Early Delivery Systems Status

Early Delivery Systems Status. Daryl Cote. EDS Status Update. Sep. Oct. Nov. Dec. Jan. 2008. 2007. Feb. E1 R2. ICCP Fail-over / P2P. SE Verification. E2 R3. R3: SE / Telemetry Criteria (SE Tuning). Reporting. Network Model Verification. NOMCR Checkout. E2 R4.

carsyn
Download Presentation

Early Delivery Systems Status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Early Delivery SystemsStatus Daryl Cote TPTF

  2. EDS Status Update Sep Oct Nov Dec Jan 2008 2007 Feb E1 R2 ICCP Fail-over / P2P SE Verification E2 R3 R3: SE / Telemetry Criteria (SE Tuning) Reporting Network Model Verification NOMCR Checkout E2 R4 R4: NOMCR / Network Model verification 6-month LMP Posting RT ICCP E3 R5 SCED R5.1 SCED R5.2 SCED R5.3: RT ICCP SCED R5.4: LMP Post E3 R6 LFC R6.1: ACE E3 R7 CRR R7.1 E4 R9 R9 Plan to bring updated EDS 1 approach to TPTF on 12/17 for completion approval Legend: % in parentheses are from the 11/05 TPTF update TPTF

  3. Alarm Processing Approach – Expected Delivery Schedule Implementation Plan Alarm implementation is dependant on systems availability. The following table describes the implementation sequence for categories by EDS release. • EDS 1 by 12/15 • EDS 2 by 1/15 • EDS 3 by 2/15 Market Participation ERCOT is asking for 4 MP (2 QSE, 2 TSP) volunteers to help test alarm limits and to verify the ERCOT processes that respond to alarms. Email eds1@ercot.com if interested. One MP volunteer is confirmed. TPTF

  4. Release 3 – State Estimator and Telemetry Sep Oct Nov Dec Jan 2008 2007 Feb E1 R2 ICCP Fail-over / P2P SE Verification E2 R3 R3: SE / Telemetry Criteria (SE Tuning) Reporting Network Model Verification NOMCR Checkout E2 R4 R4: NOMCR / Network Model verification 6-month LMP Posting RT ICCP E3 R5 SCED R5.1 SCED R5.2 SCED R5.3: RT ICCP SCED R5.4: LMP Post E3 R6 LFC R6.1: ACE E3 R7 CRR R7.1 E4 R9 R9 Legend: % in parentheses are from the 11/05 TPTF update TPTF

  5. Release 4 - NOMCR Sep Oct Nov Dec Jan 2008 2007 Feb E1 R2 ICCP Fail-over / P2P SE Verification E2 R3 R3: SE / Telemetry Criteria (SE Tuning) Reporting Network Model Verification NOMCR Checkout E2 R4 R4: NOMCR / Network Model verification 6-month LMP Posting RT ICCP E3 R5 SCED R5.1 SCED R5.2 SCED R5.3: RT ICCP SCED R5.4: LMP Post E3 R6 LFC R6.1: ACE E3 R7 CRR R7.1 R9 Expect to start connectivity testing in 2007; actual NOMCR testing to start in 2008 Legend: % in parentheses are from the last update TPTF

  6. Release 5 - SCED Sep Oct Nov Dec Jan 2008 2007 Feb E1 R2 ICCP Fail-over / P2P SE Verification E2 R3 R3: SE / Telemetry Criteria (SE Tuning) Reporting Network Model Verification NOMCR Checkout E2 R4 R4: NOMCR / Network Model verification 6-month LMP Posting RT ICCP E3 R5 SCED R5.1 SCED R5.2 SCED R5.3: RT ICCP SCED R5.4: LMP Post E3 R6 LFC R6.1: ACE E3 R7 CRR R7.1 E4 R9 R9 Legend: % in parentheses are from the 10/22 TPTF update TPTF

  7. SCED Inputs (Telemetry and ICCP to SCADA) • AEN, AEP, BEC, BTU, CPS, LCRA, Tenaska 100% verified • Ongoing efforts: • Reliant 95% • APX 75% (covers all QSEs using APX for Telemetry) • BP 90% • Calpine 92% • Constellation 90% • Coral 100% • Exelon 85% • FPL 90% • Garland 90% • NRG 90% • STEC 90% • SUEZ 88% • Luminant 90% The status above indicates ERCOT configuration and does not reflect efforts required by QSEs. QSEs are contacted directly if ERCOT detects deltas between Zonal and Nodal or missing nodal data TPTF

  8. SCED Reports Reports are available on MIS & requires NODALTEST certificate. Developing a solution to post to nodal.ercot.com for general public (early to mid-December) TPTF

  9. Release 6 - LFC Jan Feb Mar Apr May 2008 2007 Jun E2 R4 R4: NOMCR / Network Model verification 6-month LMP Posting E3 R5 R5.3 SCED R5.4: LMP Post E3 R6 R6.1: ACE R6.2: QSE Testing R6.3: TST E3 R7 R7.1 R7.2 R7.3 R7.4 E4 R9 Legend: % in parentheses are from the 10/22 TPTF update TPTF

  10. Release 7 - CRR • Reminders – • Email eds3@ercot.com by Dec 1 if you intend to participate in Release 7 testing • NOIE - Dec 1st ’07 (PCRRs) • NOIE – Dec 1st ’07 (NOIE Load Zones) • WGRs – Dec 1st 07 (MCFRIs) • CRR Account Holder – Jan 15, 2008 TPTF

  11. EDS Deliverables  *SCED Handbook for R5.4 will require a discussion at TPTF prior to completing the handbook.  Legend: indicates completion TPTF