An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PROGRESS REPORTFEBRUARY 2012 • Published March 20, 2012

  2. The Banks Project

  3. Master Development Plan

  4. Executive Summary

  5. Summary: Construction • February 2012: Close-out • BP#9—Mehring Way guardrail installation complete. • BP#11—Outstanding punch list items being addressed. • All that’s left is the paperwork! • Public Safety Technologies work ramping up • BP#12—Contract awarded to ESI; work already underway

  6. Bid Package #12 Street Grid/Pedestrian Improvements Design • Pedestrian walkway and street improvements planned • Part 2 of BP#12 to be bid Fall 2012—sidewalk upstream side of Roebling Bridge, pedestrian bring over Pete Rose Way, construction of Ohio River Trail segment • Part 1 of BP#12 to be bid Spring 2013—widening of Second Street sidewalk, removal of Race Street Bridge, reconstruction of portion of Freedom Way, completion of Public Safety technology

  7. Summary: Budget • All public parties construction (Phases 1 and 2a) work have operated continuously within budget. • Approx. $1M Phase 1 contingency can be moved to Phase 2a • http://www.thebankspublicpartnership.com/sites/default/files/budget-detail-feb2012.pdf

  8. Summary: Developer • Carter-Dawson: • Phase 1a residential is 99% leased • Retail is 80% leased

  9. Developer’s Leasing Activity • Holy Grail, Johnny Rockets, Toby Keith, and Police Welcome Center open and operating. • The Tin Roof and Crave are finalizing permits and preparing to start construction. • Mahogany’s lease is executed; project is in design phase. • Lease executed with The Wine Guy; design is underway. • Ruth’s Chris is designing their space; construction anticipated to begin second quarter 2012.

  10. Economic Inclusion

  11. Summary: Economic Inclusion • The Project maintained the 36% SBE participation commitment (goal for Construction is 30%) as of 1/25/12. • SBE: 36% • MBE: 15.9% • WBE: 2.8% • Professional Services (SBE goal is 10%) • SBE: 8.1%

  12. Economic Inclusion f Bid Packages #5, #6, and #7 are closed out. Substantial work was completed this month by the DBE contractors on Bid Packages #9 & #11; final billings are projected to meet ODOT goals. Click here for Economic Inclusion reports: http://www.thebankspublicpartnership.com/sites/default/files/economic-inclusion-feb2012.pdf • .

  13. Economic Inclusion • Combined Minority/Female Workforce participation is 17.44% as of 1/25/12. • Minority Workforce (female and male) is 16.14% • For the one-month period ending 1/25/12, a total of 89.3% of workers lived within the 15-County Cincinnati-Middletown MSA • Local residency analysis 1,406 workers (through 12/25/11) • Tri-State 97.7% • Cincinnati-Middletown MSA 77% • Hamilton County 25.5% • City of Cincinnati 9.2% • There are no local residency participation goals.

  14. Summary: Safety • The Project has logged over 416,000 hours worked without a lost-time accident for both Public Parties construction phases through Bid Package #11.

  15. Cincinnati Parks

  16. Cincinnati Parks • Phase 1 Walnut Street Fountain and Grand Stairway to open in early Spring. • Bike Center design completed in February; scheduled to open in early Spring. • Schmidlapp Event Lawn and Stage canopy will be completed late March. • Work at Smale Riverfront Park Phase 3 continued. • Moerlein Lager House opened 2/27/12.

  17. Cincinnati ParksWork South of Mehring Way

  18. Cincinnati Parks

  19. Communications • The Banks Project in the News • Over 20 articles mentioning The Banks in February and two progress update presentations delivered. • http://www.thebankspublicpartnership.com/sites/default/files/media-summary.pdf

  20. Progress: February 2012 For more information: John F. Deatrick The Banks Project Executive (513) 946-4434 john.deatrick@hamilton-co.org http://www.thebankspublicpartnership.com