1 / 5

LS1@LHC BLM planning

LS1@LHC BLM planning. 10 /03/2014. Surface racks. 11/03, Tuesday Seghair and Russian team will check, correct, install the all in P1,P2,P5 surface racks P1 -/+, P2 -/+, P5 -/+: to change the configuration: P6 + , P7 +, P8 +, P3 + : OK Pt4 : March (Bernd’s request)

claire
Download Presentation

LS1@LHC BLM planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LS1@LHC BLM planning 10/03/2014

  2. Surface racks 11/03, Tuesday Seghair and Russian team will check, correct, install the all in P1,P2,P5 surface racks • P1 -/+, P2 -/+, P5 -/+: tochange the configuration: P6 + , P7 +, P8 +, P3 +: OK • Pt4: March (Bernd’s request) • Rack configuration: R L I C - ground metallic bar: >5 fixation – OK (P3)

  3. Tunnel racks and HV divider • HV divider installation: Installed in all “standard” locations in all Points, except L6 In “special cases” – not installed, but long cables was ordered ( Remo) - ? • L5: restoration of racks after He spill test • Racks – CFC cards : ready for installation ( Ion or Russian team)

  4. BLM re-installation • Current status of DS+ARC installation: Sector 6-7 - done Sector 5-6 – done Sector 7-8 – R7 – done L8 – 4 working days to finish - All SEMs was dismounted in L8 ( to exchange for LIC) - BLMQI.01L8.B1E30)MQXA(BPMSW) with support was dismonted for LHCb counter installation, and to install in new, shifted place But no access in sector 7-8 10-11-12/03 and 17-18/03 Remarks: a) good collaboration with QPS team on DS of L8 to put down the common longest cable trays b) BLM team works with walkways • List what we need to be work before RSM: Installation, surface rack, tunnel rack, DB, … • Request to move the source on surface? • LSS installation • New installation:

  5. Divers • Databases: cryoBLM-BJBAP box and expert names and DCUM are in Layout(MTF) • Slot Labels ( after changes of expert names) • Rad Source test ( 2 sources ) • ECR for HV divider is released • Label for new “short” cable (BJBDV - BJBAP) • Amendment for 1 month* 4 persons prolongation – signed at CERN • ECR for LICs • LIC’s tests and shrinking at GIF: - shrinking – 12.03 - irradiation on front irradiator – 17-18/03