State Highway Program Update Lets and Quantities Report Wisconsin Transportation Builders Association Annual Meeting – September 25, 2008 Mark Wolfgram Division of Transportation Investment Management
FY08 Financial Recap • State budget not passed until the end of October, a record 4 months late • Budget repair bill not passed until mid-May, nearly the end of the fiscal year • When the smoke cleared………
FY08 Financial Recap • Major highway program was up $7 million • SE freeway rehabilitation and local highway programs were unchanged • However, as in FY07, late resolution of financing led to a higher proportion of lets later in the fiscal year • State rehabilitation program was up $6 million over the starting budget
$4 Maintenance/Operations $792 Improvement Program Millions Final FY08 LET Level $796
Improvement Portion of Lets Exceeds Goal $792 • Main Reasons? • Assembly Budget was used to set the let goal last year • Final budget was higher $760 Let Goal Range $740 Millions
History Of Lets Millions 1023 MQ 792 745 708 662 MQ 645 639 639 606 597 534 473 442 426 416 406 403 353 331
History Of Construction Costs Index 1990=100
History Of Construction Costs Index 1990=100 Prices Up 3x 1990
History Of Lets – Constant $ Millions 413 408 363 360 352 346 345 MQ 330 331 331 328 309 MQ 297 295 284 280 280 276 263 Highway Construction Cost Index used to provide constant dollar comparison
Final vs. Estimated Quantities For FY08 Millions Even -11% Even -8% +38% (Tons) (Sq Yds) (Sq Ft) (Sq Yds) (Sq Yds)
Final vs. Estimated Quantities For FY08 Millions +40% +5% +1% Even (Cu Yds) (Tons) (Sq Yds) (Lin Ft)
Setting the FY09 Program • Update all project cost estimates to FY09 dollars • Confirm a funding level for each program • State Rehabilitation • Major Highway • SE Freeway Rehabilitation • Local Highway • Add federal earmarks and carryover balances • Subtract funding needed for design/construction delivery and contract change orders
Setting the FY09 Program • Result: State/Fed funding level for lets and non-lets in each program • Finalize schedule of lets and non-lets needed to deliver the program
Program Funds Going To Lets % Program Funds Going To Lets
Program Funds Going to Lets 66% State Highway Rehab Program Major Highway Program 58% % Program Funds Going To Lets
Setting the FY09 Program • Result: State/Fed funding level for lets and non-lets in each program • Finalize schedule of lets and non-lets needed to deliver the program • Identify contingency projects to have ready in FY09 in case they’re needed • Delivery timetable slips • Increased funding becomes available
$5 Maintenance & Operations $870-890 Improvement Program Millions Projected FY09 LET Level As of September 25, 2008 $875-895
Caveats On FY09 Let Level Funding?
Quantity Estimates Based on FY09 Program As Of September 25, 2008
Estimated Excavation Quantities For FY09 17.5 Millions Of Cubic Yards
Estimated Base Course Quantities For FY09 5.6 Millions Of Tons
Estimated Concrete Quantities For FY09 2.0 Millions Of Square Yards
Estimated Bridge Deck Quantities For FY09 2.0 Millions Of Square Feet
Estimated Asphalt Quantities For FY09 2.8 Millions Of Tons
Estimated Milling Quantities For FY09 6.6 Millions Of Square Yards
Estimated Grinding Quantities For FY09 925.0 Thousands Of Square Yards
Estimated Rubblizing Quantities For FY09 690.6 Thousands Of Square Yards
Estimated Striping Quantities For FY09 22.4 Millions Of Linear Feet
A Recap… Concrete Even Excavation +2% Milling -12% Asphalt -3% Base Course +10% Estimated FY09 vs. Final FY08 Rubblizing +6% Striping -33% Bridge Deck Even Grinding +75%
August TPC Report • 20 Major projects enumerated and in varying stages of construction • Reported an increase in cost of $321 million (2009 $) • $307 million for energy, materials and real estate • $14 million for scope and design refinements • 8 projects under study for potential enumeration
Majors Schedule As of August TPC Report Millions Of 2009 Dollars Program Level Current Schedule Of Costs = $2.48 Billion
Reschedule and Scope USH 41 Work To Interstate Standards Millions Of 2009 Dollars Program Level Costs Moving to ’16 and Beyond are Currently Unknown ? ? ?
Future Enumerations? • Program is fully scheduled over the next 6 years, maybe longer • Timing of future enumerations depends on the future rate of increase in project costs vs. the funding available