1 / 21

Production and Regional Center at NCU, Taiwan

Production and Regional Center at NCU, Taiwan. CMS-PreShower-PRR. W.T. Lin Department of Physics National Central University Chung-Li, Taiwan. Production at ERSO, Hsin-Chu. After the PHOBOS’ sensors production, ERSO’s production line had been re-modified.

chad
Download Presentation

Production and Regional Center at NCU, Taiwan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Production and Regional Center at NCU, Taiwan CMS-PreShower-PRR W.T. Lin Department of Physics National Central University Chung-Li, Taiwan

  2. Production at ERSO, Hsin-Chu After the PHOBOS’ sensors production, ERSO’s production line had been re-modified. • Mar. 2000 Integration completed • Apr. 2000 PE aligner installed • Jul. 2000 Machine warmed up • Sep. 2000 R&D runs began Capacity : 1000 wafers per month

  3. PHOBOS vs. CMS Preshower • Tracker vs. Preshower • 6 masks vs. 4 masks AC vs. DC, Double metal vs. single metal • Itotal < 5 mA @ Vfd Itotal @100 V < 10 mA vs. Itotal@300V < 10 mA • Completed vs. On going project • 450 sensors vs. 1200 sensors

  4. PHOBOS Sensor Technology bias bus signal lines metal 2 1.2um ONO vias metal 1 0.2um ONO Double Metal, Single sided, AC coupled, Polysilicon biased p+ Implant Polysilicon Drain Resistor 300mm 5000kW-cm n+ TestKeys PN junction Thin ONO Thick ONO Polysilicon

  5. IV curve of PHOBOS sensor More than 450 wafers have been delivered. Vfd=60V 5mA

  6. Preshower Detector Layout Test key Silicon Detector 63 mm

  7. Structural Drawing Passivation Metal Strip Field oxide P+ strip i-type substrate N+ layer Metal

  8. CMS Si-Sensor R&D • Depth of p+ and n+ : 3, 5, and 14 mm • Thickness of Al :1.2 mm • Passivation : nitride + oxide 1.2 mm p+ Al Passivation n type (1,1,1) 320mm n+

  9. Pilot runs & Pre-productions Date batch# wfrs 6/5 cms01 24 6/5 cms02 24 6/15 cms03 24 6/18 cms04 24 6/18 cms05 24 6/15 cms06 24 Date batch# wfrs 10/27 90074 12 10/28 90075 12 1/15 90074A 12 3/2 90075A 12 3/16 00017 12 3/2 00018 12

  10. Summary of IV/CV tests Date batch# depth of n+ majority I@V>Vfd 6/5 cms01 14 mm 50-150 nA/strip 6/5 cms02 50-150 nA/strip 6/15 cms03 5 mm 100-150 nA/strip 6/18 cms04 50-100 nA/strip 6/18 cms053 mm 250-350 nA/strip 6/15 cms06 300-400 nA/strip • More than one strip have high leakage current that sensor • can not be accepted. • 20 accepted sensors : 17 from 03 and 04, 3 from 01 and 02 • 23oC, Cstrip=38 - 42 pF, Vfd= 80 - 120 V

  11. Flow Chart of Testing 1) Sensor received 2) Visual scan 3) Pre-screening : CV, IV 4) sensor dicing 5) Select good sensor for assembly : CV, IV • Write to the data base during the test • CV+IV measurement takes about 20 min/wfr

  12. Wafer Dicing 45o down view Diamond saw : 30 mm Spinning : 35K rpm Speed : 40 mm/sec 35mm P+/top side 300mm 210mm Side view IV curves unchanged after dicing

  13. Production Plans Milestone of delivery • Jun 2001 20 pcs • Dec 2001 130 pcs • Jun 2002 150 pcs • Jan 2003 900 pcs ERSO capacity : 1000 wfrs/month

  14. Equip. for Tests & Assembly • Probe card, Switch board, HV isolation • IV(K236), CV(K590), and HVps(K237) • Single channel probe station • Bonding machine (Kulicke Soffa 4123) • Visual scan station • Jigs will be ordered from CERN

  15. Setup at Regional Lab. IV/CV meters (NCU and ERSO) Visual scan and Bonding machine in 30 m2 clean room

  16. Time consuming and Manpower • 150 working days for measurement : (Base on 50% of yield, 20 min/wfrs, deliver 1200 wfrs) • 2 technicians + 1 Ph.D. student (extra technician + 2 master students will join when assembly starts)

  17. Summary • IV/CV test benches have been set and tested at NCU and ERSO. • CRISTAL data base has been set and tested. • ERSO and Miracle co. are trying to improve the yield

More Related