An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Southeastern Inter-Regional Planning Update (SIRPP) Entergy Transmission SummitAugust 11, 2009Astor Crown PlazaNew Orleans, Louisiana

  2. Presentation Overview SIRPP: Southeast Inter-Regional Participation Process • www.southeastirpp.com

  3. SIRPP consist of the following members: • Southeastern Region (SERTP) • PowerSouth • Dalton Utilities • Georgia Transmission Corporation (GTC) • Municipal Electric Authority of Georgia (MEAG) • South Mississippi Electric Power Association (SMEPA) • Southern Companies • Duke Energy Carolinas • Entergy Companies • E. ON U.S. • Progress Energy Carolinas • Santee Cooper • South Carolina Electric & Gas (SCES) • Tennessee Valley Authority (TVA)

  4. SIRPP Activity • November 13, 2008 – Stakeholders Conference Call to discuss study scope • March 16, 2009- Stakeholders Conference Call to finalize scope of revised study • August 19, 2009- Review/Present Report of Step 1 Study Results to Stakeholders • Q4 2009- Final Posting of Step 1 • Q1 2010- Process for Step 1 and 2 begins

  5. STEP 1 Study Assumptions • Methodology • Run Study Case (A) without transfer, and (B) with transfer. Each Transmission Owner applies TPL criteria to identify upgrades in Case B vs. upgrades in Case A. • Upgrades associated with Transfer • Compare Case B vs. Case A to identify any upgrades at 115 kV and above • Comments : • Upgrades are identified by each Transmission Owner that experiences a flow impact using its TPL criteria. Upgrades would be identified independent of any ultimate contract path selected

  6. Stakeholders Comments to Transmission Owners on the Five Economic Scenarios • Stakeholders would like each scenario to be looked at in a way that identifies the upgrades needed on the collective SIRPP systems to accommodate the requested economic transfer. • The stakeholders are looking for a flow-based analysis as opposed to a contract path based analysis. • For example, on the requested 3000 MW PJM Classic to SOCO transfer, simulate a 3000 MW generation increase in PJM Classic and 3000 MW generation decrease in SOCO and determine: • How the 3000 MW of flow distributes across the system (i.e., how much flows through TVA, though Duke, through Entergy, through systems outside the SIRPP, etc.) • What are the limitations / associated upgrades identified on the SIRPP systems

  7. SIRPP Step 1 Economic Studies for 2008/2009 GA Integrated Transmission System (GAITS) 2000 MW Entergy 3000 MW PJM (classic) Southern Company 2000 MW PJM (west) Southern Company 3000 MW Southern Company PJM (classic) 5000 MW SPP SIRPP

  8. For additional information or to sign up to be part of SIRPP: www.southeastirpp.com

  9. Southeast Regional Transmission Planning Process (SERTP) • December 16, 2008 – Final 2008 study results were presented at Southeast Transmission Summit – available on SERTP website: http://www.southeasternrtp.com/ • March 25, 2009 – 2009 transfer studies selected • Savannah > GA 60%, AL 20%, MS 20% - 1000 MW • Gulfport > Georgia - 1000 MW • Ties to SCEG > Georgia - 1000 MW • Murray 500 > Florida Border - 650 MW • Washington County > Georgia - 5000 MW • June 24, 2009 – Presentation of Southeast Expansion Plan • 2009Q4 – Final 2009 study results will be presented at the Southeastern Transmission Summit – date/location TBD

  10. Eddie FilatSenior Engineer, ICT Planning501-688-1708efilat@SPP.org Questions / Comments