CERN modulator R&D Pulsed High Power Modulators. 09/03/2010. Modulator Roadmap. The CERN Electrical Power Converter group is starting a study on high-power modulators to investigate Appropriate modulator technologies Detailed design of critical sub-systems

chaz
Download Presentation

CERN modulator R&D Pulsed High Power Modulators

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CERN modulator R&DPulsed High Power Modulators 09/03/2010 CERN Pulsed Power Modulators

  2. Modulator Roadmap • The CERN Electrical Power Converter group is starting a study on high-power modulators to investigate • Appropriate modulator technologies • Detailed design of critical sub-systems • Prototype evaluation of key sub-systems • Objectives • Propose well evaluated technical solutions for future accelerator requirements, in particular HP-SPL and CLIC • Provide estimates of cost, volume and other pertinent data • The project is structured such that a working modulator prototype for SPL or CLIC could be envisaged for ~2014 CERN Pulsed Power Modulators

  3. Development directions • Appropriate modulator technologies • Detailed design of critical sub-systems • Prototype evaluation of key sub-systems • Pulse transformers • HV Transformers • Pulse-to-pulse stability • Ripple characterisation (HF and LF) and compensation • Cost effective chargers • ‘Most efficient’ topologies (eg resonant topologies )? CERN Pulsed Power Modulators

  4. R&D Planning… CERN Pulsed Power Modulators

  5. Collaborations • We need to collaborate to create a modulator: CERN Pulsed Power Modulators

  6. Collaborations • Partnerships for medium term – what could be envisaged? • Contract between EPC and Researcher OR CERN and University? • Can multiple partnerships work together (eg Nottingham has experience of SNS and resonant topologies)? • Partial funding from national bodies? CERN Pulsed Power Modulators

  7. R&D Planning… CERN Pulsed Power Modulators

  8. Objectives • Select topology and justify decision: May 2010 • Dimensioning model for 1 (or more) topologies: June 2010 • For main components • Full simulation of selected topology: November 2010 • Design of main magnetic component(s): Oct 2010 • Design of main power electronics: May 2011 • Reduced power prototype: Oct 2011 CERN Pulsed Power Modulators

  9. Objectives - documentation • Internal papers • Pulsed modulator topologies (Draft: May 2010) • High Voltage Pulse Transformers (Draft: May2010) • Models for dimensioning pulsed power modulators (Draft: May 2010) • … • Conference paper(s) at one (or more) of: • PAC 2011, New York, USA, 28/3 — 1/4 • IPAC 2011, Spain, 1/9 – 6/9 • EPE 2011, UK, 30/8 – 2/9; Abstract: 1/11/2010 CERN Pulsed Power Modulators