50 likes | 206 Views
Health Sector. Update. Total to be Reconstructed 307 Target for 2006-07 & 2007-08 237/293 (95.43%) 237/307 (100%). * BHU Reshiyan by PRCS under construction. Forecast (July 2008) = Expected completion – 13 HF (4 RHC + 9 BHU). Construction Status - District Wise. *Rs. in Million.
E N D
Update • Total to be Reconstructed 307 • Target for 2006-07 & 2007-08 237/293 (95.43%) 237/307 (100%) * BHU Reshiyan by PRCS under construction Forecast (July 2008) = Expected completion – 13 HF (4 RHC + 9 BHU)
Construction Status - District Wise *Rs. in Million
Construction Status GoP - District Wise * 9 WHO prefab completed
Construction Status D&S- District Wise * 9 WHO prefab completed