Muon Campus Projects Jerry Annala Jan 23, 2013
AIP Scope • Recycler RF system to provide needed bunch structure to future Muon Experiments • Recycler Extraction system and connection to P1 beam line • Primary beam line aperture improvements • Beam line power supply upgrades
Scope • Secondary beam line connection to Delivery Ring • Delivery Ring injection • Delivery Ring abort system • Delivery Ring extraction systems • Collider equipment removal • Delivery Ring power supply upgrades • Infrastructure (building electrical) • Instrumentation upgrades
Schedule constraints • Availability of funds • Project Milestones • Accelerator schedule (Neutrino Program) • Length of tasks • Availability of resources
AIP/GPP spending profile Required t o meet g-2 field shimming schedule Need to fill in funding and meet g-2 start date Required to meeting Ring shipping schedule Required installation during Accelerator Shutdowns
Additional considerations • Period following present NOvA shutdown will be last opportunity to run beam prior to major reconfiguration • Controls to rings should be re-established before being interrupted by beam line construction • Savings to the lab possible by starting kicker controls work to coincide with Booster kicker work
Additional Considerations • Early completion of beam line from RR to AP0 target would allow early commissioning and characterization • Long duration for tasks such as septa and kicker PS • Manpower availability may impact schedules based on these other considerations
Costs Originally made up Recylcer AIP
Long term CD-schedule G-2 MC-1 Building Mu2e Hall Tunnel Enclosure CD-1 CD-3a CD-3c CD-2/3b CD-4 Accelerator Shutdown Accelerator Shutdown Accelerator Shutdown Accelerator Shutdown Accelerator Shutdown Mu2e Accelerator Shutdown Operation FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 g-2 Operation CD-2/3b Area of concentration CD-0 CD-1/3a CD-4 Conflict of concern CD-3c
Milestone driven schedule items MC-1 Building Tunnel Enclosure Cryo AIP A0 Pond Would have to be part of AIP Ring Controls g-2 AP30 Cryo Room Mu2e CD-4 CD-3a CD-2/3b CD-1/3a CD-3c CD-2/3b Accelerator Shutdown Accelerator Shutdown Beam stud Accelerator Shutdown Beam studies FY13 FY14 FY15 FY16
Accelerator driven schedule MC-1 Building Tunnel Enclosure P1 stub line RR Extraction kicker MI52 Extension Recycler RF g-2 Beamline aperture Mu2e CD-4 CD-3a CD-2/3b CD-1/3a CD-3c CD-2/3b Accelerator Shutdown Accelerator Shutdown Beam stud Accelerator Shutdown Beam studies FY13 FY14 FY15 FY16
Costs based on externally driven schedule Resource limited year Funding limited years
Notes • Nothing planned to pay for storage or disposal of anything other than cable • We think we have done all the value engineering possible. • Still need to establish activities to allow proper tracking. • Magnet factory can do all of the individual jobs, but can they fit all of them in the available time
Conclusion • Many non-technical factors will drive the schedule • Funding profile will make meeting schedule difficult • Original AIP funding packages are too close to (or beyond) spending limits • Complete involvement of Muon Dept. makes for good coordination, but will be source of some conflicts