1 / 58

Undulator Magnets and Supports 20 February 2006 APS All Hands Meeting

Undulator Magnets and Supports 20 February 2006 APS All Hands Meeting. Long-Lead Procurements Titanium Strongbacks 1.04.03.03.01 Magnet Blocks 1.04.03.03.02 Magnet Poles 1.04.03.03.03 1 st -Article Undulator Assemblies 1.04.03.03.04 Single Undulator Test. Michael Bracken

cissy
Download Presentation

Undulator Magnets and Supports 20 February 2006 APS All Hands Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Undulator Magnets and Supports20 February 2006APS All Hands Meeting • Long-Lead Procurements • Titanium Strongbacks 1.04.03.03.01 • Magnet Blocks 1.04.03.03.02 • Magnet Poles 1.04.03.03.03 • 1st-Article Undulator Assemblies 1.04.03.03.04 • Single Undulator Test

  2. Michael Bracken Loretta Cokeley Jeff Collins Alex Didenko Patric Den Hartog* Mark Erdmann Horst Friedsam Glen Lawrence Dan Nocher Tom Powers Brain Rusthoven Sushil Sharma* Emil Trakhtenberg Kurt Boerste Roger Dejus Elizabeth Moog* Shigemi Sasaki Ken Thompson Janet Werner Isaac Vasserman Dana Capatina (DD) Ron Kmak (DD) Thomas Barsz (QA) Marion White (CAM) * = Group Leader Undulator Magnets & Supports Team (significant % but none full time)

  3. LLP – Titanium Strongbacks • Require forty (40) 3.4-m-long titanium bars: Forged, annealed, vibration-stress-relieved, rough machined, vibration-stress-relieved, precision machined, inspected… • Competitively bid and awarded to two vendors to reduce risk: • Metalex [Blue Ash, OH] • Dial Machine [Rockford, IL]

  4. LLP - Titanium Strongback 1.04.03.03.01

  5. LLP – 40 Titanium Strongbacks • Total cost about 4M$ • Some growth in the raw materials cost was anticipated – but… • All material is under contract, but finding it... • 95% of titanium is used to make pigment; only about 5% is made into metal; titanium supplies are under very high pressure due to: • Civilian and military aircraft, other military applications, a very hot market in Asia…

  6. Excellent Work by Metalex – 1st Article was site-accepted by ANL on 17 October 2005

  7. Rough Machining #2 @ Metalex - 10th October

  8. 01 Feb: Metalex is ahead of schedule • S/N: 5A06990-02 Complete and Staged for Assembly • S/N: 5A06990-04 Complete and Staged for Assembly • S/N: 5A06990-06 Complete and Staged for Assembly • S/N: 5A06990-08 Complete and Staged for Assembly • S/N: 5A06990-10 Complete and Staged for Assembly • S/N: 5A06990-12 Complete and Staged for Assembly • S/N: 5A06990-14 Complete and Staged for Assembly • S/N: 5A06990-16 Complete and Staged for Assembly (The P3 date for #16 is May 24th 2006) • S/N: 5A06990-18 At machining Oper#100 • S/N: 5A06990-20 At machining Oper#100 • S/N: 5A06990-22 At machining Oper#100 • S/N: 5A06990-24 At machining Oper#100

  9. Metalex – Forging Deliveries • ATI Wah Chang plans delivery of the balance of (8) forgings to Metalex: • (4) by the end of February 2006. • (4) by the end of March 2006. • We are keeping a close eye on this, but they are so far ahead of schedule that it is unlikely to be a problem.

  10. Titanium Strongbacks – Progress@Dial 1st Article – site-accepted - 10 Nov 2005 • 10 forgings in house now. The remaining 10 are slated for shipping to Dial on Feb 20th, 2006. • Processing Strongbacks: rough machine, semi machine, drill, & tap; then inspect on the CMM before final dust mill of channel surfaces. • They will inspect, clean, deburr, and prepare for shipment; they expect to ship #3 to Hi-Tech about Feb 13th, and then about one per week for four weeks. Their bottleneck is in waiting for inspection. P3 Date Dial Date Status 07 Feb 2006 • #3 13 Jan. 2006 06 Feb. 2006 ANL Accept 07 Feb. 2006 • #5 13 Feb. 2006 10 Feb. 2006 machined, wait for insp. • #7 14 Mar. 2006 17 Feb. 2006 machined, wait for insp. • #9 12 Apr. 2006 24 Feb. 2006 machined, wait for insp.

  11. First-Article Strongback Site-Acceptance at Dial Machine, Rockford, IL – Well done !!!

  12. Titanium Strongbacks – Progress@Dial - roughing

  13. Magnet Blocks 1.04.03.03.02 • 19,200 Neodymium Iron Boron magnet blocks - about 1M$. • Magnets are fabricated in Shin-Etsu’s Takefu Plant in Japan, ground to final precise dimensions, plated for surface protection, magnetized, labeled, sorted by magnetic field, and divided into undulator-sized lots. http://www.shinetsu-rare-earth-magnet.jp/e/masspro/index.shtml details the process. • Precise sorting by magnetic field must be done, then a spreadsheet is given to the assembly vendors listing the magnet serial number and orientation for each magnet in each slot.

  14. LLP - Magnet Blocks 1.04.03.03.02 Magnetic verification of the first sample lot of magnets at APS • Initial problems • More shrinkage than anticipated • Problem with Ni plating • Magnets packed with Ink wet • All resolved • 10 sample magnets from 1st two lots were tested • Magnetic & dimensional measurements were verified. • Lots 3&4: approved to ship • Lots 5&6: samples selected and shipped to ANL • ANL magnet expert visited Shin-Etsu 24-26 Jan.

  15. 1st 2 Lots: Magnet Blocks look good Field measurement of first 10 blocks compared to the measurements from Shin-Etsu. The slight reference offset is understood. Angular direction measurement of the first 10 blocks compared to the measurements done by Shin-Etsu

  16. Schedule - Magnet Blocks 1.04.03.03.02 • The first shipment of 960 magnets, enough for both of the 1st-article undulators, finally was delivered to the assembly vendors on the 3rd of January 2006. Later than planned. • We were told to expect a faster delivery rate after the new production line, installed to meet increased global demand for these high-quality magnets, began operation in December 2005. • Met with Shin-Etsu 17 January 2006 @ANL.

  17. Magnets received at Metalex 3rd January

  18. Our needs are met by Shin-Etsu’s Re-Commitment dated 19 Jan 2006:

  19. LLP - Magnet Poles 1.04.03.03.03 • 19,200 vanadium permendur magnet poles. • The material is forged into rectangular bars and annealed for ductility [www.vacuumschmelze.com], then sawed into slices, milled, ground, lapped to the precise dimensions, and finally annealed for best magnetic performance. • 49% cobalt, 49% iron, 2% vanadium

  20. LLP Scope: Magnet Poles 1.04.03.03.03 (2) • Awarded to Hi-Tech Manufacturing, Schiller Park, IL [near O’Hare Airport]. • Award value: about 1M$ • Major simplification of the pole design, eliminating titanium wings, saved a lot. • Vendor has made similar items for APS. • Understands the job and has developed special tooling and processes for working with this tricky material.

  21. Magnet Poles – Progress @ Hi-Tech • Raw material is in house. • 1st 1000 poles, enough for the 2 first-article undulators plus spares, were complete, inspected, and ready for delivery the week of November 7th; • Hi-Tech procured a new CMM to enable automatic inspection of the 19200 poles. • Poles are ahead of the required schedule.

  22. Pole Mfg/Shipping Summary • Poles Sent To Metalex 50% of their needs • 5000 Pieces L143-110105-03 (undulators 2, 4, 6,8,10,12,14,16,18,20) • 85 Pieces L143-110107-02 • Completed For Hi-tech • 1000 Pieces L143-110105-03 (undulators 1 and 3) • 10 Pieces L143-110107-02 • Next Lot For Hi-tech (Ready By Mid-February) • 4000 Pieces L143-110105-03 (undulators 5,7,9,11,13,15,17,19) • 75 Pieces L143-110107-02 • Total Machined 13,000 Pieces

  23. Poles – example of inspection report

  24. Magnet Poles – Mfg. Progress @ Hi-Tech Staged for Assy.

  25. 1st Article Undulator Assemblies Prototype undulator (now @SLAC) on a simple breadboard girder used to gain experience with CAM mover control and monitoring @ANL.

  26. LLP – 1st-Article Undulator Assembly • First-article assembly awards were made to two vendors, with options for more pending 1st-article acceptance, available BA, and arrival of actual money at ANL. • Very favorable assembly costs; significant savings: • Two 1st articles • Series of 38 • The design, intellectual development, and prototyping were completely done by ANL, thus we could utilize precision machine shops instead of special-purpose magnet firms for the assembly. The budgeted amounts were based on past history with magnet specialists. • Intensive value engineering efforts and assembly planning contributed greatly to the savings.

  27. 1st-Article Undulator Assembly - Two Awards: • Metalex - Blue Ash, OH • Making ½ of the strongbacks • Excellent vendor • Saves on shipping • Hi-Tech - Schiller Park, IL • Making all of the poles • Performed many jobs for APS in the past • Saves on shipping

  28. ES&H and Informational Visit • Representatives of both undulator assembly vendors visited the APS in October 2005 in order to see the prototype undulator before it was shipped to SLAC. • They gained valuable experience in safe handling of these extremely strong magnets, and were able to practice a little bit in preparation for assembly at their facilities.

  29. QA & Vendor Management • The APS undulator experts responsible for design, construction, assessment, and value engineering of the prototype undulator, are responsible to oversee the undulator magnet and support procurements. • Responsibility for vendor management, vendor oversight and performance, and undulator performance rests with ANL-APS.

  30. Vendor relations and management are critical. If you start off right, chances for success are far better. Even a superb vendor may need some prodding to get in tune with the program. Incorporate QA from the start; pay attention to the details; work together with the vendors and keep procurement involved.

  31. Assembly Progress @ Hi-Tech • Hi-Tech has received all long lead items (LLP) required for its 1st article. • The assembly area as well as all required documentation deliverables, such as work plans, are ready. • Hi-Tech is 100% complete with non-LLP components and has started 1st-article undulator assembly.

  32. The Plan: Assembly – short base

  33. Assembly – short base with poles

  34. Assembly – short base - fully assembled with poles, magnets, and clamps

  35. Assembly – short base – fixture for precision positioning of the first poles

  36. Assembly – Use the transfer fixture for precision positioning of the next poles; anchor with four poles

  37. Assembly – continue down the line

  38. Assembly – completed long base

  39. Poles are inserted into the long base using the precision fixture designed by ANL. The four end poles are used as a locating reference for the next group. The fixture that enables safe joining of the top and bottom is also ready. Insert Poles into Base; Joining Fixture @Hi-Tech

  40. Poles assembled into bases, being readied for insertion of magnets and then assembly into the strongback. Hi-Tech 06 Feb 2006

  41. Magnets are labeled and arranged according to our sorting list; Red on top, Green on the bottom Assembly Progress at Hi-Tech (07Feb06)

  42. Assembly Progress @ Metalex • All documentation received: • Program Plan • Inspection and Test Planning • Quality Verification Plan • Program Schedule • Raw Materials are delivered. • The assembly area dedicated to this project is prepared. All work benches, storage racks, overhead cranes, and special tools are ready. • Parts are 100% ready.

  43. Assembly Progress @Metalex: Short Bases

  44. Assembly Progress @Metalex: Inspection of Short Base

  45. Assembly Progress atMetalexLong Bases

  46. Assembly Progress @Metalex: Clamps and Travelers

  47. Non-Magnetic Tools @ Metalex

  48. Assembly Area @Metalex – huge clean space – plenty of room for other things {ILC???}

  49. 1st Article Assembly/Tuning Schedule UN33_40060 AWARD: 1st Art Mag Assy - Hi-Tech 1 25-Oct-05 UN33_40100 Hi-Tech Procure - 1st Art Mag Assy Parts 42 10-Nov-05 19-Jan-06 UN33_40110 RCV: Ti S/B Article 01, Blocks, Poles, Parts 0 03-Jan-06 UN33_40120 Hi-Tech Fab/Assy-Mag Article 01 Assembly 42 20-Jan-06 20-Mar-06 UN33_40122 Review Hi-Tech travelers/data 2 21-Mar-06 22-Mar-06 UN33_40124 Factory Acceptance Article 01 - Hi-Tech 2 23-Mar-06 24-Mar-06 UN33_40128 Hi-Tech Undulator Article 01 Ship to ANL 1 28-Mar-06 UN33_40140 RCV: From Hi-Tech - Magnet Assy #1 1 29-Mar-06 UN33_00530 Mag Meas & Tune-Hi-Tech Article 01 21 30-Mar-06 27-Apr-06 UN33_00550 ACCEPT: Hi-Tech Und Article 01 @ANL 5 28-Apr-06 04-May-06 UN33_00554 ACCEPT: Hi-Tech Und Article 01 @SLAC 0 18-May-06 UN33_40150 AWARD: 1st Art Mag Assy - Metalex 1 26-Oct-05 UN33_40190 Metalex Procure - 1st Art Mag Assy Parts 42 15-Nov-05 24-Jan-06 UN33_40200 RCV: Ti S/B Article 02, Blocks, Poles, Parts 0 03-Jan-06 UN33_40210 Metalex Fab/Assy-Mag Article 02 Assembly 42 25-Jan-06 23-Mar-06 UN33_40211 Review Metalex travelers/data 2 24-Mar-06 27-Mar-06 UN33_40212 Factory Acceptance Article 02 - Metalex 2 28-Mar-06 29-Mar-06 UN33_40214 Metalex Undulator Article 02 Ship to ANL 5 31-Mar-06 06-Apr-06 UN33_40220 RCV: From Metalex - Magnet Assy #2 1 07-Apr-06 UN33_00560 Mag Measure & Tune-Metalex Article 02 21 28-Apr-06 26-May-06 UN33_00580 ACCEPT: Metalex Und Article 02 @ANL 5 30-May-06 05-Jun-06 UN33_00620 ACCEPT: Metalex Und Article 02 @SLAC 0 19-Jun-06

  50. Single Undulator Test • Prototype Fixed Supports • Prototype Girder and Motion System • Prototype or 1st-article Undulator • Controls software and hardware for readout, monitoring, and motion control. • Vacuum chamber prototype (solid) • Quadrupole Ersatz • BPM prototype • All other components on the girder or in the break sections will be represented by actuals or Ersatz.

More Related