LS1 general planning and strategy for LHC, LHC injectors LHC Performance Workshop Chamonix 2012 K. Foraz K. Foraz - LHC Performance Workshop 2012
Outline • General frame • Injectors • LHC machine : Main activities and risks • Organization • Conclusion General frame Injectors LHC machine : Main activities and risks Organization Conclusion K. Foraz - LHC Performance Workshop 2012
Draft 10 years plan (27/10/11) 2012 2013 2014 2020 2015 2017 2018 2019 2021 2016 Operation period 2 (OP2) Operation period 1 (OP1) Long Shutdown 1 (LS1) • Machine : Splices consolidation… • ATLAS: - Consolidation and new forward beam pipes • ALICE: detector completion • CMS:FWD muons upgrade + Consolidation & infrastructure improvements • LHCb: consolidations Operation period 3 (OP3) Long Shutdown 2 (LS2) OP2 • Machine: Collimation & prepare for crab cavities & RF cryo system • ATLAS: new pixel detect. - detect. for ultimate luminosity. • ALICE - Inner vertex system upgrade • CMS - New Pixel. New HCAL Photodetectors. Completion of FWD muons upgrade • LHCb - full trigger upgrade, new vertex detector etc. LINAC 4 connection ? K. Foraz - LHC Performance Workshop 2012
LS1 - Goal Full maintenance Consolidation & upgrade LHC machine & experiments Injectors Take all measures for a safeand reliable operation of LHC @ 7TeV/beam K. Foraz - LHC Performance Workshop 2012
LS1 - Time window Marzio: “ LHC experiments upgrade & maintenance” • 20 months from Beam OFF to Beam ON • Actual total duration agreed between experiments and machine • LHC machine: 20 months • ALICE: 12 months (up to 15 months) • ATLAS: 15 months (but from April 2013) • CMS: 20 months • LHCb: 12 months K. Foraz - LHC Performance Workshop 2012
Requests Approval • Mauro : “EN-CV upgrade & consolidation” • Francois: “EN-EL upgrade & consolidation” • Erk : “RF upgrade program in LHC injectors and LHC machine“ • Meetings being held with stakeholders to understand • Goal of activities • Time key drivers • Support needed • For accelerator complex: database of requests is being filled : LHC and injectors • To detect conflicts/overloads & to decidewhat is compulsory, what we can afford &what we have to postpone to LS2 • Priorities set for LHC machine • P1: Beam to 6.5-7TeV, nominal performance • P2: Reliable operation • P3: CERN approved projects • P4: no CERN approved projects K. Foraz - LHC Performance Workshop 2012
Outline General frame Injectors LHC machine : Main activities and risks Organization Conclusion K. Foraz - LHC Performance Workshop 2012
Injectors General Shutdown works: ABT, Magnets, RP, lifts… RF Upgrade Decabling campaign Survey: Tilt & vertical - Quads Irradiated cables Survey Will be detailed during IEFC workshop Survey Irradiated cables Survey Power Converter Consolidation Other groups: BI, CO works Survey: Alignment maintenance Survey: Vertical & Radial measurements & Alignment General Shutdown works: ABT, Magnets, RP, lifts… • “Normal” Xmas shutdown (*2) • Survey: measurements, til, alignment • SPS: • EL: clear unused cables & irradiated cables in SPS • RF upgrades • Power converter consolidation • Other groups works Courtesy D. McFarlane V. Chohan K. Foraz - LHC Performance Workshop 2012
Injectors General Shutdown works: ABT, Magnets, RP, lifts… RF Upgrade Decabling campaign Renovation of Vacuum control system Survey: Tilt & vertical - Quads Interlck Interlck Irradiated cables Survey Interlck Interlck Survey Cooling & Ventilation maintenance & renovation RF maintenance & upgrade Irradiated cables Survey Power Converter Consolidation New Access system Other groups: BI, CO works Survey: Alignment maintenance Other groups : BI, CO,… Survey: Vertical & Radial measurements & Alignment General Shutdown works: ABT, Magnets, RP, lifts… General Shutdown works: ABT, Magnets, RP, lifts… New access system commissioning • PS & PS booster • Renovation of vacuum control system • Cooling & ventilation maintenance and renovation • RF maintenance & upgrade • New access system • Other groups works • Interlock Courtesy D. McFarlane V. Chohan K. Foraz - LHC Performance Workshop 2012
Injectors access system Rui: “Access strategy in the accelerator complex and experimental area” Courtesy E. Sanchez K. Foraz - LHC Performance Workshop 2012
Injectors General Shutdown works: ABT, Magnets, RP, lifts… LINAC 4 commissioning CTF operational dates TBC AD hall preparation for ELENA RF Upgrade Decabling campaign Renovation of Vacuum control system CV Set up of Argon & Xenon beam (1) Survey: Tilt & vertical - Quads Interlck Interlck Irradiated cables Survey Interlck Interlck Survey Cooling & Ventilation maintenance & renovation RF maintenance & upgrade Irradiated cables Survey Power Converter Consolidation New Access system Other groups: BI, CO works Set up of Argon & Xenon beam (2) Survey: Alignment maintenance Other groups : BI, CO,… Survey: Vertical & Radial measurements & Alignment General Shutdown works: ABT, Magnets, RP, lifts… Cold Checkout & Start-up New access system commissioning Cold Checkout & Start-up • Early 2014 :Cold check-out and Start up • LINAC3 : set up of Argon and Xenon beam • LINAC4 commissioning • CTF operational – dates TBC • HI-ISOLDE: Cooling & Ventilation works • AD & ELENA: AD hall preparation for ELENA Courtesy D. McFarlane V. Chohan K. Foraz - LHC Performance Workshop 2012
Outline General frame Injectors LHC machine : Main activities and risks Organization Conclusion K. Foraz - LHC Performance Workshop 2012
LHC machine – Time key drivers • Time key drivers in LHC machine • Superconducting circuits consolidation • Radiation To Electronics R2E • Maintenance • …. And many other activities (already > 100 entries in the db for LHC machine) K. Foraz - LHC Performance Workshop 2012
One typicalsector • Powering and ELQA tests prior to Warm-up (4+4 d) • qualify circuits except mains to 7TeV • fault localization.. • CSCM (1 sector) Mirko: “Powering tests before LHC warm-up: What is new from Chamonix 2011? ” Warm-up: incl. vacuum leak tests at 80K (1wk) to localize leaks Maintenance & consolidation Preparation for & cool-down Powering tests K. Foraz - LHC Performance Workshop 2012
Splices PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Preparation for cool-down Splices Powering Tests Warm-up Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Jean-Philippe : “LHC consolidation of the superconducting circuits ” K. Foraz - LHC Performance Workshop 2012
Other superconducting circuits PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Consolidation of SAM Y lines Magnets exchange Inner triplets braid DN200 Connection Cryostat K. Foraz - LHC Performance Workshop 2012
Maintenance PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up Cryo Maint. CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Cryo Maint. Splices Splices Splices Cryo Maint. Cryo Maint. Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Cryogenics : 18 weeks per cryoplant + Maintenance of all the equipment: CV, EL, RF…, mainly in service areas K. Foraz - LHC Performance Workshop 2012
R2E mitigation measures Anne-Laure : “R2E strategy and activities during LS1 ” Courtesy M. Barberan Detailed & graphical schedules ready, except P7 in progress K. Foraz - LHC Performance Workshop 2012
R2E mitigation measures P7 to be finalized PT PT Just in time for CD of s.12 Delay by 2 wks CD of S.81 PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up R2E R2E R2E CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Delay Cool-down of 56 (1st sector) Delay Powering tests of 56 But 1 monthmarginw.r.t s45 Powering Tests Splices Preparation for cool-down Warm-up R2E Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests K. Foraz - LHC Performance Workshop 2012
Skeleton schedule – Physics to physics PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up Cryo Maint. CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Cryo Maint. Splices Splices Splices Cryo Maint. Cryo Maint. Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Cold check-out & Beam Commissioning 1 week stand-by 2014-2015 Ezio : What is the maximum reasonable energy Physics K. Foraz - LHC Performance Workshop 2012
Risks (possible changes in schedule): IC trains From installation experience, first 2 sectors took ~ 20% longer But leak detection and electrical tests at the end can reserve bad surprises in the last sectors… PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up CSCM preparation Splices + 20% CSCM Splices Warm-up + 20% Splices Splices Splices Splices Splices Splices Powering Tests Preparation for cool-down Splices Warm-up Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests K. Foraz - LHC Performance Workshop 2012
Risks (possible changes in schedule): R2E mitigation measures P1 & P5 are tight in schedule : Effect of 6 weeks delay No direct impact on end dates but will delay the powering tests of 3rd and following sectors. P7 to be finalized PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up R2E R2E R2E CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Splices Powering Tests Preparation for cool-down Warm-up R2E Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests K. Foraz - LHC Performance Workshop 2012
Risk (possible changes in schedule): additional activities • Additional activities, especially those requiring supports from other groups can disorganize the global schedule, and induce delays. • CSCM tests in all sectors will cost around 4 weeks PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up Cryo Maint. CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Cryo Maint. Splices Splices Splices Cryo Maint. Cryo Maint. Cool-down Cool-down Cool-down Powering Tests Cool-down CSCM CSCM Cool-down CSCM CSCM CSCM Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests CSCM Cool-down CSCM Powering Tests CSCM Powering Tests Powering Tests Cold check-out & Beam Commissioning Physics K. Foraz - LHC Performance Workshop 2012
Outline General frame Injectors LHC machine : Main activities and risks Organization Conclusion K. Foraz - LHC Performance Workshop 2012
Organization Reiner : “QPS upgrade and machine protection during LS1 ” Miguel : “Vacuum upgrade” Laurent: “Cryogenics system: strategy to achieve nominal performance and reliable operation “ • Schedule & logistics • Lots’of work still to be done in matter of schedule & logistics for all the other activities w.r.t. skeleton schedule • Preparation • ECR have to be written prior to works • Modification of the envelope of your equipment ICL • DIMR • Materials have to be ready in due time…..This has often induced delays !!! • Follow-up • Weekly coordination and scheduling meeting K. Foraz - LHC Performance Workshop 2012
Conclusions • Analysis of requests well advanced (LHC & experiments, injectors) • w.r.t. priorities & resources & time & interaction between groups • New requests will be scrutinized, especially the support form overloaded groups (VSC, EL, CV) • “Skeleton” schedules for LHC machine & injectors ready • Workload is huge and the schedule is tight • Worksites have to be well prepared.Please do not forget layout, integration & safety K. Foraz - LHC Performance Workshop 2012