1 / 6

R2E Mitigation Project Status Report

R2E Mitigation Project Status Report. 2 nd R2E Committee Meeting. Follow-Ups. R2E Mandate: not required for Chamonix presentation, propose however that we reorganize the website according to committee and project (according to current understanding)

Download Presentation

R2E Mitigation Project Status Report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. R2E Mitigation ProjectStatus Report 2nd R2E Committee Meeting R2E Project Report

  2. Follow-Ups R2E Mandate: not required for Chamonix presentation, propose however that we reorganize the website according to committee and project (according to current understanding) Safe-Rooms:phased approach agreed upon -> see last slide “Benchmarking”: -> see report from Marco Layout drawings: 90% ready, whom to contact to include them into the official repository Memorandum for P5: update from RP + safe room discussion to be included -> rather a report than a memorandum? R2E Project Report

  3. R2E Highlights (Dec, Jan) Calibration, Calibration, Calibration Priority: Ready for 2012 • Detailed Analysis of 2010 Operation • RadMon, BLM & Ratios • TLD Results for low-rad readings • Analysis of losses/luminosities/intensities • Shielding & Integration • P5 close to baseline (few issues: e.g., support structure) • Opening of shielding tender (21.1.) • Shielding update for US85 • P1 issue through UX/UL wall • Power-Converter R&D • Project advancing (conceptual studies) • 1st course on radiation hard developments held (for TE/EPC) • Extensive component test campaign for 2011 (test request?) • Collaboration set up with University of Montpellier & TRAD • Safe-Rooms • phased approach developed together with EN/EL(waiting for safety input for phase-I, EN/EL for phase-II/III) • Critical point for baseline in P5 and P7 • Benchmarking (good agreements with FLUKA) • UX85/US85 • IR7 + … R2E Project Report

  4. Safe-Room Update • phased relocation approach which foresees: • a first relocation of the most sensitive control equipment (racks: EYU, EYC and EYP) • 230/48V supply from the surface (safety light + remaining 48V equipments) • AUG verification and options (surface or other location) • relocation of remaining (so-far judged low-risk) equipment, especially in case new (sensitive) components have to replace the existing equipment Reduce Risk Improve If Required Radiation Tests in H4 R2E Project Report

  5. Further • Failure Rate • 2010 Radiation Level Analysis • Update of Estimate (scary) • Interesting • Loss balance not available (so far) by OP • Many issues with quality of logging (and signals) -> difficult for anlaysis • Aiming for 50ns in 2012 (~100MJ or 1/2nom @4TeV) See Chamonix Slides R2E Project Report

  6. R2E Global Strategy & Dates • Study Phase (2008-2010) • Calculations, Early Actions, Strategy • Panic • Evaluation • Project Proposal (2010) • Testing, Evaluation, Mitigation Plan • Resources • Struggling • R2E Mitigation Project (2011-2016) • Medium Term • R&D For Long-Term • Evaluation • Long-Term • Shielding & • Relocation • P1, P5, P7, P8(+ small items) • Power-Converters • Rad-Tol Solution • SCLs • Horizontal/Vertical Links • Combination • Relocation • Rad-Tol Equipment • SCLs • (Civil Engineering) • Monitoring • Analysis, Calibration • Testing • Component & System Tests Key Dates (Status 01.2011): 02.11. (Cables)03.11. (SafeRoom1)06.11. (SafeRoom2) 11.11. (1st Test Results) 12.11. (1st CD Review) 2012 (FGCs Production) 2010 Operation06.11 (UX/UL@P1) 08.11. (CE Prestudy) 04.12 (CE Study) 10.12. (Hori-SCLs)2013 (PCs and/or SCLs) R2E Project Report

More Related