This document provides an update on the status of vacuum sectors in LS2 and outlines the planning for SPS #27. It includes information on works in LSS6, electrical connections of septas, Qjack campaign, RF shielding, ac coating, sprinklers tests, and more.
E N D
SPS Planning meeting for LS2 #27Vacuum sectors status Antonio Grande EN-ACE 10-Jul-2019
Documents • Schematic view file:///G:/Departments/EN/Groups/ACE/OSS/Estrella/Schematic%20view/SPS_Schematic_View/SVG_SPS.svg Antonio Grande EN-ACE
Open point BA5+&6- • From week 27 to week 29 there are works in LSS6- regarding the bake out of the septas, which are partially blocking the passage to access arcs 6- and 5+ • Some problems with the electrical connections of the septas for the bake-out • Slight delay on the Qjack campaign (now together with the RF shielding works) • aC coating is foreseen for week 31 but in week 30 some works will be done to dismantle the line • QDs need to be aligned separately of QFs • Testing of the sprinklers after bake-out Antonio Grande EN-ACE
Open point - Conclusion BA5+&6- • New agreed planning: • W 29: Qjack + RF shielding in 5+ • W 30: ac Coating transport activities (from 25th to 31st July) + Sprinklers tests in shaft (to be determined along with Anna) • W 31: Sprinklers tests in the LSS6 (to be determined along with Anna) • W 32: bake out for 2-3 weeks • On Thursday 11th July, the inspection for RF shielding will be done in 5+. Also related to vacuum, vacuum sectors 634 and 635 are validated. • New Qjackcampaign sequence is 5+ 4+ 1&2. • Additionally, the vertical alignment campaign will start on W32 if resources are available, if not it will start in W33 Antonio Grande EN-ACE
Follow up SPS: QD RF shielding ✓ ✓ ✓ ✓ • Next inspection, in BA 5+, willbecarried out this Thursday ✓ ✓ Position 405 – C. Pasquino ✓ ✓ During this week QD MBB New positions after inspection in BA 4+ Inspection QD Position 415 – C. Pasquino Antonio Grande EN-ACE
Follow up Qjacks’ campaign • Arc 2+ done • Arc 3- done • Arc 3+ done • Arc 4- on going • Next steps: arc 5+ • New sequence:5+ 4+ 1&2 Antonio Grande EN-ACE
Vacuum sectors dashboard - Opening Opened twice Week 28 Antonio Grande EN-ACE
Vacuum sectors dashboard - Closing Week 28 Antonio Grande EN-ACE
Forecast for the next 3 weeks – LSS2&LSS4SPS LSS2 – Some works in ZS LSS4 – Prep works for WS Antonio Grande EN-ACE
Forecast for the next 3 weeks – arcsSPS 24 25 26 27 Week # Qjack aC coating Dismantling of ZS Antonio Grande EN-ACE
Forecast for the next 3 weeks – arcs SPS Qjack Qjack Qjack aC coating Qjack
Passage restriction status – w 28 RP restriction LSS2 2+ 2- 3- 1+ LSS3 LSS1 3+ 1- 4- 6+ LSS1 LSS1 LSS4 LSS6 4+ 6- 5- 5+ LSS5 LSS6- Restricted Passage partially restricted Possible punctual restrictions in passage No restriction foreseen Antonio Grande EN-ACE
Passage restriction status – w 29 RP restriction LSS2 2+ 2- 3- 1+ LSS3 LSS1 3+ 1- 4- 6+ LSS1 LSS1 LSS4 LSS6 4+ 6- 5- 5+ LSS5 LSS6+ Restricted Passage partially restricted Possible punctual restrictions in passage No restriction foreseen Antonio Grande EN-ACE
Passage restriction status – w 30 RP restriction LSS2 2+ 2- 3- 1+ LSS3 LSS1 3+ 1- 4- 6+ LSS1 LSS1 LSS4 LSS6 4+ 6- 5- 5+ LSS5 Restricted Passage partially restricted Possible punctual restrictions in passage No restriction foreseen Antonio Grande EN-ACE
All comments are more than welcome but please let me know by mail Thank you