An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PeopleSoft Upgrades Best Practices Tom Reznicek and Patrick Savage

  2. Save the Date APRIL 7-11, 2014 Sands Expo and Convention Center Las Vegas, Nevada QuestDirect.org/COLLABORATE COLLABORATE 14- Quest Forum is THE source for PeopleSoft roadmaps & news. It matters where you register! All PeopleSoft education and events run through Quest

  3. Agenda • Introduction of Speakers and Emtec • Project Success • Project Shortcomings and Solutions

  4. Project Successes

  5. On Time Within Budget • Kept a detailed project plan so people knew what was expected of them and when • Had regularly scheduled meetings to review plan, risks, and resolve issues • Kept upper management involved in project

  6. Final Move to Production on Time • Developed detailed task list for go-live weekend • Leveraged PeopleSoft Change Assistant • Had specific call-in times for progress reporting • Used production like hardware on the final test move to production to get accurate timing for the real move to production

  7. Latest User Data Security Migration • Developed method to migrate permission lists and roles separate from user data • Created diagrams and client deliverable to explain security migration plan

  8. Trained Two Client Resources • Resources had PeopleSoft Upgrade experience but did not execute test scripts • Allowed upgrade weekend tasks to be split between 3 people • Documented manual steps • Documented common issues and resolutions

  9. Reduced Data Conversion Time (72 hours to 42 minutes) • Identified slow processes by running Application Engine tracing and data conversion steps report • Tech leads tuned slow processes

  10. Move to Production Completed On-Time • Used job properties in Change Assistant to record time, file name, and issues • Let Change Assistant accept errors (i.e. duplicate keys) and clean after scripts run • Created go-live spreadsheet with pre and post steps • Bypassed some backups saving hours

  11. Knowledgeable Team • Technically strong and larger than previous upgrade teams • Two Emtec resources to go to with concerns • Knowledgeable Emtec PeopleSoft Upgrade Specialist • Cyber Source configured without additional Cyber Source specific consultants

  12. Prepared Microsoft SQL Server • Turned off database logging before scripts started • Monitored database file size • Added memory to database server • Set maximum memory usage on database to allow for other processes on server

  13. Updated/Validated User Guides • Guides consolidated multiple documents into one document per business area • Created process flow diagrams for requisition and PO entry • New testing documents for requisition and voucher approval, GL reports, and other processes • Created technical check printer setup document

  14. Minor Post Go-Live Issues • Extensive testing: • Leveraged existing test scripts by updating menu navigation and business process changes for version 9.1 • Last round of testing done on production hardware • End users involved in system and user acceptance testing

  15. Went Live On-Time & Within Budget • Managed issues with Excel worksheet, included owner and resolution • Assigned close action, which identified resolutions required for production and how to apply to production

  16. Functional Ch. 2 & 6 Steps Completed Quickly • Functional users completed Ch. 2 tasks to reduce the number of transactions processed • Wrote SQL statements to perform validation checks before conversion • Identified Ch. 2 & 6 steps that had to be performed for A in test moves to production

  17. Project Shortcomings and Solutions

  18. Test Scripts Not as Usable as Thought • Review test plans and scripts upfront in project • Review any work already done

  19. Canadian Payroll Customization Removed and Later Re-Added • Verify removal of customizations with the business

  20. Differing Data Conversion Hours • Ensure final test move has as much in common with eventual go-live as possible • Should have ensured three data conversion processes were able to run error-free prior to go-live to accurately gauge run time

  21. Applied Large Maintenance Pack Taking Longer in Production • Keep more careful track of how much time it takes to apply large Maintenance Pack post-upgrade so more accurate estimate could be made

  22. Initial Upgrade Pass Overlaid Delivered V9.1 Objects with V8.9 • Confirm initial upgrade pass is correct • Confirm filter that removed non-customizations is run • Confirm compare report is configured properly

  23. Go-Live Move to Production Fell Behind in Day 2 • Escalate issues faster when processes run behind schedule • Document how performance issues will be investigated and have required tools ready • Do not apply new patches after last move to production • All hand-offs should be done by phone call and e-mail

  24. Identified PM Areas for Improvement • Keep checklist from RFP to make sure everything taken care of • Some deadlines missed by project phase • Assign 1-2 people to check with everyone regarding environment restarts and refreshes

  25. Longer Testing Than Estimated • Test check printing earlier for MICR and signature fonts • Test nVision reports earlier in process • Have Hyperion environment refreshed and ready for PeopleSoft testing • Test credit card transactions through to Cyborg • After initial install, test system while consultants on-site • Test on same operating system (64 bit) as production

  26. Open Billing and Payable Transactions in Database from 2001 • Identify open transactions early in upgrade process and clean up transactions before go-live • Run Ch. 2 tasks to identify open transactions to clean up

  27. Environments Required and Migration Path Not Communicated • Define environments and naming at the start • Define migration path and how environments will be validated and kept up to date • Do not build test environment too early in upgrade • Define how performance issues will be debugged and have proper tools installed on database

  28. Wrong Initial Move to Production • Confirm the “Initial Alter Audit” is complete before starting to use an environment

  29. Application Engine Jobs Run Manually Instead of Running Change Assistant • Install PeopleSoft Change Assistant on Windows Admin Server • Workstation version does not allow for automatic processing of application engine jobs

  30. Security Migrated Twice and Custom Objects Built Twice • Apply the security after migration of custom code • Build database objects after migration of custom code

  31. Knowledge Transfer Not Completed between 1st Team and Current Emtec Team • Document what was completed by first team and what will need to be completed by second team

  32. Thank you for listening.Questions?