Baltimore County Public Schools. Schematic Design Presentation Catonsville Elementary School at Bloomsbury. 1104 Kenilworth Dr. Suite 500 Towson, MD 21204 (410) 337-2886 fax (410) 337-2974 www.rubeling.com. Aerial Location View. Overview and Comparison Existing Catonsville E.S.
E N D
Baltimore County Public Schools Schematic Design Presentation Catonsville Elementary School at Bloomsbury 1104 Kenilworth Dr. Suite 500 Towson, MD 21204 (410) 337-2886 fax (410) 337-2974 www.rubeling.com
Overview and Comparison Existing Catonsville E.S. & Proposed Catonsville E.S. at Bloomsbury Current C.E.S.Proposed C.E.S. Site 6.16 acres 11.8 acres SRC 405 700 Current Enrollment 445 Bus Loop 2 8 Parking 68 150 Building Size 59,600 sf 103,000 sf Historic Structure Yes Yes Original Construction 1909 1925 Additions 1929, 1934, 1970 1930-1962 (additions removed 1990) Converted to County Building N/A 1980’s Current Use Elementary School Bureau of Elections Recreation & Park
Existing Bloomsbury Site 1930’s Building 1990’s Gymnasium
EXISTING SITE PHOTOS 1930’s Building 1990’s Gymnasium
Site & Grading Plan ENTRY ENTRY
Project Objectives • Restore Historic Features of the Original 1925 Building • Interior Renovation and Addition to Convert Building to a New 21st Century Learning Facility • Incorporate Facility Upgrades to Support the Instructional Environment for Students • Provide All New Building Systems • Provide Building Security and Address Student Safety • Address all Code, ADA and Life Safety Issues
GROUND FLOOR 1ST GRADE CLASSROOMS (TYP) KINDERGARTEN PRE-K PARENT DROP OFF GROUND FLOOR
GROUND FLOOR STAIRS (TYP) ELEVATOR GROUND FLOOR
FIRST FLOOR CLASSROOMS (TYP) MEDIA CENTER ENTRY MAIN FLOOR
FIRST FLOOR STAIRS (TYP) ELEVATOR MAIN FLOOR
SECOND FLOOR CLASSROOMS (TYP.) SECOND FLOOR
Summary of Improvements Curriculum: • The building interior will be new and designed to current curriculum and building standards and will meet BCPS and State of Maryland’s Standard for Technology. Building Envelope Improvements: • Replace existing roof. Code Improvements: • Install elevator to access all levels. • All new doors and hardware to be in compliance with current code. • New restrooms to comply with ADA guidelines. MEP System Improvements: • New mechanical system to all year round climate control thru central heating and cooling. • New lights to meet BCPS standards and building code. • New light controls. • New intercom and clock system.
Project Schedule Design March 2014 - February 2015 Bid & BCPS Board Meeting February 2015 - April 2015 Construction May 2015 - July 2016 Opening August 2016