190 likes | 314 Views
Woodward Light Rail Transit Project. NAMC Detroit Transporation Symposium September 15, 2011. Agenda. Welcome & Introductions Downtown & Mainline Alignment Environmental Impact Statement Decision Making Factors DBE and Contracting Opportunities Next Steps. Presentation Team.
E N D
Woodward Light Rail Transit Project NAMC Detroit Transporation Symposium September 15, 2011
Agenda • Welcome & Introductions • Downtown & Mainline Alignment • Environmental Impact Statement • Decision Making Factors • DBE and Contracting Opportunities • Next Steps
Presentation Team Kamau C. Marable, M.A. Manager Public Involvement Woodward Light Rail Transit Tim Roseboom Manager Strategic Planning DDOT Mark Ryan Project Manager URS
Alignment • 19 Stations • 9.3 Miles • Mainly Median • Park & Ride • Maint. Facility • Downtown
Light Rail Vehicle Example Two-Car Consist Hiawatha LRT Minneapolis, MN Light Rail Vehicle (LRV) – Twin Cities
Vehicle Features Bike Racks on Trains Level Boarding for ADA Access Modern LRV Features
Typical Platform / Station Hiawatha LRT, Minneapolis, MN
350’ Uninterrupted Frontage Congress and Larned Street – Current Concept Congress St. Shelby St. Griswold St. Larned St. Parking Ramp’ Access 250’ Uninterrupted Frontage Station Location Current Concept
McNichols Rd. Geneva St. McNichols Road Station – Current Concept A A Florence St. B B Louise St. Stevens St. Current Concept Alternate Concept A Station Location Issues: - Reconfigure With Two End-to-End Platforms - Secondary Access at South End
Record of Decision • Issued August 31 by FTA • Allows Federal funds to be used • Clears project to receive over $300 million in New Starts Federal grant • Binding commitments for project
Environmental Impact Statement MDOT/FHWA Workshops: Guiding Principles • 11’ Travel Lanes, Except Where Necessary • e.g. Overpass • Maintain Vehicular Corridor Capacity • Two Through Lanes each Direction • Limit Moving Curb • 15’ Sidewalk Margin Where Possible • Station Locations Impact Sidewalk • 8’ Parking Adjacent to Train is too Narrow • Minimum of 10’
Key Decision Making Factors Maintain On Street Parking Design Service to Ridership Projection Provide Safe Pedestrian Environment Design and Build using Existing Bridges
Project Time-Line • Enter Preliminary Engineering (PE): Nov 2011 • Issue Vehicle RFP: January 2012 • Early Construction Activities: September 2012 • Enter Final Design: August 2013 • Mainline Construction: May 2013 to April 2015 • Delivery of Vehicles: May 2015 • Final Testing: July 2015 • Revenue Service: September 2015
Creating Jobs in Detroit & Surrounding Areas Carla BrownDBE/Workforce Specialist
Overview A Disadvantaged Business Enterprise (DBE) is a business that functions with a minimum of 51% of the ownership and daily operation, management and overall control is held by minority groups or persons determined by the Small Business Administration to be economically and socially disadvantaged. Citizens presumed to be disadvantaged are: African Americans, Hispanic Americans, Asian-Pacific Americans, Native Americans, and women.
Bid Opportunities WLRT’s Office of Public Involvement provides information (bid opportunity listing) on upcoming contracts and information on prime contractor/consultants with whom potential subcontracts and/or joint venture arrangements can be made. Given the economic climate in the Metropolitan Detroit Area, the proposed DBE participation is 30%.