140 likes | 300 Views
August 9, 2013 | Markets COMMITTEE. Matt Brewster. Market Development. Materials prepared in response to Markets Committee requests. NCPC Payments: requested exhibits and examples. SIDE-BY-SIDE Comparison of “Penalties”.
E N D
August 9, 2013 | Markets COMMITTEE Matt Brewster Market Development Materials prepared in response to Markets Committee requests NCPC Payments: requested exhibits and examples
SIDE-BY-SIDE Comparison of “Penalties” Actions that reduce the Offer cost considered for NCPC under existing and Offer Flexibility designs
Actions that reduce Offer cost (continued) Observations: • Adjustments are largely the same or eliminate “step-change” in compensation to align severity of adjustment with system impact • Late Start is the only new adjustment • Generators most often achieve ordered time within 30 minute window • Adjustment is gradual and preserves incentive to continue startup • Comparable to existing adjustment for Early Shutdown
Start-Up and No Load Offer Values Sample statistics for dollar value of these Offers
Summary Start-Up and No-Load Offer values Supply Offer values were selected from a single day in January 2013 *Average of Start-Up for hot, intermediate, and cold state resource start
Examples of NCPC CALCULATION Steps Demonstration of how certain (previously described) elements of the calculations are performed
Reduction of Start-Up fee when release occurs later than planned time (after 30 minute grace) 2 hour commitment “planned” and “actual” are release for dispatch time Start-Up is not reduced because actual release occurs within 30 minutes after planned time ramp • Start-Up is reduced by 20% = (54 – 30) / 120 • NCPC considers Start-up of $4,800 = (1 - .20) * $6000 ramp
Calculation of Energy offer cost for RT Commitment and RT Dispatch NCPC eligible quantity amounts DDP = 110 MW Marginal energy offer at DDP = $24/MWh EcoMin Limit = 70 MW • RT Commitment NCPC eligible quantity = EDP (= 90 MW) • Energy offer cost = $1,110 ( = $720 + $390 ) • RT Dispatch NCPC eligible quantity = DDP – EDP (= 110 – 90 MW) • Energy offer cost = $450 EDP = 90 MW Marginal energy offer at EDP = $21/MWh Cost to EcoMin at Commitment offer RT LMP = $21/MWh Cost above EcoMin at Dispatch offer *Offer requested offer slope Unit is not ramp constrained
RT eligible quantity treatment during ramp-constrained resource dispatch Resource’s total NCPC credits = $408 = ( $400 + $8 ) Hour 2: Resource is ramp-constrained up which is reflected in the DDP value; DDP is upper-limit for EDP
RT eligible quantity treatment during ramp-constrained resource dispatch (continued) Resource’s total NCPC credits = $408 = ( $400 + $8 ) Hour 4: Resource is not ramp-constrained but dispatched to operate above the EDP RT Dispatch NCPC credit
RT eligible quantity treatment during ramp-constrained resource dispatch (continued) Resource’s total NCPC credits = $408 = ( $400 + $8 ) Hour 6: Resource is ramp-constrained down EDP set equal to DDP (feasible dispatch) and cost included in RT Commit NCPC
RT Commitment NCPC credit determination for multi-commitment settlement period* Min Run Time is now 2 hours Best Alternative: Resource would choose to shutdown at Hour 5. Continues to run through Hour 7 and loses $810. *Excludes Start-Up to demonstrate Commitment Cost change with No Load