Copper Stabilizer Continuity Measurement Project

Copper Stabilizer Continuity Measurement Project. Copper Stabilizer Continuity Measurement Status & Plans – May 2011. MPE-TM – 12 May 2011 M. Koratzinos, J. Steckert, H. Thiesen, A. Verweij. Contents. Description of CSCM tests (Arjan) Status and Plans (Hugues) mQPS (Jens).

Download Presentation

Copper Stabilizer Continuity Measurement Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Copper Stabilizer Continuity Measurement Project Copper Stabilizer Continuity Measurement Status & Plans – May 2011 MPE-TM – 12 May 2011 M. Koratzinos, J. Steckert, H. Thiesen, A. Verweij

  2. Contents • Description of CSCM tests (Arjan) • Status and Plans (Hugues) • mQPS (Jens)

  3. CSCM Objectives • Objectives of CSCM tests • Concerned circuits: RB, RQD and RQF • Determine the max. safe energy of LHC (4 - 5 TeV) • Other limitations (LHC non conformities) • RQX.R1 • RB.A78 (B30R7) • Other limitations ? (to be defined) • Assumptions • Time constants of the EE systems • 4 TeV: RB = 51 s, RQ = 10 s • 4.5 TeV: RB = 68 s, RQ = 15 s • 5 TeV: RB = 68 s, RQ = 15 s • No defect on the diode path

  4. CSCM Tests • CSCM current cycle (see Arjan presentation) • Heat the defect to identify it (runaway) Temp : 20 K Current : 4 kA – 6 kA Time : 10 s – 50 s Max T : 200 K Interlock = protection = stop the tests at the beginning of the runaway before destroying the splice interlock RB busbar 20 K – 6 kA 52 uOhm 0.2 s 50 mV mQPS threshold

  5. CSCM Tests • CSCM protection system (see Jens presentation) • 3 elements have to be protected • Splice = mQPS • Diode path (or magnet) = Qsym • CL = Qcl Qcl (CL at nominal operating conditions) Qsym mBS 20 K

  6. CSCM Tests • Power Converters • Use the same power converters for the 3 circuits (RB) • Voltage budget (RB): • 20K • Vdiode_rb # 265 V and Vdiode_rq # 90 V (Vdiode # 1.7 V @ 20 K) • Vdc_cable # 10 V @ 6 kA • Vbusbar_rb # 15 V @ 6 kA and Vbusbar_rq # 30 V @ 6 kA 280 - 290 V @ 20 K

  7. CSCM Tests • Power converter resources (20K) • 2 RB bridges in series

  8. CSCM Tests • RB circuit powering configuration RB Fip RB Pic RB RB Ext RB Earth

  9. CSCM Tests • RQ circuit powering configuration RB RB Earth RQ Fip RQ Pic RQ RQ Ext

  10. CSCM Test campaign • Sequence (1 sector): • Preparation: 1 week – 1 shift • QPS: 4 persons – 5 days/1shift • Disable QPHS, oQPS, Qsym and EE system • Install mQPS boards • IST of the mQPS • Cryogenic: • Empty the sector • Warm up and stabilize the sector at 20 or 40 K • PC: 2 technicians – 5 day/1shift • Modify the RB converters (2 days) • IST of PC (2 days) • PIC: • PIC tests w/o current # 6 persons during 1 week (1 sectors)

  11. CSCM Test campaign • Sequence (1 sector with 1 PC): • Powering tests: 7 days/2 shifts (2 weeks for the 1st sector) • ElQA: 2 persons – 1 day (M) • RB commissioning: 4 persons – 1 day (A) (2-QPS, 1-PC, 1-Cryo) • RB tests: 4 persons – 1 day (A) • Connect the RB PC to RQD circuit: 3 persons – 1 day (M) (1-QPS, 2-PC) • RQD commissioning: 4 persons – 1 day (A) • RQD tests: 4 persons – 1 day (A) • Connect the RB PC to RQF circuit: 3 persons – 1 day (M) (1-QPS, 2-PC) • RQF commissioning: 4 persons – 1 day (A) • RQF tests: 4 persons – 1 day (A) • Data analysis: 2 persons – 5 days (M) # 7 persons during 7 days and 2 shifts (1 sector) M = morning A = afternoon N = night

  12. CSCM Test campaign • Sequence (1 sector): • Recovery (w/o cryo): 1 week – 1 shift • Reinstall old BS board and enable oQPS, Qsym and EE system • IST of QPS • Reconfigure the RB power converter • IST of RB power converter • ElQA • Full recommissioning of the main circuits # 6 persons during 1 week (1 sectors) w/o powering tests

  13. CSCM Test campaign • Schedule: # 10 weeks (2 sets of test boards) # 1st RB # 1st RQ Preparation = 3 persons – 5 days – 1 shift Tests = 7 persons – 7 days – 2 shifts Recovery = 3 persons – 5 days – 1 shift (w/o cryo and powering tests)

  14. CSCM Test campaign • Schedule: # 8 weeks (3 sets of test boards) # 1st RB # 1st RQ Preparation = 3 persons – 5 days – 1 shift Tests = 7 persons – 7 days – 2 shifts Recovery = 3 persons – 5 days – 1 shift (w/o cryo and powering tests)

  15. CSCM Status and Plan • Status: • Today the limits of the CSCM tests are defined • Circuits (magnet and DFB) at 20 K • Current leads at nominal operating conditions • Current cycle (4 or 6 kA) • Protection system (mBS, Qcl and Qsym) • Powering system (RB converter with both bridges in series) • Test campaign

  16. CSCM Status and Plan • Planning: • First draft meeting: 8 June 2011 • Second draft meeting: 22 June 2011 • Internal review: 29 June 2011 • Type test in RQ circuit: September 2011 • Tests campaign: December 2011 – February 2012