Attention !! Draft Proposal. Cavity String Assembly Procedure for S1-Global. Eiji Kako (KEK, Japan). Preparation of cavity string assembly ( 12-21, January 2010 ) 2. String assembly of four cavities ( 22-26, January 2010 ) 3. Vacuum leak check & Ar slow-leak
E N D
Attention !! Draft Proposal Cavity String Assembly Procedure for S1-Global Eiji Kako (KEK, Japan) • Preparation of cavity string assembly • (12-21, January 2010) • 2. String assembly of four cavities • (22-26, January 2010) • 3. Vacuum leak check & Ar slow-leak • (27-31, January 2010) S1-G Webex meeting Global Design Effort
Cavity Assembly Team for S1-Global FNAL Tug Arkan (Leader) Brian Smith DESY Axel Matheisen (Supervisor) Manuela Schmoekel ??? KEK Shuich Noguchi Eiji Kako S1-G Webex meeting Global Design Effort
List of clean room work (1) 1. Preparation for Cavity Assembly (1000 & 10) • Checking of all tools & jigs for assembly • Cleaning of cavity support post & table (1000) • Cleaning of outside of cavity package (1000) • Setting a cavity on the support table (1000) • Rough alignment of 4 cavities (1000) • Cleaning of 3 bellows between 2 cavities (10) • Cleaning of 1 gate-valve (10) • Cleaning of 1 taper beam tube (10) • Cleaning of 1 blind flange (10) • Cleaning of bolts and nuts (10) • Cleaning of Al sealing material (10) l. etc........ S1-G Webex meeting Global Design Effort
List of clean room work (2) 2. Cavity String Assembly (class 10) • Ar gas slow-leak into a cavity up to 1 atm • Alignment of cavity rotation • Introduction of Ar gas flow into #1 cavity • Installation of a taper beam tube to #1 cavity • Installation of a gate-valve to #1 cavity • Connection of #1 - #2 cavities with a bellows • Connection of #2 - #3 cavities with a bellows • Connection of #3 - #4 cavities with a bellows • Attachment of a blind flange to #4 cavity • Move to class 1000 for pumping & leak check • Ar gas slow-leak into 4 cavities up to 1 atm S1-G Webex meeting Global Design Effort
Clean Room at KEK-STF Clean room at STF Entrance HPR Air Shower Pass-box 5.4 m To cryomodule assembly area Class 1000 Class 10 Water Shower 2.2 m 7 m 16.2 m Pass-box S1-G Webex meeting Global Design Effort
Infrastructure in STF clean room Entrance of cavity (car washer, 8 MPa) Entrance for men & women Air shower for men & women Exit of string cavities outside CR S1-G Webex meeting Global Design Effort
Infrastructure in clean room (c-1000) Ultra-sonic bath, Ultra-pure water He leak detector, Pumping system S1-G Webex meeting Global Design Effort
Infrastructure in clean room (class-10) Top Gun and Particle counter Vacuum parts on a table 1st Gas line of dry air, Ar, He, N2 S1-G Webex meeting Global Design Effort
Slow-leak procedure for filling Ar gas Class 1000 Flow rate of Ar gas = 60 ~ 100 ml / min Filter = particles > 0.003 um, >99.999999% Release valve = 1/3 PSI S1-G Webex meeting Global Design Effort
Schedule of cavity assembly (1) January 2010, (Preparation by KEK) 11 Mon;National Holiday 12 Tue;am/pm “”Check of tools and jigs for assembly”“ 13 Wed;am/pm Rinsing of 9 support posts by car washer Set-up of support posts in class-1000 14 Thu; am Rinsing of a cavity (outside) by car washer Installation of a cavity on support in c-1000 pm Rinsing of a cavity (outside) by car washer Installation of a cavity on support in c-1000 Rough alignment of 2 cavities in c-1000 S1-G Webex meeting Global Design Effort
Schedule of cavity assembly (2) (Preparation by KEK) 15 Fri;am Attach. of vacuum parts with #1 cavity in c-10 Ar slow-leak for 24 h (80 ml/min) in c-1000 pm Cleaning of 1 gate-valve (wiping & blower) Cleaning of 3 connection bellows (US & UPW) Cleaning of 1 taper beam tube (US & UPW) Cleaning of 1 blind flange (US & UPW) Cleaning of bolts and nuts (US & UPW) 16 Sat;am Movement of #1 cavity from c-1000 to c-10 Attach. of vacuum parts with #2 cavity in c-10 Ar slow -leak for 24 h (80ml/min) in c-1000 S1-G Webex meeting Global Design Effort
Schedule of cavity assembly (3) (Preparation by KEK) 18 Mon;am Movement of #2 cavity from c-1000 to c-10 Rinsing of a cavity (outside) by car washer Installation of a cavity on support in c-1000 pm Rinsing of a cavity (outside) by car washer Installation of a cavity on support in c-1000 Rough alignment of 2 cavities in c-1000 19 Tue; am Attach. of vacuum parts with #3 cavity in c-10 Ar slow-leak for 24 h (80 ml/min) in c-1000 20 Wed;am Movement of #3 cavity from c-1000 to c-10 Attach. of vacuum parts with #4 cavity in c-10 Ar slow -leak for 24 h (80ml/min) in c-1000 S1-G Webex meeting Global Design Effort
Schedule of cavity assembly (4) (Preparation by KEK) 21 Thu; am Movement of #4 cavity from c-1000 to c-10 Alignment of cavity rotation of 4 cavities in c-10 Check of STF clean room by FNAL & DESY colleagues pmMeeting of Cavity Assembly Team at KEK Tug, Brian, Manuela, ?(DESY), Shuichi, Eiji, Norihito Confirmation of assembly procedure, tools & jigs S1-G Webex meeting Global Design Effort
Schedule of cavity assembly (4) (Cavity string assembly by DESY & FNAL, KEK) 22 Fri ~ 26 Tue (5 days) (not correct order of works, ?? need discussion) . Cleaning of parts and jig . Setup of Ar gas flow . Attachment of a taper beam tube (#1 cavity) . Attachment of a gate-valve (#1 cavity) . Attachment of a blind flange (#4 cavity) . Connection of #1 and #2 cavities with bellows . Connection of #3 and #4 cavities with bellows . Connection of #2 and #3 cavities with bellows . etc. S1-G Webex meeting Global Design Effort
Schedule of cavity assembly (5) (Leak check by DESY & FNAL, KEK) 27 Wed ; . Movement of string cavities from c-10 to c-1000 . Vacuum pumping in c-1000 . Leak check in c-1000 . Start of Ar slow-leak 28 Thu – 29 Fri ; (Work by KEK) . Ar slow-leak for 4 ~ 2 days 30 Sat – 31 Sun ; . Spare time (if something happen,) February 01 Mon ; . Movement of string cavities from c-1000 to outside S1-G Webex meeting Global Design Effort
Preparation status at KEK (1) 2 jigs from FNAL Ordered ; 2 jigs for FNAL 2 jigs for DESY Ordered ; 4 jigs To be attached with KEK support posts Ordered ; 4 jigs S1-G Webex meeting Global Design Effort
Preparation status at KEK (2) Ordered ; 8 support table with rollers Use present 8 support posts for 4 cav. Ordered ; + 1 support post for a gate-valve Ordered ; Rotational alignment fixture S1-G Webex meeting Global Design Effort
Preparation status at KEK (3) Ordered; . Taper beam tube between #1 cavity and a gate-valve . Bellows support jigs Under design . . . etc. S1-G Webex meeting Global Design Effort
Thank you for your attentions ........ S1-G Webex meeting Global Design Effort