An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Work for Shutdown 2006/2007(2nd part of presentation) CO-TC 23.11.06 C.H.Sicard

  2. Basis • Main Shutdown Planning Milestones • Basic Front-End • Workload from Equipment groups / CO3 • HT (Timing)

  3. Planning Milestones • Based on machine shutdown schedule • Contains commitments from CO for service availability • (See Excel file)

  4. Basic FE • Hardware: • Supply/fan preventive maintenance in PS complex ( => Temporary FE unavailability) • System: • Diskless Linux FEs: from SLC3 base to SLC4 • LynxOS: none • Drivers: Solve pb on VIP626 (CTF supplies via RS422) • Configuration: • Continuation of centralisation of startup sequence in Oracle (SPS FEs)

  5. Equipment Group work/ CO3: CO3 has collected planned work from eq groups (see CO3 web page / LinksShutdown work 2006/7 This repository should contain all shutdown work implicating CO (kept up-to-date by Andy/Claude-Henri) Below is a synthetic view of this list: (excludes parallel devt during year: PS CODD, Qmea, CTF July upgrades...) • General CO work: • PS complex & SPS VME cpu upgrades • terminal servers

  6. Equipment Group work/ CO3 [1: Main injector chain] PS Complex: • BI: Lin2 sw renovation +PS BCT • PO: Lin2 (1553), PS gamma-trans, PFW • BT: new PSB Distributor • RF: PS xverse damper, LEIR RF power SPS: • BI: Wire scanners/FESA, new Cedar NA • BT: MKE Pt4 & Septa pos/FESA • BT:SPS Emergency Dumps->BIC (MI) • ATB: SPS Stoppers/Dump, NA Targets (AP) • RF: Ions Low level, 800MHz switch/CCC • ROCS/FESA?

  7. Equipment Group work / CO3 [2: Auxiliary machines: Isolde, AD, CTF..] • Isolde BI: • Grids,scanner -> get rid of Windows FECs • Rex-Isolde • Beam Profile (AP) • Ion Trap/EBIS (TBD:not in CO3 list?) • AD: • Scrapers via PLC/FESA • CTF: • PO : +more in July • Stepping motors • nTOF/MERIT: • MERIT Solenoid: new VME system • BI MTV

  8. Timing Infrastructure • Timing low level: • Upgrade VHDL & drivers in all CTRx[January] • Timing library update (?) • LHC telegram change (affects LHC FEs, not really shutdown related) • Specific Demands: • SPS Prepulse HW renovation to LHC solution • SPS Fibre distribution system renovation (=>rid of Foxcom)

  9. Diagnostic tools • Continue harmonisation work • FE startup sequences • Hw config in DB • Fully implement Front-end based diagnostics: • FIP • FESA • PLC • GM • … • Then see higher-level tools: • Xcluc • TimDiag: New Java application from April • From console level: JAPC, Directory services