1 / 20

Muon Campus Projects Mary Convery

Muon Campus Projects Mary Convery. Background on Muon Campus plan. Earlier Plan had 5 Common Projects:  MC1 Building (GPP) MC Beamline Enclosure (GPP) MC Site Preparation (GPP) MC Cryo Plant (AIP) MC Delivery Ring Upgrades (AIP) This plan has evolved in response to

cicily
Download Presentation

Muon Campus Projects Mary Convery

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Muon Campus ProjectsMary Convery

  2. Background on Muon Campus plan • Earlier Plan had 5 Common Projects:  • MC1 Building (GPP) • MC Beamline Enclosure (GPP) • MC Site Preparation (GPP) • MC Cryo Plant (AIP) • MC Delivery Ring Upgrades (AIP) • This plan has evolved in response to • Recommendations made at Mu2e DOE CD-1 review • Maturing designs for (g-2) and Mu2e • Recycler AIP was added in response to DOE recommendation and includes scope that was originally part of the g-2 project • Scope of Site-Prep GPP changed in response to DOE recommendation that resulted in acceleration of Mu2e civil construction schedule • Muon Campus projects plan actively orchestrated and managed via regular program meetings • Although the packaging of the projects has been in flux, most of the individual jobs to be done are well-known and mature • Aiming for Director’s review of full program in next few months

  3. Beam path to Muon Campus

  4. Aerial view Recycler Ring g-2 Target Station Beam Transfer and Delivery Ring MC1 Mu2e Muon Campus

  5. MC-1 GPP • MC-1 building to house g-2 and future experiments, cryo system for g-2 and Mu2e, and power supplies for some beamline components • 80’ x 80’ high-bay with 30 T crane • internal loading dock • floor stable, load-bearing to 700 T • good temperature control • 70’ x 70’ low-bay for staging, assembly, control room • Includes extension of existing communication duct to replace duct which is interrupted during tunnel excavation

  6. MC-1 GPP WBS Total cost expected to be $9M, costing is mature

  7. Beamline enclosure GPP • Civil construction of enclosures for M4 and g-2 extraction lines • Delivery Ring to Mu2e – M4: 10’ wide x 8’ high concrete box type enclosure with 16’ equivalent earth shielding. Base slab at El:728’-8”. • M4 line to g-2: 8’wide x 8’ high enclosure. Base slab slopes from El: 728’-8” to El 734’-6”. • Beamline power supplies from AP-30, g-2 and Mu2e. Low Conductivity Water extended from Delivery Ring. • Includes lighting, grounding, electrical power distribution, cable tray, fire detection, life safety egress, drainage and sumps. Installs beam abort.

  8. Beamline enclosure GPP WBS Current estimate $9.2M, could increase as plans become better defined (beamline design still in progress)

  9. A-0 Cooling Pond • Civil construction to renew the A-0 pond heat rejection capacity and provide capacity for the 13.8 kv feeder from Master Substation to F-3 Switch. • A-0 Pond – Restore pond depth to the original profile; replace pond pumps and intake; relocate and replace discharge. • 13.8 KV Electrical Upgrade – Install new feeder (24B) in existing Main Ring duct bank from Master Substation to the F-3 Switch Costing still in progress

  10. Site prep GPP • Originally (early 2012) the Site Prep GPP included: • removal of an old spoils pile • relocation of KautzRd • installation of an additional power feeder • Issues since then: • items 1) and 2) above need to be accelerated in order to accommodate accelerated Mu2e civil construction schedule • items 1) and 2) above total ~$2M, not in lab's FY14 budget • unclear feeder is needed: the estimated (g-2)+Mu2e needs are on the edge of current capabilities and carry a large uncertainty • Current plan    • eliminate this GPP? • move items 1) and 2) to Mu2e project • Mu2e funding profile can accommodate this • will identify scope to swap out of Mu2e • revisit need for feeder once beamline designs are more mature and power needs can be estimated more accurately • if needed, would require funding in FY16-17 to be ready for Mu2e solenoid commissioning in late FY17

  11. Cryo AIP piping headers • Compressor and refrigeration systems • g-2 and Mu2e cryogenic distribution system • Reuse Tevatron compressors at A0 • Compressed He line from A0 to MC-1 building • Refurbish Tevatron refrigeration components to be housed in MC-1 building • 4 refrigerators to support simultaneous steady-state operation of both g-2 and Mu2e • Cold lines extending to both experimental halls to A0

  12. Cryo AIP WBS Total cost $9.8M, contingency is well understood

  13. Recycler AIP • Allows 8 GeV proton beam to be rebunched in the Recycler and extracted to the P1 line for transport to experimental areas • 2.5 MHz RF for re-bunching beam • Extraction kickers • Beamline connection from Recycler to P1 line • MI52 building extension for kickers (civil – move to separate FESS project?) • RF cavity production • Cavities must have active cooling • Reuse ferrites from MI coalescing cavities • Labor intensive • 7 RF systems (cavities + PA’s) for Recycler • 2 cavities for Mu2e to be installed in the Delivery Ring 13

  14. Recycler AIP WBS Costing and scheduling in progress, costs of some pieces are well-known

  15. Delivery Ring and Beam Transport AIP • P1, P2, M1 line aperture improvements for 8 GeV beam • DR injection • DR aperture improvements • Removal of unneeded devices such as stochastic cooling tanks • DR abort • Beam abort for Mu2e • Proton removal for g-2 • DR and beamline instrumentation needed for both Mu2e and g-2 • Electrical infrastructure improvements DR injection area 15

  16. Delivery Ring AIP WBS Unescalated costs well understood, scheduling in progress, current estimate $9.5M

  17. Timeline

  18. Current funding plan for GPPs and AIPs on critical path for g-2 • The additional site power feeder that was part of site-prep GPP ($1M) is not included here, may be needed in 2017 or 2018 longer lead time for RF on critical path for g-2

  19. Status of Muon Campus project plans • Preparing for comprehensive Director’s review in next few months

More Related