Fullerton CollegePhysical Education Project Community Meeting March 11, 2009
Discussion Items • Community Concerns • Initial Study – CEQA Requirements • Status of Project • Lighting • Bleachers • Sound System • Traffic • Project Phases • Project Budget
N. BERKELEY AVE. • Phase 1 • Olympic Pool • 50 Meter Pool Replaces • Old 25 Meter Pool • 1 Meter and 3 Meter • Springboards • Pool Pump House • Building • Fire Pump Building • Serves as Additional • Fire Protection to Campus • Tennis Courts • Refurbished • New Fire Lane N. LEMON ST. N. BERKELEY AVE. FIRE LANE E. CHAPMAN AVE. Fullerton College Athletics Project
Phase 2A • Artificial Turf Fields • Football, Soccer and • Track and Field per NCAA • Standards • 1,500 Seat Home Bleacher & • Pressbox • 500 Seat Visitors Bleacher • Six 100 ft. Light Poles with • Directional Reflectors • 76.6 footcandles for games • (30 footcandles for simple use) • 0.6 footcandles at 100 ft east • (1.5 footcandles on vertical) • 0.16 footcandles at 150 ft east • ( 0.5 footcandles on vertical) • Fieldhouse • 20,000 sf / 2 Stories • Locker Rooms/Training • Field Support Services • 3 Classrooms • 10 Offices • 6 Workstations • Roof Plaza Assembly • Space (1,800 sf) • 60 New Parking Stalls Level 2 Level 1 N. BERKELEY AVE. N. LEMON ST. N. BERKELEY AVE. Light Pole Reflectors E. CHAPMAN AVE. Fullerton College Athletics Project
Phase 2C • Dance Studio • New Lighting and A/C • Refinished Floors and Paint • Corridors • New Lighting, Floors, and Paint • Restrooms • Storage • Phase 2B • South Gym • New Lighting and A/C • Refinished Floors, Paint • Refurbished Basketball Equipment • Women’s Locker Room • New Lighting and Ventilation • Refurbished and New Showers • New Dedicated Team Rooms • New Bathrooms • Coaches Locker Rooms • Officials Changing Rooms • Equipment Storage Fullerton College Athletics Project
Phase 2E • Outdoor Sports Court • New Sand Volleyball Pit • New Basketball Half-Court • Refurbished Strength Lab • Expanded Training Facilities • New Circuit Lab • Phase 2D • North Gym • New Power Retractable Bleachers w/Assistive Listening • Refinished Floors • New Lighting and A/C • Mezzanines • Renovated for Multi-Purpose Use • New Lights, A/C & Paint • (16) Offices & (2) Meeting Spaces • New Storage • Men’s Locker Room • New Lighting and Ventilation • New Lockers • Refurbished and New Showers • New Dedicated Team Rooms • New Bathrooms Fullerton College Athletics Project
N. BERKELEY AVE. • Additional Work • Playing Field • Bleachers/Pressbox • Jump Events • Signage • Throwing Field • Doors • Security • Access Hardware • Value Engineering • Dance Studio • Floor Repair • Ballet Bars • South Gym • Bleachers N. LEMON ST. N. BERKELEY AVE. E. CHAPMAN AVE. Fullerton College Athletics Project