An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Blade Fold & Prepare for shipment by C5

  2. Blade Fold • Prep for shipment. • Blade fold • Tail rotor • Main rotor • Struts • Main • Tail

  3. Prep for shipment.(con’t) • Stabilator • Step fairings • Install tow plates

  4. M/R Fold • Alignment of Swashplate • Line up yellow index • Inbd T/R horizontal (If The swashplate is not lined up you will not be able to put in the support pole )

  5. Take all commands from the guy on the head

  6. M/R Fold • Fwd left (red) • Fwd right (black) • Aft left (blue) • Aft right (yellow)

  7. Take all commands from the guy on the head

  8. T/R Fold • Remove 12 OTBD RET plate bolts • Remove balance washers • Install both on star plate and hang as they came off • Disconnect P/C rods at pitch beam& deice • Rotate • Pad

  9. Struts Connect HYD cart before opening kneeling valve!

  10. Struts • Main • Hyd cart. • Lower stage only. • Record exposed strut. (eliminates servicing) • Raise cargo floor to 30 inches.

  11. Struts Connect HYD cart before opening kneeling valve!

  12. Struts • Tail • Remove tail access panel. • Record exposed strut. • Lower until no silver showing. • If tail loaded first upper stage may need to be lowered requiring complete servicing.

  13. Struts Connect HYD cart before opening kneeling valve!

  14. Tow plates • Remove step fairing • Install & torque bolts on tow plate • 1 left & 1 right • Rotate WSPS

  15. STAB • Remove tail cone!!!!! • Remove STAB and rack it

  16. Antenna • Remove FM whip • Stow lower anti-collision light

  17. FODCONTROL • BAG ALL PARTS • Attach bag to ACFT or in fold box • Step fairing screws and stab bolts end up missing • T/R star plates attach and label to acft • Tools