1 / 15

MOSC Meeting Operations Market Manual updates

MOSC Meeting Operations Market Manual updates. October 22, 2003 Presented by: Ron Falsetti Steve Cooper. Changes. MM 4.3 - Real-Time Scheduling of Ph. Mkts. IMO - NYISO Scheduling Protocol (IMDC 0051) Dispatch instruction enhanced filtering (IMDC 0053)

creda
Download Presentation

MOSC Meeting Operations Market Manual updates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MOSC MeetingOperations Market Manual updates October 22, 2003 Presented by: Ron Falsetti Steve Cooper

  2. Changes • MM 4.3 - Real-Time Scheduling of Ph. Mkts. • IMO - NYISO Scheduling Protocol (IMDC 0051) • Dispatch instruction enhanced filtering (IMDC 0053) • MM 7.1, 7.4 Policies, Procedures & 7.8 OPSRP - Changes arising from: • August 14th blackout + other contingencies; • Power system restoration exercises; • Operating reserve pricing initiative;and • Voltage reduction test results.

  3. IMO - NYISO Scheduling Protocol

  4. IMOpre-dispatch schedule incorporatingNYISODay Ahead commitments posted IMOdetermines and posts first pre-dispatch schedule 15:30 11:00 12:00 14:00 15:00 NYISO passes Day-Ahead commitments (with pre-schedules identified) to the IMO NYISO posts Day-Ahead interchange schedules IMO-NYISO Scheduling Protocol IMO Pre-Dispatch /NYISODay Ahead Period

  5. IMO determines projected interchange schedules for the dispatch hour based on 2-hour ahead pre-dispatch run and passes them toNYISO IMOandNYISO confirm final interchange schedules T-75 T-30 T-60 T-100 Dispatch Hour T-40 T-120 T=0 NYISOhour ahead market closes NYISOfilters BME bids using information on interchange schedules accepted by the IMO2-hour ahead pre-dispatch NYISOruns BME and posts BME results IMO-NYISO Scheduling Protocol IMOHourly Pre-Dispatch /NYISOBalancing Market Evaluation Period

  6. Dispatch Instruction Filtering

  7. Existing Dispatch Filtering • Filter prevents sending out dispatch instructions for small changes in scheduled quantities • New dispatch instructions issued for provision of energy change from the previous dispatch instruction provided greater than the lesser of 2% of maximum offer/bid capability and 10 MW

  8. Filtering Enhancements • More adaptive filtering capability to help maintain adequacy and minimize CMSC that: • disables filtering of dispatch instruction within filter thresholds for: • energy resource dispatches to the facilities HIGH or LOW operating limit; and • energy reduction changes when previous dispatch instruction is > max. offer

  9. Filtering Enhancements cont’d • disables filtering every 30 minutes & prior to dispatch hour (intervals 1, 7 and 12) • permits filter thresholds to be energy resource configurable

  10. Operating Policies and Procedures

  11. Policies & Procedures • Enhance operational communication protocols & communication content involving the IMO, transmitters & connected marketparticipants • Potential changes to controlled rotational & U/F load shedding • Clarify procedures for emergency reduction of majorgenerating facility output to mitigate OSL after a contingency.

  12. OPSRP • Emergency Preparedness Task Force annual review of OPSRP - after the Nov. 26, 2003 exercise • Lessons learned from the Aug. 14 blackout • EPTF sponsored Restoration Working Group feedback - end of Nov.

  13. OPSRP Cont’d • Reinforce need for key facility and critical component testing • Reinforce need for restoration plan market participants to open circuit breakers

  14. Control Action Breakers

  15. Control Action Breakers • By removing from service certain circuit breakers & eliminating the breaker failure contingency there are opportunities to improve transfer capabilities • This is required for TLR (TLR 4), but can also help to relieve interface congestion, enhance our ability to mitigate adequacy concerns, and provide additional transaction opportunities • Should this policy change be adopted it would require changes to market manual 7.4 and Appendix E “EOSCA list”

More Related