility restoration practices • FPL’s distribution, transmission, & substation facilities performed well • FPL’s transmission system was restored effectively • Areas of opportunity • Enhance customer communications by providing lower level ETR’s • Establish critical infrastructure priorities with local EOC’s • Establish partnerships to improve resource acquisition capabilities • Internal reviews • Distribution • Introduced forensic team to perform detail analysis • Streamlined processes for underground conversions • Transmission/Substation • Reviewed remainder of system from lessons learned • Implemented plans accordingly 6

  8. Hurricane force winds Tropical storm force winds 2005 Hurricane Season Hurricane KatrinaCategory 1 Hurricane WilmaCategory 3 7

  9. 2005 Hurricane Season – Distribution and Transmission Equipment Repaired • Distribution • 12,632 poles (FPL & non-FPL) • 930 miles of OH conductor • 570 miles of OH service conductor • 1.1 million OH splices • 30 miles of UG cable • 100 miles of UG service cable • Transmission / Substation • 100 structures • 7 miles of conductor • 1 substation transformers • 7 regulators • 16 breakers 8

  10. Distribution Performance Distribution Standards Quality Processes Pole Maintenance Transmission Performance Substation Performance Weather Assessment Industry Benchmark Lessons Learned from 2005 • Retained independent outside consultant (KEMA) to examine the performance of FPL facilities during Wilma in an attempt to better understand whether transmission and distribution structures performed appropriately • Key Finding • FPL’s transmission, substation and distribution systems are designed to meet or exceed all required safety standards, and, during Wilma, performed as expected and in accordance with FPL standards • Most of FPL’s poles are designed 50% stronger than required by the NESC 9

  11. Next Steps • Evaluate recommendations from KEMA study • Develop infrastructure hardening plan –”Hardening Roadmap”. Items under consideration: • Strengthen Poles • Shorter Spans • Conductor Size • Undergrounding of Facilities • Vegetation Management • Other Design Considerations • Substation Facilities 10

  12. Questions 11

More Related