Case StudyIR Viewing of the LH Antenna Project(IRLH)Scheduling and Costing Malcolm Kear
Development of Work Breakdown Structure (WBS) • Identification of Work Package tasks • Development of Gantt Chart (Schedule) • Development of Costs • Finalising the Work Package information Case StudyIRLH Project Contents of Presentation
IRLH Project Development of Gantt Chart • Step 1 - Create Top-Level ‘Strands’ • Do NOT insert durations - these will automatically be created
IRLH Project Development of Gantt Chart • Step 2 - Create Second-Level items • Do NOT insert durations - these will automatically be created
IRLH Project Second-level WBS - Levels 2-4 - Engineering Design & Manufacture Work Packages
IRLH Project Development of Gantt Chart • Step 3 - Create Work Packages • Do NOT insert durations - these will automatically be created
IRLH Project Work Package Description Summary Sheets - WP 1.2.1.1 Do NOT enter Start and End Dates at this stage Enter name of WP Manager Define Inputs required - these may be Outputs from other WPs Define the tasks that comprise this Work Package Define Outputs from Work Package Do NOT enter Management Info. At this stage
IRLH Project Development of Gantt Chart • Step 4 - Create Work Package Tasks • Now insert task durations and interdependencies Note: Work Package Tasks can be copied from the Work Package Description Summary Sheets Durations are the TOTAL length of time it will take to do the task and can be fixed or variable. Example: Preparing a meal. Time taken to cook in the oven is fixed, whereas the time taken to prepare the meat and veg, set the table, etc is dependent of the number of people available
IRLH Project Compiling Costs • Costs are compiled ‘bottom-up’ using the Work Package as the smallest entity • 3 Cost elements are defined (Manpower, Article 7 and Purchases) BUT there can be any number and any definition • Spreadsheet automatically ‘rolls-up’ costs through WBS • The number of Man-days is the time the man will spend on the task
IRLH Project Finalise WPD Summary Sheets - WP 1.2.1.1 Enter Start and End Dates for WP from Plan Enter Management Info. From Cost Spreadsheet and SAP