LS1 general planning and strategy for LHC, LHC injectors

LS1 general planning and strategy for LHC, LHC injectors. LHC Performance Workshop Chamonix 2012 K. Foraz. Outline. General frame Injectors LHC machine : Main activities and risks Organization Conclusion. General frame Injectors LHC machine : Main activities and risks Organization

kaycee
Download Presentation

LS1 general planning and strategy for LHC, LHC injectors

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LS1 general planning and strategy for LHC, LHC injectors LHC Performance Workshop Chamonix 2012 K. Foraz K. Foraz - LHC Performance Workshop 2012

  2. Outline • General frame • Injectors • LHC machine : Main activities and risks • Organization • Conclusion General frame Injectors LHC machine : Main activities and risks Organization Conclusion K. Foraz - LHC Performance Workshop 2012

  3. Draft 10 years plan (27/10/11) 2012 2013 2014 2020 2015 2017 2018 2019 2021 2016 Operation period 2 (OP2) Operation period 1 (OP1) Long Shutdown 1 (LS1) • Machine : Splices consolidation… • ATLAS: - Consolidation and new forward beam pipes • ALICE: detector completion • CMS:FWD muons upgrade + Consolidation & infrastructure improvements • LHCb: consolidations Operation period 3 (OP3) Long Shutdown 2 (LS2) OP2 • Machine: Collimation & prepare for crab cavities & RF cryo system • ATLAS: new pixel detect. - detect. for ultimate luminosity. • ALICE - Inner vertex system upgrade • CMS - New Pixel. New HCAL Photodetectors. Completion of FWD muons upgrade • LHCb - full trigger upgrade, new vertex detector etc. LINAC 4 connection ? K. Foraz - LHC Performance Workshop 2012

  4. LS1 - Goal Full maintenance Consolidation & upgrade LHC machine & experiments Injectors Take all measures for a safeand reliable operation of LHC @ 7TeV/beam K. Foraz - LHC Performance Workshop 2012

  5. LS1 - Time window Marzio: “ LHC experiments upgrade & maintenance” • 20 months from Beam OFF to Beam ON • Actual total duration agreed between experiments and machine • LHC machine: 20 months • ALICE: 12 months (up to 15 months) • ATLAS: 15 months (but from April 2013) • CMS: 20 months • LHCb: 12 months K. Foraz - LHC Performance Workshop 2012

  6. Requests Approval • Mauro : “EN-CV upgrade & consolidation” • Francois: “EN-EL upgrade & consolidation” • Erk : “RF upgrade program in LHC injectors and LHC machine“ • Meetings being held with stakeholders to understand • Goal of activities • Time key drivers • Support needed • For accelerator complex: database of requests is being filled : LHC and injectors • To detect conflicts/overloads & to decidewhat is compulsory, what we can afford &what we have to postpone to LS2 • Priorities set for LHC machine • P1: Beam to 6.5-7TeV, nominal performance • P2: Reliable operation • P3: CERN approved projects • P4: no CERN approved projects K. Foraz - LHC Performance Workshop 2012

  7. Outline General frame Injectors LHC machine : Main activities and risks Organization Conclusion K. Foraz - LHC Performance Workshop 2012

  8. Injectors General Shutdown works: ABT, Magnets, RP, lifts… RF Upgrade Decabling campaign Survey: Tilt & vertical - Quads Irradiated cables Survey Will be detailed during IEFC workshop Survey Irradiated cables Survey Power Converter Consolidation Other groups: BI, CO works Survey: Alignment maintenance Survey: Vertical & Radial measurements & Alignment General Shutdown works: ABT, Magnets, RP, lifts… • “Normal” Xmas shutdown (*2) • Survey: measurements, til, alignment • SPS: • EL: clear unused cables & irradiated cables in SPS • RF upgrades • Power converter consolidation • Other groups works Courtesy D. McFarlane V. Chohan K. Foraz - LHC Performance Workshop 2012

  9. Injectors General Shutdown works: ABT, Magnets, RP, lifts… RF Upgrade Decabling campaign Renovation of Vacuum control system Survey: Tilt & vertical - Quads Interlck Interlck Irradiated cables Survey Interlck Interlck Survey Cooling & Ventilation maintenance & renovation RF maintenance & upgrade Irradiated cables Survey Power Converter Consolidation New Access system Other groups: BI, CO works Survey: Alignment maintenance Other groups : BI, CO,… Survey: Vertical & Radial measurements & Alignment General Shutdown works: ABT, Magnets, RP, lifts… General Shutdown works: ABT, Magnets, RP, lifts… New access system commissioning • PS & PS booster • Renovation of vacuum control system • Cooling & ventilation maintenance and renovation • RF maintenance & upgrade • New access system • Other groups works • Interlock Courtesy D. McFarlane V. Chohan K. Foraz - LHC Performance Workshop 2012

  10. Injectors access system Rui: “Access strategy in the accelerator complex and experimental area” Courtesy E. Sanchez K. Foraz - LHC Performance Workshop 2012

  11. Injectors General Shutdown works: ABT, Magnets, RP, lifts… LINAC 4 commissioning CTF operational dates TBC AD hall preparation for ELENA RF Upgrade Decabling campaign Renovation of Vacuum control system CV Set up of Argon & Xenon beam (1) Survey: Tilt & vertical - Quads Interlck Interlck Irradiated cables Survey Interlck Interlck Survey Cooling & Ventilation maintenance & renovation RF maintenance & upgrade Irradiated cables Survey Power Converter Consolidation New Access system Other groups: BI, CO works Set up of Argon & Xenon beam (2) Survey: Alignment maintenance Other groups : BI, CO,… Survey: Vertical & Radial measurements & Alignment General Shutdown works: ABT, Magnets, RP, lifts… Cold Checkout & Start-up New access system commissioning Cold Checkout & Start-up • Early 2014 :Cold check-out and Start up • LINAC3 : set up of Argon and Xenon beam • LINAC4 commissioning • CTF operational – dates TBC • HI-ISOLDE: Cooling & Ventilation works • AD & ELENA: AD hall preparation for ELENA Courtesy D. McFarlane V. Chohan K. Foraz - LHC Performance Workshop 2012

  12. Outline General frame Injectors LHC machine : Main activities and risks Organization Conclusion K. Foraz - LHC Performance Workshop 2012

  13. LHC machine – Time key drivers • Time key drivers in LHC machine • Superconducting circuits consolidation • Radiation To Electronics R2E • Maintenance • …. And many other activities (already > 100 entries in the db for LHC machine) K. Foraz - LHC Performance Workshop 2012

  14. One typicalsector • Powering and ELQA tests prior to Warm-up (4+4 d) • qualify circuits except mains to 7TeV • fault localization.. • CSCM (1 sector) Mirko: “Powering tests before LHC warm-up: What is new from Chamonix 2011? ” Warm-up: incl. vacuum leak tests at 80K (1wk) to localize leaks Maintenance & consolidation Preparation for & cool-down Powering tests K. Foraz - LHC Performance Workshop 2012

  15. Splices PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Preparation for cool-down Splices Powering Tests Warm-up Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Jean-Philippe : “LHC consolidation of the superconducting circuits ” K. Foraz - LHC Performance Workshop 2012

  16. Other superconducting circuits PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Consolidation of SAM Y lines Magnets exchange Inner triplets braid DN200 Connection Cryostat K. Foraz - LHC Performance Workshop 2012

  17. Maintenance PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up Cryo Maint. CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Cryo Maint. Splices Splices Splices Cryo Maint. Cryo Maint. Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Cryogenics : 18 weeks per cryoplant + Maintenance of all the equipment: CV, EL, RF…, mainly in service areas K. Foraz - LHC Performance Workshop 2012

  18. R2E mitigation measures Anne-Laure : “R2E strategy and activities during LS1 ” Courtesy M. Barberan Detailed & graphical schedules ready, except P7 in progress K. Foraz - LHC Performance Workshop 2012

  19. R2E mitigation measures P7 to be finalized PT PT Just in time for CD of s.12 Delay by 2 wks CD of S.81 PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up R2E R2E R2E CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Delay Cool-down of 56 (1st sector) Delay Powering tests of 56 But 1 monthmarginw.r.t s45 Powering Tests Splices Preparation for cool-down Warm-up R2E Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests K. Foraz - LHC Performance Workshop 2012

  20. Skeleton schedule – Physics to physics PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up Cryo Maint. CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Cryo Maint. Splices Splices Splices Cryo Maint. Cryo Maint. Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests Cold check-out & Beam Commissioning 1 week stand-by 2014-2015 Ezio : What is the maximum reasonable energy Physics K. Foraz - LHC Performance Workshop 2012

  21. Risks (possible changes in schedule): IC trains From installation experience, first 2 sectors took ~ 20% longer But leak detection and electrical tests at the end can reserve bad surprises in the last sectors… PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up CSCM preparation Splices + 20% CSCM Splices Warm-up + 20% Splices Splices Splices Splices Splices Splices Powering Tests Preparation for cool-down Splices Warm-up Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests K. Foraz - LHC Performance Workshop 2012

  22. Risks (possible changes in schedule): R2E mitigation measures P1 & P5 are tight in schedule : Effect of 6 weeks delay No direct impact on end dates but will delay the powering tests of 3rd and following sectors. P7 to be finalized PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up R2E R2E R2E CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Splices Splices Splices Splices Powering Tests Preparation for cool-down Warm-up R2E Cool-down Cool-down Cool-down Cool-down Powering Tests Cool-down Cool-down Powering Tests Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests Cool-down Powering Tests Powering Tests K. Foraz - LHC Performance Workshop 2012

  23. Risk (possible changes in schedule): additional activities • Additional activities, especially those requiring supports from other groups can disorganize the global schedule, and induce delays. • CSCM tests in all sectors will cost around 4 weeks PT PT PT PT PT PT Warm-up Warm-up PT Warm-up Warm-up PT Warm-up Warm-up -> 10K Warm-up Cryo Maint. CSCM preparation Splices CSCM Splices Warm-up Splices Splices Splices Cryo Maint. Splices Splices Splices Cryo Maint. Cryo Maint. Cool-down Cool-down Cool-down Powering Tests Cool-down CSCM CSCM Cool-down CSCM CSCM CSCM Powering Tests Powering Tests Cool-down Powering Tests Cool-down Powering Tests CSCM Cool-down CSCM Powering Tests CSCM Powering Tests Powering Tests Cold check-out & Beam Commissioning Physics K. Foraz - LHC Performance Workshop 2012

  24. Outline General frame Injectors LHC machine : Main activities and risks Organization Conclusion K. Foraz - LHC Performance Workshop 2012

  25. Organization Reiner : “QPS upgrade and machine protection during LS1 ” Miguel : “Vacuum upgrade” Laurent: “Cryogenics system: strategy to achieve nominal performance and reliable operation “ • Schedule & logistics • Lots’of work still to be done in matter of schedule & logistics for all the other activities w.r.t. skeleton schedule • Preparation • ECR have to be written prior to works • Modification of the envelope of your equipment  ICL • DIMR • Materials have to be ready in due time…..This has often induced delays !!! • Follow-up • Weekly coordination and scheduling meeting K. Foraz - LHC Performance Workshop 2012

  26. Conclusions • Analysis of requests well advanced (LHC & experiments, injectors) • w.r.t. priorities & resources & time & interaction between groups • New requests will be scrutinized, especially the support form overloaded groups (VSC, EL, CV) • “Skeleton” schedules for LHC machine & injectors ready • Workload is huge and the schedule is tight • Worksites have to be well prepared.Please do not forget layout, integration & safety K. Foraz - LHC Performance Workshop 2012