An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Oregon State UniversityFSI Teleconference Wade Marcum 6/30/2014

  2. Experimental Work • Recall (02/28/2014 presentation) • GTPA Flow Testing • …to Partially Complete During FY 14 • MP-1 Testing • …to Fully Complete During FY 14

  3. Experimental Work • Recall (02/28/2014 presentation) • GTPA Flow Testing • Ran into issues with strain gages during FY 13 and 14. • Used a decision tree process to down-select hardware independent variables to seek resolution. • Have preliminarily identified the appropriate hardware (strain gages and protective coating) that meets our required testing. • Have ordered strain gages and will arrive in week 3 of July • SHOULD satisfy all remaining items for GTPA prior to testing

  4. Experimental Work • Recall (02/28/2014 presentation) • MP-1 Testing • Have to modify test section to provide lower flow rate range, including • Bypass leg • Flow straightener • Test section piping • Appropriate Instrumentation • 4 x TCs • 4 x Accelerometers • 2 x Flow Meters • 1 x flow control valve

  5. Experimental Work • Recall (02/28/2014 presentation) • MP-1 Testing • Timeline • Contract Date 02/15/2014 • Fab Contract 04/04/2014 • Prelim Design 05/15/2014 • Design Review 05/21/2014 • Aprvd Design 05/26/2014 • Fab Completion 06/13/2014

  6. Experimental Work • Recall (02/28/2014 presentation) • MP-1 Testing • Timeline • Contract Date 02/15/2014 • Fab Contract 04/04/2014 • Prelim Design 05/15/2014 • Design Review 05/21/2014 • Aprvd Design 05/26/2014 • Fab Completion 06/13/2014 • Fab Install 06/18/2014 • V&V of Install Present • Baseline Change 07/28/2014 • Recv Hardware 08/03/2014 • Matrix Testing 08/18/2014 Estimated Projection Dates

  7. Theoretical FSI Work • Can we solve these complex problems with relatively simple tools? • Matlab Script • Structural Domain • Wide-beam theory of heterogeneous plate

  8. Questions?