An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Flamboro Quarry Water Monitoring Program CAP Meeting Presentation June 21, 2010

  2. DFA has a water monitoring program for: • Creating a historical log of precipitation, pumping and water levels in the area surrounding the quarry. • Understanding the potential effect of dewatering on neighbouring domestic water supplies and environmental features. • Ensuring that water quality is not compromised. • Ensuring compliance with MOE regulations, our permit to take water (PTTW) and our Certificate of Approval for Industrial Sewage Works (C of A Discharge). Flamboro Quarry – Water Monitoring Program June 2010

  3. Legislative Requirements • The Flamboro Quarry is licensed under the Aggregate Resources Act to extract to a maximum depth of 230 mASL (we’re currently at 240 mASL). The site is approved to mine under dry conditions which requires dewatering. • In order to keep the quarry floor dry (dewatered) we need to 2 main approvals from the Ministry of Environment (MOE): • PTTW (permit to take water) was issued by the MOE – under permit No. 03-P-2355 and • Certificate of Approval for Industrial Sewage Works was also issued by the MOE – under certificate No. 0276-7DJJCA Flamboro Quarry – Water Monitoring Program June 2010

  4. Well & Sump Locations Flamboro Quarry – Water Monitoring Program June 2010

  5. PTTW Requirements • Measure water levels twice monthly from observation wells all around the property (30 of them). • Record the water levels in each sump on a weekly basis. • Monitor the quality of discharged water on a quarterly basis – TSS, alkalinity, nitrates, sulphates, metals, pH, conductivity & temperature. • Record water takings (pumping) on a daily basis and record any water used for dust suppression in the quarry. • Submit an annual report presenting and interpreting the above data each year – and outlining quarry activities, water events and any upcoming changes. Flamboro Quarry – Water Monitoring Program June 2010

  6. Certificate of Approval Requirements • To monitor and ensure water discharge remains below the limit of 17,500m3/d (average is about 2,500 - 3000m3/d, cap. is 15,500m3/d). • To monitor and ensure that pumping rates do not exceed 12,000l/min at any given time (our max capacity is 9000l/min). • To ensure that any changes to the water discharge system (pumps & pipeline) are recorded – and elements of the system remain within what is outlined in the certificate. Flamboro Quarry – Water Monitoring Program June 2010

  7. Certificate of Approval Requirements (cont’d)… • - Routine inspections of the water pumping, monitoring and discharge system – including flow meter calibrations. • Keeping a log book of inspections and any resulting repairs. • Sampling of sump & discharge water for TSS, temperature, pH, Conductivity, Alkalinity, Nitrate, Sulphate, Metals, Ammonia, Oil & Grease – this sampling is also required to follow ministry procedures to ensure reliability before being sent off to a laboratory for analysis. Flamboro Quarry – Water Monitoring Program June 2010

  8. The Flamboro Quarry does use water as part of its dust suppression strategy during dry periods. • Our water truck has a 7500L capacity. • The truck fills are metered and reported as water taking for dust mitigation. • - The water truck is only used as supplemental dust mitigation during very dry periods (CaCl is applied). Flamboro Quarry – Water Monitoring Program June 2010

  9. Well Monitoring • - Each well is encased in a protective casing which is locked to prevent contamination. • - Well levels are measured using a well probe, which consists of a measuring tape and a probe which sounds an alarm when the water level is reached. • Well levels are measured twice monthly as per PTTW requirements. • The well probe is cleaned between wells – also to prevent contamination. Flamboro Quarry – Water Monitoring Program June 2010

  10. HGRS_Master 09/08/2014