ESPLOST Update Savannah-Chatham County Public Schools August 1, 2007
ESPLOST Fourth payment received • $5,292,731.43 (May Collections) • Total of $24,107,940.79 • G.O. Bond Debt Payment of approximately $12 Million due August 1, 2007
ESPLOST Project Management • URS in association with Pat Mathis was selected on July 11. • Contract Review • URS has prepared draft schedule of construction • Goal to open at least 3 schools in Fall 2009
ESPLOST ESPLOST Project Updates • Woodville-Tompkins • Phase I on schedule • W/T Phase II • Architect Selection – August 1 • Safety Fencing • Extending Bid Timeline due to low response on initial bid • Godley Station Land Study • Site Selection Criteria for DOE
ESPLOST • ESPLOST Financial Reporting • Updated Monthly • Synchronization with Program Management Data
ESPLOST Update Board Discussion / Questions