Network Analysis Operational Research Level 4

Network Analysis Operational Research Level 4. Prepared by T.M.J.A.Cooray Department of Mathematics. Project Planning. Given: Statement of work written description of goals work & time frame of project Work Breakdown Structure

Download Presentation

Network Analysis Operational Research Level 4

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Network AnalysisOperational Research Level 4 Prepared by T.M.J.A.Cooray Department of Mathematics MA 4020 -Network Analysis

  2. Project Planning • Given: • Statement of work • written description of goals • work & time frame of project • Work Breakdown Structure • Be able to: develop precedence relationship diagram which shows sequential relationship of project activities MA 4020 -Network Analysis

  3. Gantt Chart • Popular tool for project scheduling • Graph with bar representing time for each task • Provides visual display of project schedule • Also shows slack for activities • (amount of time activity can be delayed without delaying project) MA 4020 -Network Analysis

  4. A Gantt Chart Month 0 4 2 6 8 10 ½ ½ ½ ½ ½ Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work ½ ½ ½ ½ ½ 1 3 5 7 9 MA 4020 -Network Analysis

  5. CPM/PERT • Critical Path Method (CPM) • - DuPont & Remington-Rand (1956) • - deterministic task times • - activity-on-node network construction (AON) • Project Evaluation & Review Technique (PERT) • - U.S. Navy, Booz, Allen & Hamilton • - multiple task time estimates( probabilistic) • - activity-on-arrow network construction (AOA) MA 4020 -Network Analysis

  6. Network Construction • In AON, nodes represent activities & arrows show precedence relationships • In AOA, arrows represent activities & nodes are events for points in time • An event is the completion or beginning of an activity • A dummy shows precedence for two activities with same start & end nodes MA 4020 -Network Analysis

  7. 1 2 3 The Project Network Network consists of branches & nodes Node Branch MA 4020 -Network Analysis

  8. 1 2 3 Simplified Project Network Construct forms Pour concrete MA 4020 -Network Analysis

  9. Consider the following table which describes the activities to be done to build a house and its sequence Activity predecessors Duration A Design house and obtain financing - 3 B Lay foundation A 2 C Order and receive materials A 1 D Build house B,C 3 E Select paint B,C 1 F Select carpet E 1 G Finish work D,F 1 MA 4020 -Network Analysis

  10. Lay foundation 3 2 Order material Concurrent Activities 3 Lay foundation Dummy 2 4 Order material Incorrect precedence relationship Correct precedence relationship MA 4020 -Network Analysis

  11. Project Network For A House 3 Dummy Lay foundation 0 Build house Finish work 2 3 1 7 6 1 2 4 1 3 Order and receive materials Design house and obtain financing 1 1 Select paint Select carpet 5 MA 4020 -Network Analysis

  12. Critical Path • A path is a sequence of connected activities running from the start to the end node in a network • The critical path is the path with the longest duration in the network • A project cannot be completed in less than the time of the critical path (under normal circumstances) MA 4020 -Network Analysis

  13. All Possible Paths path1: 1-2-3-4-6-7 3 + 2 + 0 + 3 + 1 = 9 months; the critical path path2: 1-2-3-4-5-6-7 3 + 2 + 0 + 1 + 1 + 1 = 8 months path3: 1-2-4-6-7 3 + 1 + 3 + 1 = 8 months path4: 1-2-4-5-6-7 3 + 1 + 1 + 1 + 1 = 7 months MA 4020 -Network Analysis

  14. Early Times(Housebuilding example) • ES - earliest time activity can start • Forward pass starts at beginning of network to determine ES times • EF = ES + activity time • ESij = maximum (EFi) • EFij = ESij + tij • ES12 = 0 • EF12 = ES12 + t12 = 0 + 3 = 3 months i j MA 4020 -Network Analysis

  15. Computing Early Times -ES23 = max (EF2) = 3 months - ES46 = max (EF4) = max (5,4) = 5 months - EF46 = ES46 + t46 = 5 + 3 = 8 months - EF67 =9 months, the project duration MA 4020 -Network Analysis

  16. Late Times • LS - latest time activity can be started without delaying the project • Backward pass starts at end of network to determine LS times • LF - latest time activity can be completed without delaying the project • LSij = LFij - tij • LFij = minimum (LSj) MA 4020 -Network Analysis

  17. Computing Late Times • If a deadline is not given take LF of the project to be EF of the last activity • LF67 = 9 months • LS67 = LF67 - t67 = 9 - 1 = 8 months • LF56 = minimum (LS6) = 8 months • LS56 = LF56 - t56 = 8 - 1 = 7 months • LF24 = minimum (LS4) = min(5, 6) = 5 months • LS24 = LF24 - t24 = 5 - 1 = 4 months MA 4020 -Network Analysis

  18. ES=5, EF=5 LS=5, LF=5 ES=3, EF=5 LS=3, LF=5 ES=8, EF=9 LS=8, LF=9 ES=5, EF=8 LS=5, LF=8 ES=3, EF=4 LS=4, LF=5 ES=0, EF=3 LS=0, LF=3 ES=6, EF=7 LS=7, LF=8 ES=5, EF=6 LS=6, LF=7 Early And Late Times 3 0 2 3 1 7 6 1 2 4 3 1 1 1 5 MA 4020 -Network Analysis

  19. Activity Slack • Slack is defined as the LS-ES or LF-EF • Activities on critical path have ES = LS & EF = LF (slack is 0) • Activities not on critical path have slack • Sij = LSij - ESij • Sij = LFij - EFij • S24 = LS24 - ES24 = 4 - 3 = 1 month MA 4020 -Network Analysis

  20. Total slack/float or Slack of an activity • Total slack/ float means the amount of time that an activity can be delayed without affecting the entire project completion time. • The activity on a given path share the maximum possible slack of the activity along that path according to its share. • Sum of the possible slacks of the activities can not exceed the maximum slack along that path. MA 4020 -Network Analysis

  21. Free slack of an activity • This is the maximum possible delay of an activity which does not affect its immediate successors. • This is evaluated as • FSij = ESj – EFij • FF34=ES4-EF34 =5-5=0 • FF24=ES4-ES24=5-4=1 MA 4020 -Network Analysis

  22. Activity Slack Data Activity ES LS EF LF Slack (S) Free slack 1-2* 0 0 3 3 0 0 2-3 3 3 5 5 0 0 2-4 3 4 4 5 1 1 3-4* 5 5 5 5 0 0 4-5 5 6 6 7 1 0 4-6* 5 5 8 8 0 0 5-6 6 7 7 8 1 1 6-7* 8 8 9 9 0 0 * Critical path MA 4020 -Network Analysis

  23. 0 2 4 6 8 10 • Activity • Design house and • obtain financing • Lay foundation • Order and receive • materials • Build house • Select paint • Select carpet • Finish work 1 3 5 7 9 MA 4020 -Network Analysis

  24. a + 4m + b t = Mean (expected time): 6 b - a ( ) Variance: s 2 = 6 Probabilistic Time Estimates • Reflect uncertainty of activity times • Beta distribution is used in PERT 2 where, a = optimistic estimate m = most likely time estimate b = pessimistic time estimate MA 4020 -Network Analysis

  25. Example Beta Distributions P (time) P (time) m t a b a t m b P (time) a b m = t MA 4020 -Network Analysis

  26. PERT Example Equipment testing and modification 2 6 Final debugging Dummy Equipment installation System Training 1 3 5 8 9 System development Manual Testing System changeover System Testing Job training Dummy Position recruiting Orientation 4 7 MA 4020 -Network Analysis

  27. Activity Information Time estimates (wks) Mean Time Variance Activity a m b t s2 1 - 2 6 8 10 8 .44 1 - 3 3 6 9 6 1.00 1 - 4 1 3 5 3 .44 2 - 5 0 0 0 0 .00 2 - 6 2 4 12 5 2.78 3 - 5 2 3 4 3 .11 4 - 5 3 4 5 4 .11 4 - 7 2 2 2 2 .00 5 - 8 3 7 11 7 1.78 5 - 7 2 4 6 4 .44 7 - 8 0 0 0 0 .00 6 - 9 1 4 7 4 1.00 8 - 9 1 10 13 9 4.00 MA 4020 -Network Analysis

  28. Early And Late Times Activity t s2 ES EF LS LF S FS? 1 - 2 8 0.44 0 8 1 9 1 1 - 3 6 1.00 0 6 0 6 0 1 - 4 3 0.44 0 3 2 5 2 2 - 5 0 0.00 8 8 9 9 1 2 - 6 5 2.78 8 13 16 21 8 3 - 5 3 0.11 6 9 6 9 0 4 - 5 4 0.11 3 7 5 9 2 4 - 7 2 0.00 3 5 14 16 11 5 - 8 7 1.78 9 16 9 16 0 5 - 7 4 0.44 9 13 12 16 3 7 - 8 0 0.00 13 13 16 16 3 6 - 9 4 1.00 13 17 21 25 8 8 - 9 9 4.00 16 25 16 25 0 MA 4020 -Network Analysis

  29. ES=8, EF=13 LS=16 LF=21 ( ) ES=0, EF=8 LS=1, LF=9 ES=13, EF=17 LS=21 LF=25 ( ) ( ) ES=8, EF=8 LS=9, LF=9 ( ) ES=0, EF=6 LS=0, LF=6 ES=9, EF=16 LS=9, LF=16 ( ) ( ) ES=6, EF=9 LS=6, LF=9 ES=16, EF=25 LS=16 LF=25 ( ) ( ) ES=9, EF=13 LS=12, LF=16 ( ) ES=0, EF=3 LS=2, LF=5 ( ) ES=13, EF=13 LS=16 LF=16 ES=3, EF=7 LS=5, LF=9 ( ) ( ) ES=3, EF=5 LS=14, LF=16 ( ) Network With Times 2 6 5 8 4 0 3 9 8 1 3 5 9 6 7 0 4 3 4 2 4 7 MA 4020 -Network Analysis

  30. Project Variance Project variance is the sum of the variances along the critical path s2 = s2 13 + s2 35 + s2 58 + s2 89 = 1.00 +0.11 + 1.78 + 4.00 = 6.89 weeks MA 4020 -Network Analysis

  31. Probabilistic Network Analysis Determine the probability that a project is completed (project completion time is ) within a specified period of time where m = tp = project mean time s = project standard deviation x = project time (random variable) Z = number of standard deviations of x from the mean (standardized random variable)  x - m Z = s MA 4020 -Network Analysis

  32. Normal Distribution Of Project Time Probability Zs m = tp x Time MA 4020 -Network Analysis

  33. Standard Normal Distribution Of transformed Project Time Probability Z m =0 z Time MA 4020 -Network Analysis

  34. Probabilistic Analysis Example What is the probability that the project is completed within 30 weeks? P(X 30) = ? s2 = 6.89 weeks s= 6.89 = 2.62 weeks Z = x - m =30 - 25 = 1.91 P(Z  1.91) = ? s 2.62 MA 4020 -Network Analysis

  35. . . . . . . . . . Determining Probability From Z Value Z 0.00 0.01 .. 04 … 0.09 1.1 0.3643 0.3665 0.3729 1.9 0.4713 …0.4767 +0.4719 P( x < 30 weeks) = 0.50+ 04719 = 0.9719 m = 25 x = 30 Time (weeks) MA 4020 -Network Analysis

  36. What is the probability that the project will be completed within 22 weeks? 22 - 25 -3 2.62 2.62 = = -1.14 Z = P(Z< -1.14) = 0.1271 x = 22 m = 25 x=28 Time (weeks) P( x< 22 weeks) = 0.1271 MA 4020 -Network Analysis

  37. Benefits of PERT/CPM • Useful at many stages of project management • Mathematically simple • Uses graphical displays • Gives critical path & slack time • Provides project documentation • Useful in monitoring costs MA 4020 -Network Analysis

  38. Advantages of PERT/CPM Networks generated provide valuable project documentation and graphically point out who is responsible for various project activities Applicable to a wide variety of projects and industries Useful in monitoring not only schedules, but costs as well MA 4020 -Network Analysis

  39. Limitations of PERT/CPM • Assumes clearly defined, independent, & stable activities • Specified precedence relationships • Activity times (PERT) follow beta distribution • Subjective time estimates • Over-emphasis on critical path MA 4020 -Network Analysis