150 likes | 387 Views
Cavity Preparation for S1-Global. Eiji Kako (KEK, Japan). 1. KEK Cavities for S1-G 2. DESY Cavities for S1-G FNAL Cavities for S1-G Present Status of Preparation Schedule of Cavity Assembly. Outline. Five Cavities at KEK for S-1 Global. STF-BL #7 Cavity (MHI-07)
E N D
Cavity Preparation for S1-Global Eiji Kako (KEK, Japan) ILC meeting @ KEK Global Design Effort
1.KEK Cavities for S1-G • 2. DESY Cavities for S1-G • FNAL Cavities for S1-G • Present Status of Preparation • Schedule of Cavity Assembly Outline ILC meeting @ KEK Global Design Effort
Five Cavities at KEK for S-1 Global STF-BL #7 Cavity (MHI-07) STF-BL #8 Cavity (MHI-08) STF-BL #9 Cavity (MHI-09) STF-BL #5 Cavity (MHI-05) STF-BL #6 Cavity (MHI-06) Delivery in 2008’ March Delivery in 2009’ March ILC meeting @ KEK Global Design Effort
Surface Preparation at STF EP Hot bath Rinse C2H5OH, Degrease Flange-CP Assembly (Class 10) HPR Infrastructure in the STF Hall System check with AES#1 cavity was carried out in Oct., 2008. Vertical Test Inspection of Inner Surface Pre-tuning fo adjustment Hanging Stand Baking (Class 1000) ILC meeting @ KEK Global Design Effort
Summary of VT at STF (MHI-05 ~ 09) Oct, 2009 Cavities for S1-G 5 Cavities 15 Vert.Tests for 1 year (Dec. 2008’ ~ Nov. 2009’) Oct. 29 Nov. 12 Nov. 26 ILC meeting @ KEK Global Design Effort
Four KEK Cavities for S1-Global Oct, 2009 STF Phase-1 MHI-01,02,03,04 20, 30, 20, 20 MV/m ave. Eacc,max = 22.7 MV/m ave. + 5.7 MV/m S1-Global MHI-05,06,07,09 27, 28, 34, 25 MV/m ave. Eacc,max = 28.4 MV/m ILC meeting @ KEK Global Design Effort
Eacc,max (cell) by Passbands modes Meas. Quench by Field emission MHI-05 3rd MHI-06 6th Quench p mode; Eacc,max = 27.7 MV/m > 30. MV/m p mode; Eacc,max = 27.1 MV/m > 35. MV/m Quench Quench by Field emission MHI-09 1st MHI-07 2nd > 35. MV/m p mode; Eacc,max = 33.6 MV/m ~ 40. MV/m p mode; Eacc,max = 25.0 MV/m Oct, 2009 ILC meeting @ KEK Global Design Effort
Two DESY Cavities for S1-Global (NOT official information !! ) 25 June 2009 03 Aug. 2009 . Vertical test with He Jacket . No bead measurement after VT to avoid contamination . Installation of a cold coupler . Installation of two HOM probes, and adjust HOM filter . Transportation to KEK in the mid. of November ILC meeting @ KEK Global Design Effort
Two FNAL Cavities for S1-Global (NOT official information !! ) AES002 Cavity (?) ACCEL-8 Cavity (?) (No Qo – Eacc data ??) (No Qo – Eacc data ??) . 32.8 MV/m tested at JLab . Reserved at FNAL . To be 3rd dressed cavity . 30.6 MV/m tested at JLab . Reserved at JLab . To be sent to FNAL . To be 6th dressed cavity . When ?? He Jacket Welding . When ?? Installation of a cold coupler . Installation of two HOM probes, and adjust HOM filter ?? . Transportation to KEK in the mid. of December ILC meeting @ KEK Global Design Effort
Eight Cavities for S1-Global 1. MHI-05 (27.1 MV/m) ; Slide-Jack tuner (center) 2. MHI-06 (27.7 MV/m) ; Slide-Jack tuner (center) 3. MHI-07 (33.6 MV/m) ; Slide-Jack tuner (end) 4. MHI-09 (25.0 MV/m) ; Slide-Jack tuner (end) 5. Zanon-108 (31.3 MV/m) ; Saclay tuner (end) 6. Zanon-109 (30.7 MV/m) ; Saclay tuner (end) 7. AES-002 ? (32.8 MV/m) ; Blade tuner (center) 8. ACCEL-8 ? (30.6 MV/m) ; Blade tuner (center) MHI (Japan), Zanon (Italy), AES (USA), ACCEL/RI (Germany) Qualified Vendor !! ILC meeting @ KEK Global Design Effort
Cavity Transportation for S1-Global This week !! Transportation Route ; FNAL DESY ( Oct.) KEK DESY (mid. Nov.) KEK FNAL (end. Nov.) KEK FNAL (mid. Dec.) Four cavities from DESY/FNAL will be ready at KEK in the end of December. ILC meeting @ KEK Global Design Effort
Cavity Assembly for S1-Global KEK String Assembly Tuner Installation KEK Warm Coupler Installation DESY & FNAL String Assembly Tuner & Mag. Shield Installation DESY Warm Coupler Installation ILC meeting @ KEK Global Design Effort
Cryomodule Tests for S1-Global • High RF Power Measurements • RF meas. (QL, Qt, QHOM) • Cavity conditioning with 1.5 ms • Cavity conditioning with 0.6 ms • Mechanical vibration modes (5Hz) • RF feedback on/off by LLRF • Observation of Lorentz Detuning • Compensation of Lorentz Detuning • Dynamic RF loss measurement • 4 Cavity operation with vector-sum • 8 Cavity operation with vector-sum • Long time operation at 31.5 MV/m • etc. • Low RF Power Measurements • Slide-Jack Tuner stroke • Piezo tuner stroke • RF meas. (QL, Qt, QHOM) • HOM Qext • Frequency stability • Mechanical vibration modes • Pulse response by Piezo drive • etc. Coupler conditioning at room temp. ILC meeting @ KEK Global Design Effort
Meeting for S1-G preparation • KEK visit of Jim Kerby (FNAL), 10th -12th, Nov. • Video/Webex meeting for S1-G preparation • pm.10:00~12:00 in 11th, Nov. at KEK, • in participation of DESY and FNAL colleagues • Main topics on discussion; • (Share of collaboration works for S1-G) • . Cavity string assembly • . Tuner & mag. shield assembly • . Tuner testing • . Input coupler assembly (warm parts) • . Conditioning of input coupler at room temp. • . etc. ILC meeting @ KEK Global Design Effort
Thank you for your attention..... ILC meeting @ KEK Global Design Effort