CTA – PLANNING MAIN-HOUR (m-h) FOR EMBRAER PROGRAMS ERJ170-200 AND ERJ190-100. Prepared by: Program Management Branch (HGP) 22 September 2004 009/HGP/2004. CTA PLANNING EMBRAER PROGRAM ERJ170-200. ACTIVITIES -Total Number of Reports : 314
E N D
CTA – PLANNING MAIN-HOUR (m-h) FOR EMBRAER PROGRAMS ERJ170-200 AND ERJ190-100 Prepared by: Program Management Branch (HGP) 22 September 2004 009/HGP/2004
CTA PLANNINGEMBRAER PROGRAM ERJ170-200 ACTIVITIES -Total Number of Reports : 314 Reports for CTA review : 104 (67% delegation) (2000 m-h) Specialists Meetings : 9 weeks (2 m; PF1 availab.) (6000 m-h) -Formal CTA Meetings : 2 (2000 m-h) Support to FCAA Meetings : - Published Documents : Revisions of Doc (AFM, MRB, etc.) Pre TC Activities : 30 calendar days Coord/Flight Tests : 70 FTH (500 m-h)
CTA PLANNING EMBRAER PROGRAM ERJ-170-200 SCHEDULE OF MAIN EVENTS • Application : May 2001 • Preliminary TCBM : 5 August 2003 • 1st Flight : June 2003 • Pre-flight TCBM : 10 December 2003 • AIT issuance : 23 December 2003 • Certification Flight Tests : January – September 2004 • Last Certification Reports Delivery : 30 Sept 2004 • CTA Engineering Inspection : 11 October 2004 • Final TCBM : 25 October 2004 • TC Issuance : 29 October 2004
CTA PLANNINGEMBRAER PROGRAM ERJ 170-200 TOTAL REQUESTED HOURS • Total Required (CTA) : 10500 CTA AVAILABLE HOURS • Average Month : 7500 • Peak Month : 9000 • PF1 (50% availab.) : 3800/4500 Minimum period at 50% availability : 3 months
CTA PLANNING EMBRAER PROGRAM ERJ-190-100 ACTIVITIES • Number of Reports : 874 (1318) • Report for CTA Review : 370 (58 % delegation) (7500m-h) • Specialists Meetings : 39 weeks (9 mo (60%); PF1 avail.) (26000 m-h) • Formal CTA Meetings : 3 (3000 m-h) • Support to FCAA Meetings : 2 (1500 m-h) • Published Documents : 1000 m-h • Pre TC Activities : 30 calendar days (3500 m-h; PF1 50% avail.) • Ground/Flight Tests : 300 FHT (2500 m-h)
CTA PLANNINGEMBRAER PROGRAM ERJ-190-100 TOTAL REQUESTED HOURS • TOTAL REQUIRED (CTA) : 45000 CTA AVAILABLE HOURS • Average Month : 7500 • Peak Mont : 9000 • PF1 (50% availab.) : (3800/4500) Minimum period at 50% availability : 12 months
CTA PLANNINGEMBRAER PROGRAM ERJ-190-100 SCHEDULE OF MAIN EVENTS Application : 30 May 2001 Preliminary TCBM : 2 April 2004 1st Flight : 11 February 2004 Pre-Flight TCBM : 11 August 2004 (OCTOBER 2004) AIT Issuance : 18 August 2004 (NOVEMBER 2004) Certification Flight Tests : September 24 – March 05 Last Certification Report Delivery : 13 may 2005 CTA Engineering Inspection : 8 June 2005 Final TCBM : 23 June 2005 TC Issuance : 30 June 2005