1 / 15

Cavity Preparation for S1-Global

Cavity Preparation for S1-Global. Eiji Kako (KEK, Japan). 1. KEK Cavities for S1-G 2. DESY Cavities for S1-G FNAL Cavities for S1-G Present Status of Preparation Schedule of Cavity Assembly. Outline. Five Cavities at KEK for S-1 Global. STF-BL #7 Cavity (MHI-07)

crwys
Download Presentation

Cavity Preparation for S1-Global

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Cavity Preparation for S1-Global Eiji Kako (KEK, Japan) ILC meeting @ KEK Global Design Effort

  2. 1.KEK Cavities for S1-G • 2. DESY Cavities for S1-G • FNAL Cavities for S1-G • Present Status of Preparation • Schedule of Cavity Assembly Outline ILC meeting @ KEK Global Design Effort

  3. Five Cavities at KEK for S-1 Global STF-BL #7 Cavity (MHI-07) STF-BL #8 Cavity (MHI-08) STF-BL #9 Cavity (MHI-09) STF-BL #5 Cavity (MHI-05) STF-BL #6 Cavity (MHI-06) Delivery in 2008’ March Delivery in 2009’ March ILC meeting @ KEK Global Design Effort

  4. Surface Preparation at STF EP Hot bath Rinse C2H5OH, Degrease Flange-CP Assembly (Class 10) HPR Infrastructure in the STF Hall System check with AES#1 cavity was carried out in Oct., 2008. Vertical Test Inspection of Inner Surface Pre-tuning fo adjustment Hanging Stand Baking (Class 1000) ILC meeting @ KEK Global Design Effort

  5. Summary of VT at STF (MHI-05 ~ 09) Oct, 2009 Cavities for S1-G 5 Cavities 15 Vert.Tests for 1 year (Dec. 2008’ ~ Nov. 2009’) Oct. 29 Nov. 12 Nov. 26 ILC meeting @ KEK Global Design Effort

  6. Four KEK Cavities for S1-Global Oct, 2009 STF Phase-1 MHI-01,02,03,04 20, 30, 20, 20 MV/m ave. Eacc,max = 22.7 MV/m ave. + 5.7 MV/m S1-Global MHI-05,06,07,09 27, 28, 34, 25 MV/m ave. Eacc,max = 28.4 MV/m ILC meeting @ KEK Global Design Effort

  7. Eacc,max (cell) by Passbands modes Meas. Quench by Field emission MHI-05 3rd MHI-06 6th Quench p mode; Eacc,max = 27.7 MV/m > 30. MV/m p mode; Eacc,max = 27.1 MV/m > 35. MV/m Quench Quench by Field emission MHI-09 1st MHI-07 2nd > 35. MV/m p mode; Eacc,max = 33.6 MV/m ~ 40. MV/m p mode; Eacc,max = 25.0 MV/m Oct, 2009 ILC meeting @ KEK Global Design Effort

  8. Two DESY Cavities for S1-Global (NOT official information !! ) 25 June 2009 03 Aug. 2009 . Vertical test with He Jacket . No bead measurement after VT to avoid contamination . Installation of a cold coupler . Installation of two HOM probes, and adjust HOM filter . Transportation to KEK in the mid. of November ILC meeting @ KEK Global Design Effort

  9. Two FNAL Cavities for S1-Global (NOT official information !! ) AES002 Cavity (?) ACCEL-8 Cavity (?) (No Qo – Eacc data ??) (No Qo – Eacc data ??) . 32.8 MV/m tested at JLab . Reserved at FNAL . To be 3rd dressed cavity . 30.6 MV/m tested at JLab . Reserved at JLab . To be sent to FNAL . To be 6th dressed cavity . When ?? He Jacket Welding . When ?? Installation of a cold coupler . Installation of two HOM probes, and adjust HOM filter ?? . Transportation to KEK in the mid. of December ILC meeting @ KEK Global Design Effort

  10. Eight Cavities for S1-Global 1. MHI-05 (27.1 MV/m) ; Slide-Jack tuner (center) 2. MHI-06 (27.7 MV/m) ; Slide-Jack tuner (center) 3. MHI-07 (33.6 MV/m) ; Slide-Jack tuner (end) 4. MHI-09 (25.0 MV/m) ; Slide-Jack tuner (end) 5. Zanon-108 (31.3 MV/m) ; Saclay tuner (end) 6. Zanon-109 (30.7 MV/m) ; Saclay tuner (end) 7. AES-002 ? (32.8 MV/m) ; Blade tuner (center) 8. ACCEL-8 ? (30.6 MV/m) ; Blade tuner (center) MHI (Japan), Zanon (Italy), AES (USA), ACCEL/RI (Germany) Qualified Vendor !! ILC meeting @ KEK Global Design Effort

  11. Cavity Transportation for S1-Global This week !! Transportation Route ; FNAL  DESY ( Oct.) KEK  DESY (mid. Nov.) KEK  FNAL (end. Nov.) KEK  FNAL (mid. Dec.) Four cavities from DESY/FNAL will be ready at KEK in the end of December. ILC meeting @ KEK Global Design Effort

  12. Cavity Assembly for S1-Global KEK String Assembly Tuner Installation KEK Warm Coupler Installation DESY & FNAL String Assembly Tuner & Mag. Shield Installation DESY Warm Coupler Installation ILC meeting @ KEK Global Design Effort

  13. Cryomodule Tests for S1-Global • High RF Power Measurements • RF meas. (QL, Qt, QHOM) • Cavity conditioning with 1.5 ms • Cavity conditioning with 0.6 ms • Mechanical vibration modes (5Hz) • RF feedback on/off by LLRF • Observation of Lorentz Detuning • Compensation of Lorentz Detuning • Dynamic RF loss measurement • 4 Cavity operation with vector-sum • 8 Cavity operation with vector-sum • Long time operation at 31.5 MV/m • etc. • Low RF Power Measurements • Slide-Jack Tuner stroke • Piezo tuner stroke • RF meas. (QL, Qt, QHOM) • HOM Qext • Frequency stability • Mechanical vibration modes • Pulse response by Piezo drive • etc. Coupler conditioning at room temp. ILC meeting @ KEK Global Design Effort

  14. Meeting for S1-G preparation • KEK visit of Jim Kerby (FNAL), 10th -12th, Nov. • Video/Webex meeting for S1-G preparation • pm.10:00~12:00 in 11th, Nov. at KEK, • in participation of DESY and FNAL colleagues • Main topics on discussion; • (Share of collaboration works for S1-G) • . Cavity string assembly • . Tuner & mag. shield assembly • . Tuner testing • . Input coupler assembly (warm parts) • . Conditioning of input coupler at room temp. • . etc. ILC meeting @ KEK Global Design Effort

  15. Thank you for your attention..... ILC meeting @ KEK Global Design Effort

More Related