An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. QRL kick-off meetingPresentation of the cryogenic extensions for the QRL project A. Bouillot - AT/ACR 20.10.2005

  2. Content • Introduction • Type, location and numbers • Activities supplied by Air Liquide • Components, external supports, interconnections, … • Documentation and drawings • Engineering design • Main issues and status (external supports and cryogenic extensions elements) • Fabrication • Main issues and status (external supports, cryogenic extensions elements, conditioning and tests) • Installation • Main issues and status (external supports, transport, positioning and adjustment of the elements, leak tests, …) • Schedule and planning A. Bouillot, AT/ACR-cd, 2005.10.20

  3. Introduction • A cryogenic extension allows to link the QRL jumpers to different clients (DFBA, DFBL, Q6, ACS). • The diameter of the cryogenic extensions is 355.6 mm A. Bouillot, AT/ACR-cd, 2005.10.20

  4. Introduction • They are composed of several interconnection pipes (between 4 and 9 pipes) with different internal diameters (from 10 mm to 80 mm) Interface of the cryogenic extension element QRLXD (sector 8-1) Interface of the cryogenic extension element QRLXE (sector 8-1) A. Bouillot, AT/ACR-cd, 2005.10.20

  5. Introduction • Type, number and location • Different designs : • Straight elements  about 3m with diameter 355 mm • Elbow elements  about 2.5x2.5 m2 each • Weight : ~ 80 kg/m A. Bouillot, AT/ACR-cd, 2005.10.20

  6. Activities supplied by Air Liquide • External supports • Design • Procurement • Transport to CERN • Elements : • Design, fabrication, conditioning • Transport to CERN • Interconnections • Design • Procurement of the different components: vacuum jackets, MLI A. Bouillot, AT/ACR-cd, 2005.10.20

  7. Documentation • Drawings associated with each cryogenic extension • All Drawings are available on the AT/ACR-cd server : • \Srv2_div\CRYO\ACR-CD\Projects\QRL\Drawings\Plans TIF-PDF AL\cryo extensions\ A. Bouillot, AT/ACR-cd, 2005.10.20

  8. Engineering design • Straight and elbow pipes are in Invar material • The extremities of each interconnection pipes are equipped with Stainless Steel sleeves • Most of cryogenic extensions have no active thermal shield. Each interconnection pipe is equipped with MLI. Only cryogenic extensions QRLXF and QRLXH (linking ACS) have active thermal shield. • The vacuum jacket is in Stainless Steel. • The number of elements composing one cryogenic extension can vary from 1 to 4 elements. • Interconnection pipes are supported inside the vacuum jacket with spacers • The thermal losses per meter is around equal to ~ 1.5 W/m. • External interconnections are made with rigid sleeves. • Horizontal cardan compensator on QQS jumper side. • Flexible hoses are added on Q6 and DFBA side for the cryogenic extensions QRLXD, QRLXA, QRLXC, QRLXK and QRLXL. A. Bouillot, AT/ACR-cd, 2005.10.20

  9. Engineering design • Status A. Bouillot, AT/ACR-cd, 2005.10.20

  10. Fabrication • Main issues • The fabrication takes place at DTA (Air Liquide-Sassenage). • Each interconnection pipe (Invar) is He tested after the prefabrication. • The possible weld interfaces can be : • Stainless Steel / Invar • Invar / Invar • Each weld is X-rayed (norm EN 25817-Class B) and have associated qualifications • Each cryogenic extension undergoes the following tests : • Pressure test • He test • Cold test A. Bouillot, AT/ACR-cd, 2005.10.20

  11. Fabrication Cryogenic extension HCQRLXE100-AL000001 • QRLXE Element HCQRLXE103-AL000001 Element HCQRLXE102-AL000001 Element HCQRLXE104-AL000001 Element HCQRLXE101-AL000001 A. Bouillot, AT/ACR-cd, 2005.10.20

  12. Fabrication • QRLXD Cryogenic extension HCQRLXD100-AL000001 A. Bouillot, AT/ACR-cd, 2005.10.20

  13. Fabrication • Status • HCQRLXE100-AL000001  85% • 3 elements (HCQRLXE101-AL000001, HCQRLXE102-AL000001, HCQRLXE103-AL000001) are already fabricated (succeed in the cold test) • HCQRLXE104-AL000001 is prepared for the tests • HCQRLXD100-AL000001  70% • HCQRLXD100-AL000001 is under fabrication (installation of the vacuum jacket) • Others  0% A. Bouillot, AT/ACR-cd, 2005.10.20

  14. Fabrication • Cryogenic extension QRLXE Element HCQRLXE101-AL000001 Element HCQRLXE103-AL000001 A. Bouillot, AT/ACR-cd, 2005.10.20

  15. Fabrication • Cryogenic extension QRLXE Element HCQRLXE101-AL000001 Element HCQRLXE102-AL000001 Element HCQRLXE103-AL000001 A. Bouillot, AT/ACR-cd, 2005.10.20

  16. Fabrication • Cryogenic extension QRLXD Element HCQRLXD100-AL000001 A. Bouillot, AT/ACR-cd, 2005.10.20

  17. Fabrication • Conditionnement • Double housse thermo soudable • Mise en place de l'élément dans la première housse • Soudage de la housse • Avant fermeture de celle ci balayage azote (mesure hygrométrie) • Mise sous vide de l'enveloppe (à l'aspirateur) • Fermeture de l'enveloppe • Scellement de la 2eme housse avec déshydratant • La 2eme housse sera réalisée avec un complexe épais et résistant • L'ensemble conditionné sous housse est posé sur un plateau de type habituel. A. Bouillot, AT/ACR-cd, 2005.10.20

  18. Installation • External supports for HCQRLXD100-AL000001: Supports C1105S285 Supports C1105S286 A. Bouillot, AT/ACR-cd, 2005.10.20

  19. Installation • External supports C1105S286: A. Bouillot, AT/ACR-cd, 2005.10.20

  20. Installation • External supports C1105S285: A. Bouillot, AT/ACR-cd, 2005.10.20

  21. Installation • External supports for HCQRLXE100-AL000001: Support C1105S381 Support C1105S382 A. Bouillot, AT/ACR-cd, 2005.10.20

  22. Installation • External supports C1105S381: A. Bouillot, AT/ACR-cd, 2005.10.20

  23. Installation • External supports C1105S382: A. Bouillot, AT/ACR-cd, 2005.10.20

  24. Installation • Activities supplied by CERN • Handling • Transport CERN/tunnel with dedicated tooling • Positioning and adjustment • Interconnections : • welding : same interface type as standard jumper connection (+ leak tests associated) • Installation of rings and sleeves : • D < 30 mm  rings • D ≥ 30 mm  sleeves • MLI : 30 layers on each interconnection pipe • Welding of external rigid sleeve A. Bouillot, AT/ACR-cd, 2005.10.20

  25. Installation • Activities supplied by CERN • Interconnections : Rings for diameter pipes 10/12 mm Sleeves A. Bouillot, AT/ACR-cd, 2005.10.20

  26. Schedule and planning • Planning (supplied by R. Girardot on 19.10.2005) A. Bouillot, AT/ACR-cd, 2005.10.20

  27. Cryogenic extensions project • Link person for AT/ACR : A. Bouillot • Link person for other activities : to be defined • Periodic meetings : every two weeks ??? • Proposed subject for next meeting: finalization of organization A. Bouillot, AT/ACR-cd, 2005.10.20